8.7.04TRD Status meeting HdClemens Adler TRD ROC Status
8.7.04TRD Status meeting HdClemens Adler Production Status L1C1 Material arrived last week Glued 3 L1C1 Frames last week 1 L1C0 Frame finished Started wiring this week (Meteor switched off for last 8 cm) Try to keep up production rate of 2 Chambers per week (probably not sustainable, due to holidays)
8.7.04TRD Status meeting HdClemens Adler Production Problems „Warping of Padplane panel assembly disapears when supported on all sides Wire tension measuring machine (prototype): –Very sensitve. –Position accuracy not to spec. – has problems finding all wires Holger: most problems will be soved with the“ real“ machines.
8.7.04TRD Status meeting HdClemens Adler Chamber Status Finished: 3 x L1C0 (1 glued, 2 taped waiting to be tested) 3 x L2C0 (3 taped) 2 x L1C1 (mid next week)
8.7.04TRD Status meeting HdClemens Adler Dead Pads David measured connection of cables on one glued panel: –2 Channels were not connected Need to measure all panels? (very time consuming)
8.7.04TRD Status meeting HdClemens Adler Material Status: L-Profiles L1C1 in Production Next: L2C1,L3C1 Quality is very good now after some opimization. Rate: ~4/week (average)
8.7.04TRD Status meeting HdClemens Adler Material Status: Front Profiles L4 in Production Production rate: ~9/week
8.7.04TRD Status meeting HdClemens Adler Material Status: Padplanes L2C0: broken traces are repaired by Optiprint Arrived: L1C1, L5C1, L5C0, (L6C0) At CERN: L3C0, L4C0 Next: L2C1 Missing: L3C1, L4C1 Optiprint has to reorder base FR4 -> only 0.38 mm thickness available (instead of 0.36).
8.7.04TRD Status meeting HdClemens Adler Material Status: Fischer Panels Production will be finished in KW30. Missing: L2C1, L3C1.
8.7.04TRD Status meeting HdClemens Adler Chamber type distribution Original plan ( ): -Bukarest: L1C1, L2C1 -GSI:L3C1, L5C1 -Hd:L4C1, L6C1 (skipped-> L1C1) New proposal: -Hd: L1C1, ??? (L6C1,L0C1,++) - GSI: L5C1, L4C1 (last Padplane type) - BukarestL2C1, L3C1 - Dubna:LxC0
8.7.04TRD Status meeting HdClemens Adler HD Test Room Gas lines are in place, first leak rate measurements (but Oxygen sensor problem). Currently: bad CO2 X-Ray tube waiting for appoval by Gewerbeaufsichts- amt. X-Y-test stand is ready.