G RotoBreak Cassette Assembly Station Optimization By Randy Greenberg SMA Due Date: 12/14/99.

Slides:



Advertisements
Similar presentations
Automatic Transfer Switch (ATS)
Advertisements

Source Driver Status CMS Week November 2007 P. Debbins University of Iowa.
Motor Starter Coordination
Meritor Clearance Sensing Automatic Slack Adjusters
©2011, The McGraw-Hill Companies, Inc. Chapter 4.
ACADs (08-006) Covered Keywords Switchgear, motor control, ground, circuit breaker. Description Supporting Material
Arrowhead  Weston Transmission Line Project Dave Van House Minnesota Power.
Your Dissertation. Getting started  What current third years wish they’d done  The role of the supervisor  Your responsibilities  Provisional key.
Project Management 30 January. Odds and ends Tournament on the webweb In the newsnews.
MODELING AND ANALYSIS OF MANUFACTURING SYSTEMS Session 6 SCHEDULING E
Rapid Prototyping Cell Simulation Peter Bayer SMA12/21/2000.
Project : Man Utilization FMS Cell Unit 1104 DSES 6620 Spring 2002 William Harris.
Program Flow Charting How to tackle the beginning stage a program design.
Jai Hind Cycles, Inc. Manufacturing Simulation Using ProModel Daniel Ball and Debbie Leach Fall 2000.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
Status of the Tracker DB System Tk week april 03 D. Contardo Developments Applications.
GLAST LAT Project November 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
Scheduling PREREQUISITES FOR EFFECTIVE SCHEDULING.
SCHEDULING A FLEXIBLE MANUFACTURING SYSTEM WITH TOOLING CONSTRAINT: AN ACTUAL CASE STUDY presented by Ağcagül YILMAZ.
Department of Industrial and Engineering Technology College of Science and Technology Morehead State University IET 317 Group 5 Project Group Members:
Electro-Pneumatics Module 1
Lab #5 Overview Activity #1 - Simulation of an Op-Amp inverting amplifier Activity #2 - Build and Test the Op-Amp inverting amplifier Activity #3 - Determining.
Engineering H193 - Team Project Gateway Engineering Education Coalition P. 1Spring Quarter Project Management Week 2 Day 2.
Discrete Event Simulation in Automotive Final Process System Vishvas Patel John Ma Throughput Analysis & Simulations General Motors 1999 Centerpoint Parkway.
CROPIA Project IIE ANNUAL CONFERENCE & EXPO forums.pmcorp.com NEW! Project Scope Evaluated (by on-site observations and intervention)
Chapter 4 Process Design.
Transportation & Traction Power Programs
Senior Design, Spring 2013 Jane Peters Riley Groves Jared Jasper Matt Murphy Muzi Li.
MBA 513 Applied Business Models. MBA 513 Applied Business Models Operations Management.
Deliverables out of Scope  Mrs. Creed – Client  Ryan Rutger – CTE Student Liaison  Dr. Karen Patten- Sponsor Key Stakeholders The University of South.
11DSCI4743 Capacity Management Capacity management is planning & controlling resources needed to meet production objectives –Planning: determining resources.
1 A Fundamental Principle of TPS Produce to Demand 1.Make only what is needed when it is needed. 2.Base production and planning on Takt Time. 3.Develop.
Managing Processes and Capabilities CHAPTER THREE.
Differential for Formula SAE Race Car
* * Chapter Nine Production And Operations Management Copyright © 2010 by The McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin.
Final Demonstration Team 2A The Charles Machine Works Downhole Generator Project.
Flow Rate and Capacity Analysis
Toshiba : Ome Works Group 7.
Presented By Dr. Mohsen Alardhi College of Technological Studies, Kuwait April 19 th,2009.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Products and Services Operations Management Chapters 4&5 Roberta.
Bonitron A\C Demand Scheduler Alex Brown Cory Haugh Ajmer Dwivedi.
CAPACITY MANAGEMENT Nyoman Pujawan.
NCSX Field Period Assembly (FPA) Operations, Cost and schedule, staffing, and metrology utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
0 Asset Inventory and Reconciliation Mike Melton.
Project Title sponsored by: ABC Designs, Inc team members: name 1 name 2 etc.
Working Hours Utilities. An easy to use tool that helps maintain your company resources (setup working hours for users, update when facilities and equipment.
MOSC Meeting Operations Market Manual updates October 22, 2003 Presented by:Ron Falsetti Steve Cooper.
FSAE Engine Management System Adolfo Pereira Donald Zucaro Lee McDade Jeremy Belge Sun-Jet Liu Marcin Trelinski Advisor: Dr. Alan Nye Sponsor: FSAE Formula.
SYNERGY INSTITUTE OF ENGINEERING AND TECHNOLOGY
P10203 LV1 MOTOR CONTROLLER FINAL REVIEW MAY 14, 2010 Electrical: Kory Williams, Adam Gillon, Oladipo Tokunboh Mechanical: Louis Shogry, Andrew Krall.
We started last December: 32 channels prototype “Julich like” to:
Simulation.
Headlamps Assembly Loop for Ford Aero Headlights
Training Module OEE 1.
Receptacle Classifications
Material Requirements Planning and Enterprise Resource Planning
Introduction to Materials Management
Chapter 7 Capacity Planning and Management
More about DesignWorks
“Changes in Altitude” SMCC Payload Design and Data Collection.
EET 323 – Electrical System Design Lecture 4: Wiring Devices
LF856 2½”-10”.
Installation Binder / IRR – an example
MECH 3550 : Simulation & Visualization
856 2½”-10”.
Model 4-2: The Enhanced Electronic Assembly and Test System
Benefits & Advantages of Pogo Pins
Model 4-2: The Enhanced Electronic Assembly and Test System
Limited Resources Concept
Capacity Management Capacity management is planning & controlling resources needed to meet production objectives Planning: determining resources needed.
Presentation transcript:

