Jess Albino FAC CF April 16, 2007 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities Jess.

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES Central Chilled Water Facility – Phase II Alan Raphael MPO Project Manager CFAC Committee Review November 9, 2009 Sub-basement/Pipe.
Advertisements

Jess Albino CF – Breakout Session June 17, Facility Advisory Committee LINAC Coherent Light Source Project Conventional.
David Saenz FAC CF April 20, 06 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities D. Saenz.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science OECM Limited-External Independent.
David Saenz CM/GC April 8, 2005 CM/GC Overview CM/GC Plan & Status Systems Description Cost Estimate Construction Schedule.
1 John Arthur 1 FEH Status CXI Review June 3, 2009 FEH Layout, Status John Arthur – LCLS Expt’l Facilities Div June 3, 2009.
Jess Albino Session 5 Conventional November 11, Facility Advisory Committee LINAC Coherent Light Source Project.
David Saenz FAC CF April 07, 2005 Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule.
Stefan Moeller XES FAC Review – April 16, 2006 X-Ray Endstation Systems (XES) Status Stefan Moeller.
Javier A. Sevilla Interface & Configuration FAC Review April 16, Interface and Configuration Management Outline CF.
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
David Saenz Facility Advisory October 30, 2007 CONVENTIONAL FACILITES MANAGEMENT.
Jess Albino CF Breakout April 16, CONVENTIONAL FACILITIES Project Team CF Changes Electrical Engineer - done Mechanical.
Richard M. Boyce FAC April 16, LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH.
David Saenz Far Experimental Hall - June 17, Far Experimental Hall - Hutches Scope Budget Schedule.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
Jess Albino / David Saenz / Facility Advisory Committee October 30, 2007 FACILITY.
Bob Law FAC Review April 14, 2007 LCLS Conventional Facilities Construction Field Change Orders Bob Law.
1 Jess Albino 1 Conventional Facilities Status FAC Review – Breakout Session CONVENTIONAL FACILITIES STATUS Jess Albino – Associate.
David Saenz FAC CF Oct 12-13, 2004 Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
David Saenz CF Oct 30, CF MEP Commissioning.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
Jess Albino Facility Advisory October 30, 2007 FACILITY ADVISORY COMMITTEE BREAKOUT SESSION 5 TURNER CONTRACT OVERVIEW.
John N. Galayda LCLS FAC October Linac Coherent Light Source Overview and Charge Facility Advisory Committee.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Dick McDonald Risk April 16, LCLS Conventional Facilities Dick McDonald Deputy Systems Manager.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
John N. Galayda LCLS Facility Advisory 29 October 2007 Linac Coherent Light Source Overview 29 October 2007  Project.
Michael Scharfenstein FAC April 7, 2005 LCLS ES&H Process and Documentation.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
David Saenz FAC November 11, 2008 SLAC National Accelerator Laboratory 1 Far Experimental Hutches David Saenz Project Manager.
Mike Scharfenstein FAC Review - November 11, 2008 SLAC National Accelerator Laboratory 1 Environment Safety & Health Status.
Michael Scharfenstein FAC April 16, 2007 LCLS CONSTRUCTION SAFETY Michael Scharfenstein.
John Arthur X-ray April 20, 2006 X-Ray Beamline and Experiment Layout John Arthur LCLS Photon Systems Manager.
David McGiven FAC: Construction Management Procurement October 2006 Facility Advisory Committee (FAC) Construction Management.
David McGiven FAC: Construction April 2006 Facility Advisory Committee (FAC) Construction Procurement David.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
Javier A. Sevilla Interface & Configuration FAC Review October 12, Interface and Configuration Management Outline.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
David Saenz FAC Review CF Design, Cost and Schedule Oct 27, 2005 CF Overview & Status Design Status CMGC Status Latest.
M. Reichanadter LCLS Project November 2008 FAC Meeting Slac National Accelerator Laboratory Report to the LCLS.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
David Saenz EIR Review Oct 9-11, Conventional Facilities (CF) WBS 1.9 ETC and Methodology David Saenz CF Systems Manager.
Miller Driscoll Building Committee Construction Update Thursday April 7, :00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions & Alterations.
Experimental Facilities Planning
CF Organization & Schedule
Meeting of the LCLS Facilities Advisory Committee
CONVENTIONAL FACILITIES STATUS
CONVENTIONAL FACILITIES LCLS Office Space
Department Of Energy Review LINAC Coherent Light Source Project
Details supporting the increase
Project Management Issues John N. Galayda, SLAC April 24, 2002
Conventional Facilities WBS 1.9
Integrated Safety and Environmental Management
Conventional Facilities Status
Shutdown Planning & Installation Schedule
CONVENTIONAL FACILITIES
Installation Status & Operational Readiness Process
Department Of Energy Review Linac Coherent Light Source Project
Conventional Facilities
Phase 1 Statement of Work Preconstruction “Plan The Work”
CF Scope, Management & Organization
CMGC Overview SLAC Site Plan Systems Description Construction Schedule
Presentation transcript:

