TARGET WORKSHOP – SHEFFIELD HALLAM UNIVERSITY Monday 2 March 2009 The ISIS – MICE interface Eddie McCarron Contents 1.Target alignment with ISIS beam centre.

Slides:



Advertisements
Similar presentations
MICE MICE Target Mechanism Paul Smith University of Sheffield 8 th June 2010 (Based upon talk given by Chris Booth at CM26)
Advertisements

1 AFSWG Mtg 15 Aug 2003 Elwyn Baynham RAL Safety Overview Work done by RAL Group Contributors Elwyn Baynham Tom Bradshaw Iouri Ivaniouchenkov.
K. Long, 18 April, 2015 Beam-line status — red sky at night?
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
TPC meeting, NBI, 2-3 September 2002Børge Svane Nielsen, NBI1 Status of laser system TPC meeting, Copenhagen, 2-3 September 2002 Børge Svane Nielsen, Jørn.
The MICE Target Lara Howlett University of Sheffield.
Target Status Report Lara Howlett University of Sheffield.
MICE TARGET HARDWARE C. Booth, P. Hodgson, R. Nicholson, P. J. Smith, Dept. of Physics & Astronomy University of Sheffield, England. 1 - The MICE Experiment.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
G.Barber Tracker Planning & Mechanical Preparation June Tracker Planning & Mechanical Preparation An outline of (known) outstanding work to be carried.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
MICE Target Schedule Chris Booth Sheffield 12 th June 2006.
Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009.
March 2003 Paul Drumm MICE Collaboration Meeting, CERN 1 Beam Line & Installation Plans Paul Drumm CLRC Rutherford Appleton Laboratory.
Global Design Effort Detector concept # Plenary introductory talk IRENG07 Name September 17, 2007.
P J SmithUniversity of Sheffield1 MICE Target Electronics Paul J Smith University of Sheffield Fermilab 10 th June 2006.
MICE Target Status Chris Booth Sheffield 10 th May 2006.
M. apollonioAccel. R&D/Physics and IADR - RAL - 19/3/ Magnets Dry Run ISIS Scheduling Meeting Latest news on Target Ready to run ? Summary of: Magnets.
TARGET WORKSHOP – IMPERIAL COLLEGE LONDON Friday 8 May 2009 The ISIS – MICE interface Eddie McCarron Contents 1.Vessel mods. 2.TC performance. 3.Wiring.
Target Update – Mico Meeting Monday 21 st April 2008 General Expect to obtain new coils for stators anytime New Shafts at RAL for metrology. Will be back.
MICE Collaboration Meeting March 29 - April 1, CERN MICE Integration Edgar Black/IIT March Room.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
MICE Target Review Chris Booth Sheffield 12 th June 2006.
A Tale of Two Targets … 7 th September 2009 Chris Booth The University of Sheffield.
Target Assembly and Installation Update 20 th August 2009 Paul Hodgson The University of Sheffield.
MICE TARGET WORKSHOP – SHEFFIELD 2 nd December Target vibration and general design issues 2. Simple Vibration - causes and forces. 3. Not so simple.
MICE Alignment and Support Structure Tony Jones and Yury Ivanyushenkov Engineering Department RAL.
T. Montagne LTU – Beam Dump Installation April 16, LTU and Beam Dump Installation April 16, 2007.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
Assembly, Installation and Interfaces Steve Virostek Lawrence Berkeley National Lab RFCC Module Design Review October 21, 2008.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
F.E.T.S. Mechanical Engineering Update by P. Savage 13 th August 2008.
MICE Target Mechanical Design l Contents »Status of modelling and drawing »Work being undertaken at RAL on shaft and bearing prototypes »Procedure for.
Chris BoothMICE-UK I.C. 16th January Useful meeting held at RAL last Thursday. Representatives of MICE, ISIS & others with Sheffield electronic &
1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College.
Quick Changeover Basics This material is provided by Industrial Solutions, Inc. and is intended for internal use only. Any reproduction or re-use outside.
MICE Target – Design Update and Test Plans Chris Booth Sheffield 22 nd October 2005.
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
MICE Target - Risk Lara Howlett University of Sheffield.
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
Target Status Target installed in ISIS “Demonstrator” target in R78 Chris Booth Sheffield 7 th February 2008.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
1 Target Station Design Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory EuroNu Annual Meeting 2012.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
Jason Tarrant / November 2008 MICE Target Mechanical Design l Jason Tarrant – STFC l Introduction »Investigations into target shaft failure »Current suspicions.
LAV construction: Status and overview Matthew Moulson (Frascati) for the LAV Working Group NA62 Photon-Veto Working Group Meeting Brussels, 8 September.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
G.Barber Mice Tracker Mechanical Progress Tracker Mechanical Progress Contents:- Station Space Frame Station Layout Light Guide Map Connectors Patch.
G.Barber Mice Tracker Integration Harbin Jan Mice Tracker Integration Installation requirements & Procedure.
Pepperpot Emittance Measurement System: Current Status Simon Jolly Imperial College FETS Meeting, 10/05/06.
Chris Booth & Paul Smith Sheffield 16 th August 2007 MICE Target Installation.
CEDAR MECHANICS Liverpool Conceptual Design (Subject to funding from STFC) 1 CEDAR Mechanics Conceptual Design.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
K.Long/G.Barber Mice Tracker Mechanical Status CM20 Feb 08 1 Mice Tracker Mechanical Status Contents:- Tracker 1 Status Tracker 2 Status Further Hardware.
Radiation Shutter Re-Purposing Roy Preece STFC RAL 18 th December 2014.
Tutorial On Fiducialization Of Accelerator Magnets And Undulators
Chris Booth Sheffield 29th March 2006
Stator Plan & Schedule Chris Booth 2nd March 2009
Target Installation Plan
MICE Target Mechanical Design
MICE Target Report Video Conference 29/11/07
PSS0 Design & Concept of Operations
as a prototype for Super c-tau factory
Presentation transcript:

TARGET WORKSHOP – SHEFFIELD HALLAM UNIVERSITY Monday 2 March 2009 The ISIS – MICE interface Eddie McCarron Contents 1.Target alignment with ISIS beam centre line. 2.Target redesign and QA. 3.MICE M113 vessel mods. 4.MICE target removal/installation mods. 5.Actions and aims 1

Transferring beam datum from ISIS to MICE target The beam centre cannot be measured directly. The synchrotron parts are aligned with Taylor-Hobson (TH) datum balls from a fixed grid system in the synchrotron hall. Each part has two TH reference points that are pre aligned with a pair of rails. Taylor-Hobson cup. For dipole. Fixed grid reference tower. The TH points for the MICE vessel are mounted on removable jigs that sit on the flange dowels at either end of the vessel. 2

Target tip is not directly referenced to the synchrotron TH system. The target tip must be referenced to the trial assembly rig in R78 then transferred to the synchrotron to obtain relationship between target tip and beam centre line. 3

Procedure for calibrating the target tip to beam centre line. 1.The telescope is set up to view at a known offset parallel to the beam centre line. 2.The target is driven to a known position by the solenoid. 3.The telescope is moved to view the tip of Target. 4.The mechanical off set is recorded and logged with the reading from the solenoid drive software. 5.The target tip is now calibrated to the vessel dowels. This setting is now transferable to the synchrotron. 4

Target shaft redesign It is clear that the vulnerable parts of the target assembly are the target shaft and the driving coils and both their problems are dominated by F = ma. For the coils to produce ‘F’ they need ‘I^2’. I presume we have minimised ‘a’ and are taking steps to minimise ‘m’. Minimising the gap between the target shaft magnets and the coils would reduce the magnetic field necessary to generate ‘F’ (therefore reducing ‘I^2’). I don’t think this has been addressed. It is also clear that there is a vibration problem. The vibrations are proportional to the acceleration, second moment of area, length and the Young’s modulus of the target shaft. I believe each of these has been addressed. Target assembly Quality Assurance (QA) Following the note* about QA issued 22 May There have been some steps towards fully controlling the Target assembly production to QA methods so that reliable and repeatable assemblies can be installed. It is now time to audit these procedures. To ensure that all our stages are specification driven, inspected, and documented I suggest that an independent QA auditor is consulted. Perhaps SSTD at RAL have someone we can borrow for a day or two. * ‘MICE Target Mechanical Acceptance criteria’ 22 May 2006 attached for reference. 5

6

7 Mods to MICE vessel M113 in synchrotron The melting of the target tip endangered the observation window below the target. The window will be moved. A thermocouple will be added to a new VAT isolation valve so the target tip temperature can be monitored. Thermocouple enters here New ISIS pumping port and valve. Beam directionMoved observation windowLighting window

8 TC through Swagelok Mirror Pyrex ceiling Thermal radiation collector on end of TC Swagelok welded into valve by VAT Details of M113 vessel of mods of 9

9 Removal/Installation mods ISIS remove excess grease ISIS instal shim to protect optics from oil. Sheffield to pass all cables through these holes to aid cable safety. All cables to be have pucker labels. Avoid routing cables around these edges. (Or they will be trapped In transport casket). Target assembly partly dismantled in R5.2 after removal from Synchrotron.

10 Actions and aims 1.EM to progress vessel mods for delivery by May Sheffield to provide in-line or quick release connectors to parts on Target assembly to ensure efficient Target installation in synchrotron. 3.Sheffield to route cables through target assembly plate to avoid crushing cables in lead casket transport. 4. Sheffield to use pucker cable labels. 5. Plan acceptance trials for R Appoint a QA auditor (internal or external). of 9