Jess Albino FAC CF April 16, 2007 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities Jess Albino
FAC CF April 16, 2007 Conventional Facilities Major Developments Project Team Status of Construction Construction Schedule 6 Month Look-ahead Summary
Jess Albino FAC CF April 16, 2007 Major Developments Construction Underway Beam Transfer Hall Undulator Hall Tunnel Electron Beam Dump/Front End Enclosure Near Experimental Hall Access Tunnel
Jess Albino FAC CF April 16, 2007 Major Developments – cont’d Relocation of CM/GC Preparation of Laboratory Functionality Strategy Contractor Claim
Jess Albino FAC CF April 16, 2007 PROJECT TEAM Additional Hires in CF CM/GC Personnel Changes ES&H / SME Support Consultants for Quality Control Testing
Jess Albino FAC CF April 16, 2007 CONSTRUCTION
Jess Albino FAC CF April 16, 2007 Beam Transfer Hall (BTH)
Jess Albino FAC CF April 16, 2007 BTH SLAB
Jess Albino FAC CF April 16, 2007 BTH
Jess Albino FAC CF April 16, 2007 UNDULATOR HALL TUNNEL PORTAL
Jess Albino FAC CF April 16, 2007 PRE-DRILLING
Jess Albino FAC CF April 16, 2007 UTILITIES CROSSING BEAM DUMP
Jess Albino FAC CF April 16, 2007 PLACING NEAR HALL SLAB cu. yds
Jess Albino FAC CF April 16, 2007 PLACING SUBBASEMENT FORMS
Jess Albino FAC CF April 16, 2007 STRIPPING SUBBASEMENT FORMS
Jess Albino FAC CF April 16, 2007 ROADHEADER AT THE FACE
Jess Albino FAC CF April 16, 2007 LHD IN ACCESS TUNNEL
Jess Albino FAC CF April 16, 2007 PREPARING TO APPLY SHOTCRETE
Jess Albino FAC CF April 16, 2007 INTO THE HILLSIDE
Jess Albino FAC CF April 16, 2007 ACCESS TUNNEL
Jess Albino FAC CF April 16, 2007 CONSTRUCTION SCHEDULE MARCH 2007 UPDATE BEAM TRANSFER HALL Concrete Work ahead 6 days Excavation at East end subject to Undulator Tunnel late start. UNDULATOR HALL TUNNEL Delayed Start 11 days – late submittals and temporary power ELECTRON BEAM DUMP – Excavation may be delayed by Undulator Tunnel and Utilities
Jess Albino FAC CF April 16, 2007 CONSTRUCTION SCHEDULE MARCH 2007 UPDATE FRONT END ENCLOSURE – Excavation may be delayed by Utilities – partial excavation completed NEAR EXPERIMENTAL HALL – Ahead of schedule 7days X- RAY TUNNEL – No Activity this month FAR EXPERIMENTAL HALL – No Activity this month ACCESS TUNNEL – late start; late submittals and temporary power – approx. 100 ft mined to date
Jess Albino FAC CF April 16, 2007 CONSTRUCTION SCHEDULE MARCH 2007 UPDATE RECOVERY OPTIONS Accelerate Undulator Hall Tunnel Value Engineer Predecessor Activities Begin Second Shift of Mining Value Engineer Excavation / Support Sequence
Jess Albino FAC CF April 16, MONTH LOOK-AHEAD CONSTRUCTION Complete BTH Complete UH tunnel Excavate and Pour Electron Beam Dump Excavate and Pour CUP base slab Excavate and Pour FEE Complete Access Tunnel
Jess Albino FAC CF April 16, MONTH LOOK-AHEAD (cont.) Construction (cont.) Start Excavation of Far Experimental Hall Start Excavation of X-Ray Tunnel
Jess Albino FAC CF April 16, 2007 Summary Construction is underway for all major areas CF staff has been strengthened / tailored for construction phase Contractor Staff Changes Schedule Recovery Plans are in process Continue to Value Engineer Interface with SLAC, Tech. Systems, CM/GC Re-double efforts to support TCCo and Construction to prevent delays – keep to the schedule.
Jess Albino FAC CF April 16, 2007 End of Presentation