Jess Albino FAC CF April 16, 2007 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities Jess Albino

FAC CF April 16, 2007 Conventional Facilities Major Developments Project Team Status of Construction Construction Schedule 6 Month Look-ahead Summary

Jess Albino FAC CF April 16, 2007 Major Developments Construction Underway Beam Transfer Hall Undulator Hall Tunnel Electron Beam Dump/Front End Enclosure Near Experimental Hall Access Tunnel

Jess Albino FAC CF April 16, 2007 Major Developments – cont’d Relocation of CM/GC Preparation of Laboratory Functionality Strategy Contractor Claim

Jess Albino FAC CF April 16, 2007 PROJECT TEAM Additional Hires in CF CM/GC Personnel Changes ES&H / SME Support Consultants for Quality Control Testing

Jess Albino FAC CF April 16, 2007 CONSTRUCTION

Jess Albino FAC CF April 16, 2007 Beam Transfer Hall (BTH)

Jess Albino FAC CF April 16, 2007 BTH SLAB

Jess Albino FAC CF April 16, 2007 BTH

Jess Albino FAC CF April 16, 2007 UNDULATOR HALL TUNNEL PORTAL

Jess Albino FAC CF April 16, 2007 PRE-DRILLING

Jess Albino FAC CF April 16, 2007 UTILITIES CROSSING BEAM DUMP

Jess Albino FAC CF April 16, 2007 PLACING NEAR HALL SLAB cu. yds

Jess Albino FAC CF April 16, 2007 PLACING SUBBASEMENT FORMS

Jess Albino FAC CF April 16, 2007 STRIPPING SUBBASEMENT FORMS

Jess Albino FAC CF April 16, 2007 ROADHEADER AT THE FACE

Jess Albino FAC CF April 16, 2007 LHD IN ACCESS TUNNEL

Jess Albino FAC CF April 16, 2007 PREPARING TO APPLY SHOTCRETE

Jess Albino FAC CF April 16, 2007 INTO THE HILLSIDE

Jess Albino FAC CF April 16, 2007 ACCESS TUNNEL

Jess Albino FAC CF April 16, 2007 CONSTRUCTION SCHEDULE MARCH 2007 UPDATE BEAM TRANSFER HALL Concrete Work ahead 6 days Excavation at East end subject to Undulator Tunnel late start. UNDULATOR HALL TUNNEL Delayed Start 11 days – late submittals and temporary power ELECTRON BEAM DUMP – Excavation may be delayed by Undulator Tunnel and Utilities

Jess Albino FAC CF April 16, 2007 CONSTRUCTION SCHEDULE MARCH 2007 UPDATE FRONT END ENCLOSURE – Excavation may be delayed by Utilities – partial excavation completed NEAR EXPERIMENTAL HALL – Ahead of schedule 7days X- RAY TUNNEL – No Activity this month FAR EXPERIMENTAL HALL – No Activity this month ACCESS TUNNEL – late start; late submittals and temporary power – approx. 100 ft mined to date

Jess Albino FAC CF April 16, 2007 CONSTRUCTION SCHEDULE MARCH 2007 UPDATE RECOVERY OPTIONS Accelerate Undulator Hall Tunnel Value Engineer Predecessor Activities Begin Second Shift of Mining Value Engineer Excavation / Support Sequence

Jess Albino FAC CF April 16, MONTH LOOK-AHEAD CONSTRUCTION Complete BTH Complete UH tunnel Excavate and Pour Electron Beam Dump Excavate and Pour CUP base slab Excavate and Pour FEE Complete Access Tunnel

Jess Albino FAC CF April 16, MONTH LOOK-AHEAD (cont.) Construction (cont.) Start Excavation of Far Experimental Hall Start Excavation of X-Ray Tunnel

Jess Albino FAC CF April 16, 2007 Summary Construction is underway for all major areas CF staff has been strengthened / tailored for construction phase Contractor Staff Changes Schedule Recovery Plans are in process Continue to Value Engineer Interface with SLAC, Tech. Systems, CM/GC Re-double efforts to support TCCo and Construction to prevent delays – keep to the schedule.

Jess Albino FAC CF April 16, 2007 End of Presentation