g RotoBreak Cassette Assembly Station Optimization By Randy Greenberg SMA Due Date: 12/14/99

g RotoBreak Objectives: Produce 1000 cassette assemblies per week for each of 3 worldwide locations Use common processes and procedures for interchangeability 40 hour work week 75% location utilization

g RotoBreak Measure of success: 1000 units per week Maintain 40 hour shift 75% location utilization

g RotoBreak Schedule: Data collection 11/01/99 Working model with recommendations 12/7/99 Validation of model 2/15/00 Revision to model 3/15/00

g RotoBreak Product description:  Cassette module used in circuit breaker to make and break the circuit  Key components are: 1.Cassette housing 2.Rotor 3.Contact arm 4.contacts 5.Straps 6.Springs 7.Pins 8.Arc chute 9.Ablative material 10.Links

g RotoBreak Simulation layout Work area breakdown Welding   Line and load strap T(59,63,72)   Contact arm welder T(95,110,130) Staking  Second link to contact arm T(40,50,61) Molding  Cassette Deflasher T(310,345,400) Arc chute assembly  Arc chute T(57,64,75) Assembly  Rotor assy T(65,71,82)  Strap to cassette T(67,71,90)  Arc chute insulation and rotor to cassette T(95,105,110)

g RotoBreak Initial Layout

g RotoBreak Results-first run 383 units output Run for 37.5 hours deflash bottleneck Double number of deflash stations

g RotoBreak Initial run output

g RotoBreak Results-First modification 766 units output Deflash still bottleneck Add third station

g RotoBreak First modification run

g RotoBreak Results-Second modification Output 1000 units Strap to cassette utilization only 65% Combine ablative material with strap to cassette location Transfer 20 seconds to this station

g RotoBreak Second Modification output

g RotoBreak Final results Utilization greater than 75% combine rotor and second link to contact arm staker

g RotoBreak Final Results

g RotoBreak Conclusion Capable of meeting goal of 1000 units per week Need to add two additional deflash stations Combine rotor and second link to contact arm staker operations