All Experimenters’ Meeting January 09, 2012
Accelerator Operation Summary Calendar Week # 51 NuMI Weekly Integrated Intensity 8.81E18 protons BNB Weekly Integrated Intensity 5.56e18 protons MTest Weekly Integrated Intensity 1.03e14 protons Beam Hours To NuMI hours Beam Hours To MiniBooNE hours From : December 19, 2011 (0000 hours) To: December 26, 2011 (0000 hours)
Accelerator Operation Summary Calendar Week # 52 NuMI Weekly Integrated Intensity 1.00E19 protons BNB Weekly Integrated Intensity 6.15e18 protons MTest Weekly Integrated Intensity 9.81e13 protons Beam Hours To NuMI hours Beam Hours To MiniBooNE hours From : December 26, 2011 (0000 hours) To: January 02, 2012 (0000 hours)
Accelerator Operation Summary Calendar Week # 01 NuMI Weekly Integrated Intensity 9.32E18 protons BNB Weekly Integrated Intensity 5.72e18 protons MTest Weekly Integrated Intensity 2.96e13 protons Beam Hours To NuMI hours Beam Hours To MiniBooNE hours From : January 02, 2012 (0000 hours) To: January 09, 2012 (0000 hours)
Status /Work Completed/Plans Proton Source – Tuning & Studies – Switched to H- Source – Booster RF repairs Main Injector – Tuning & Studies – Kicker & RF maintenance – Abort vacuum valve solenoid NuMI – Running Well – Detector Hall Cooling MiniBooNE – Running Well – MB extraction PS Regulation MTest – T-1019 Done – T-958 Running
Future Access Plan We would like to replace another Solid State Power Amplifier & Modulator in Booster. It will take about 8 hours. The current plan is to install it on January 18 th, (This will be the 5 th pair)