Launch Readiness Review JASMM Virginia Tech Team Members: Robbie Robertson Zack HarlowJeremiah Shiflet Daniel Martin Matt James Anthony Rinaldi Senior.

Slides:



Advertisements
Similar presentations
RockOn! Canister Integration RockOn! 2009.
Advertisements

Building a Pressure/Temperature Weather Station (Sensor Pack) AEM 1905, Fall 2008.
RockSat-C 2012 CoDR Minnesota Sound Wreckers Conceptual Design Review University of Minnesota Alexander Richman Jacob Schultz Justine Topel Will Thorson.
Solar Cell Efficiency Flight Readiness Review Teddy Bounds Angela Dunn Joel Sasser.
Salk Institute Mobile Lab Gel Electrophoresis Teacher Instructions BioRad Set Up 8 groups Grossmont Kit.
Individual Subsystem Testing Report Northwest Nazarene University Advisor: Dr. Lawrence Chad Larson Ben Gordon Seth Leija David Vinson Zach Thomas Drew.
Protocol & Test Review Spaceport America Student Launch University/Institution Team Members Date.
Proposal Analysis Review NMSGC Student Launch University/Institution Team Members Date.
Data Test Review Spaceport America Student Launch University/Institution Team Members Date.
Flight Readiness Review New Mexico Space Grant Consortium University/Institution Team Members Date.
RockSat-C 2012 LRR Launch Readiness Review University/Institution Team Members Date.
DEBUGGING TECHNIQUES. Wiring Type of wire to use Solid core for breadboard Multiple-strand for flying leads and connections to power supply unit (PSU)
Launch Readiness Review SloshSAT University of Northern Colorado Sage Andorka Dan Welsh Maurice Woods III Motoaki Honda Zach Sears 6/11/2010.
RockSat-C 2011 SITR Payload Subsystem Integration and Testing Report University/Institution Team Members Date.
Team R3D3 Final Presentation Devon Campbell Greg McQuie Kate Kennedy Henk Wolda Marisa Antuna Nicole Ela Tyler Smith 12/1/11.
RockSat-C 2011 CDR Virginia Tech RockSat 1 Robbie Robertson Chris Gates Younes Taleb.
Launch Readiness Review Team Name University/Institution Team Members Date.
Launch Readiness Review River Rock 2010 University of Puerto Rico June 9, 2010.
Skillz That Killz Team 3 Conceptual Design Review Travis Dowdy, Jocelyn Mulkey, Hunter Hoopes, Taylor Smith, Kaitlyn Zimmitti, Jess Davidoff September.
Launch Readiness Review MinnSpec University of Minnesota Bryce Schaefer, Chris Woerhle, Art Graf
(Smart Loop System) Installation Guide. Rev B Shipping Box Contains Everything that is included in the box being shipped to a customer should contain.
P13625 – Indoor AIR Quality Monitor
Full Mission Simulation Report New Jersey Space Grant Consortium at Stevens Institute of Technology and Rutgers University Ethan Hayon, Mark Siembab, Mike.
DISSOLVED OXYGEN MONITOR TEAM MEMBERS: ANDREW BEOUGHER ANTHONY SWOPE HAO WANG I-CHUN CHAO BING BAI COLIN HICKS Senior Design Dec1211 Dec1211.
SpectraSonde Assembly. What is the SpectraSonde? Reads temperature, pressure, and humidity data from the atmosphere. The SpectraSonde doesn’t fly like.
The printed circuit board (PCB) design
Title: Corvette C5 Column Lock Bypass Originator: John Neese Date: 30 Jan 2005 Revision: Sheet: 1 of 6 Column Lock Bypass.
Team 14 Joe Grady James Crow Hongyu Chen Prakalp Sudhakar Victor Villagomez Client/Faculty Advisor: Dr. Gary Tuttle.
University of Connecticut Virtual Lab Carl DiFederico, Shane Tobey, Kasim Ward Graduate Student Advisor: Qihang Shi Senior Faculty Advisor: Mohammed Tehranipoor.
Department of Electrical and Computer Engineering Lighting Tool Box Winter 2004 ECE 498 Team Members: Nick Sitarski Blaine Thompson Brandon Harris Dave.
Segway Controller Notes. = connection on top layer of circuit board = connection on bottom layer of circuit board Ground Plane: Areas enclosed by the.
VUCIRO 3 A Balloon Project by: Team Tartive. Group Members Christopher Zanca:  Project Management  Software  Electrical Design Rachael Drella:  Science.
Analog Discovery Arbitrary Function Generator for Windows 7 by Mr
Critical Design Review Team Name University/Institution Team Members Date.
Autonomous Helicopter James LydenEE 496Harris Okazaki.
DISSOLVED OXYGEN MONITOR TEAM MEMBERS: ANDREW BEOUGHER ANTHONY SWOPE HAO WANG I-CHUN CHAO BING BAI COLIN HICKS Senior Design Dec1211 Dec1211.
Simple EL84 Basic layout DIY Paradise 13 June 2003.
RockSat-C 2012 SITR Full Mission Simulation Report Harding University William Waldron, Joshua Griffith, Drew Cancienne, Edmond Wilson, David Stair 22 April.
RockSat-C 2012 SITR Full Mission Simulation Report University of Minnesota Alexander Richman Jacob Schultz Justine Topel Will Thorson 4/23/2012.
Launch Readiness Review
Northwest Nazarene University Chad Larson, Ben Gordon, Seth Leija, David Vinson, Drew Johnson, Zach Thomas June 1 st, 2012.
RockSat-C 2013 FMSTR Full Mission Simulation Report University/Institution Team Members Date.
Section 1: Mission Overview Mission Statement Mission Objectives Section 2: The Payload! User’s Guide Compliance Beta Prototype Testing Section 3: Check-In.
SNO Calibration System The SNO calibration source was designed to deploy sources into both the AV and light water volume between the AV and PSUP.
Rain Detection System for Power Windows in Automobiles
RequirementMethodStatus The payload must not exceed a weight of 1.45 Kgm.Design, Test The payload must conform to the WFF “no volt requirement”
RockSat-C 2012 LRR Launch Readiness Review University of Minnesota Alex Richman, Jacob Schultz, Justine Topel, Will Thorson 5/27/2012.
Section 1: Mission Overview Mission Statement Mission Objectives Expected Results System Modifications Functional Block Diagrams 2.
An introduction to PIC’s for KS3 and KS4. Mr Rooks Hetton School.
Preliminary Design Review Metro State College of Denver Matthew Hanley, Daniel Bass 14 November 2008.
Full Mission Simulation Test Report RocketSat CU Boulder
Multipurpose Keychain ECE 445 Senior Design Junting Lou Yaming Tang Lida Zhu TA: Rajarshi Roy Project No. 11 Fall 2012.
Autonomous Wheelchair Tyler Morton & Ben Hoerst Senior Design Advisor: Dr. Stanislaw Legowski Project Advisor: Dr. Steven Barrett ECE Senior Design.
Moisture Controlled Irrigation System Team Members: ECE - Aaron Beekman, Adrian Fletcher, and Derek Thomas CECS – Jacob Schreiver.
RockOn! RockOn! Structure Build RockOn! 2009.
RamRack Conceptual Design Review Colorado State University Zach Glueckert Christopher Reed Timothy Schneider Brendan Sheridan Christina Watanuki Advisor:
RockSat-C 2013 SITR Payload Subsystem Integration and Testing Report University/Institution Team Members Date.
Introduction to LabVIEW
JASMM Conceptual Design Review
Gel Electrophoresis Teacher Instructions BioRad Set Up 12 groups
Instructor Resources.
Louisiana Tech University
Launch Readiness Review
Launch Readiness Review
Launch Readiness Report West Virginia University
Payload 2015 Class 9 By Jeff Dunker 5/19/ Beginner Payload.
Model Blimp Design Competition Soldering Workshop by Youth College (International) / VTC 09:30 – 11:00 11:00 – 12: May
 Is a machine that is able to take information (input), do some work on (process), and to make new information (output) COMPUTER.
P18250 ‘Smart Buoy’ Phase 7 Customer Update
Instructor Resources.
Presentation transcript:

Launch Readiness Review JASMM Virginia Tech Team Members: Robbie Robertson Zack HarlowJeremiah Shiflet Daniel Martin Matt James Anthony Rinaldi Senior Advisors: Melissa Motylinski Adam Jones Jeff Crayley Sruthi KrishnanMichelle Perez June 9, 2010

User Guide ComplianceFinal PayloadIntegration Update/PlanTesting Results Level Of ReadinessRequired ToolsInspectionsQ/A Type of RestrictionRestrictionStatus Mass allotment: = 10lb (including bottom bulkhead and half of the skin) Within.1lb Volume allotment: = Bottom Half (to 4.5”) The payload’s center of gravity (CG): At the center of our half. x-.078 y-.033 z-.177 Activation met under requirement: (either 1.SYS.1 or 1.SYS.2) 1 Ledex 1 Command Line Structure mounts: Top and bottom bulkheads. No mounts to sides of cans. Sharing: We take half volume and mass and set our CG in our center

We will complete our half first and CU will build their half off of the top of ours. The interface will consist of male threaded rods protruding through our ballast plate from standoffs. We are close enough to the edge of our canister that CU blocking our view out of the window with their lower plate should not be an issue We will be able to make weight/cg adjustments by adding or removing washers from the lower ballast (above or below the bottom plate). User Guide ComplianceFinal PayloadIntegration Update/PlanTesting Results Level Of ReadinessRequired ToolsInspectionsQ/A

Photometric Probe Testing –The A/D conversion has been calibrated and tested A power supply was used to apply various voltages to the inputs pins, and a program was written for the Gumstix computer to continuously output voltages to a putty window The results were correct within.001 V The A/D conversion has been calibrated and tested\ –The probe itself still needs to be tested For this we will use the same Gumstix code and bring the payload to our ECE professor’s lab to be tested with the correct wavelength of light. User Guide ComplianceFinal PayloadIntegration Update/PlanTesting Results Level Of ReadinessRequired ToolsInspectionsQ/A

IMU Testing –A program has been written for the Gumstix computer that outputs the IMU data once every two seconds to a putty window for testing –The current serial data packets returned by the IMU are identical to one another –The signal stops when the IMU is disconnected, so it is not some default signal from the microcontroller on the ASIM interface –We are working on the ASIM code to make this work –If it doesn’t work in time, we will only collect the photometric probe data and maybe rely on our colleagues for inertial data to correlate to our probe data User Guide ComplianceFinal PayloadIntegration Update/PlanTesting Results Level Of ReadinessRequired ToolsInspectionsQ/A

Power System Testing –The latching system works and all components work with the resulting outputs. –This Friday a researcher is returning to our lab who will bypass the g-switch and latching relays on our positive supply to prepare for a command line. –Thursday or Friday (6/10 or 6/11), we will test our new more powerful batteries for 15 minutes and run our individual IMU and probe testing programs to simulate the power requirements of flight –The heat sink on our power supply for the Cubesat computer system gets pretty hot, so we will monitor this during testing, and if it becomes an issue, we will collect data for a shorter period of time before powering off User Guide ComplianceFinal PayloadIntegration Update/PlanTesting Results Level Of ReadinessRequired ToolsInspectionsQ/A

We are not ready. To Do: –Bypass latching circuit and g-switch on one of our two power supplies to prepare for a command line –Run a day in the life power system test –Test photometric probe at optics lab –Complete IMU ASIM code Serial output is constant (not changing with IMU position) –Complete Flight Code Compiler is not working First code will be written only to store Probe Data as a minimal opition –This code is mostly finished, but compilation issues continue –Full day in the life testing User Guide ComplianceFinal PayloadIntegration Update/PlanTesting Results Level Of ReadinessRequired ToolsInspectionsQ/A

Why we aren’t ready: –Because of mistakes early on, the power system had to be redesigned and rebuilt. –Our team started late. –The software was neglected for too long. If the software can be finished in the next couple of days, our chances of finishing in time for reasonable testing are good User Guide ComplianceFinal PayloadIntegration Update/PlanTesting Results Level Of ReadinessRequired ToolsInspectionsQ/A

We have a custom box put together with padding for the payload and labeled bags of extra parts (electronics and hardware) We will bring wrenches, a drill, a soldering iron, screw drivers, a set of hex wrenches, a glue gun, large wrench for the adjustable bottom ballast, wire, shrink tube, and a heat gun. User Guide ComplianceFinal PayloadIntegration Update/PlanTesting Results Level Of ReadinessRequired ToolsInspectionsQ/A

The team members who are attending still need to go through the procedure. If we are able to complete our action items in time, the inspections should be no problem for us. User Guide ComplianceFinal PayloadIntegration Update/PlanTesting Results Level Of ReadinessRequired ToolsInspectionsQ/A

How long will the command line activate before launch? User Guide ComplianceFinal PayloadIntegration Update/PlanTesting Results Level Of ReadinessRequired ToolsInspectionsQ/A