John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements.

Slides:



Advertisements
Similar presentations
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Advertisements

FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science OECM Limited-External Independent.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
1 John Arthur 1 FEH Status CXI Review June 3, 2009 FEH Layout, Status John Arthur – LCLS Expt’l Facilities Div June 3, 2009.
Stefan Moeller XES FAC Review – April 16, 2006 X-Ray Endstation Systems (XES) Status Stefan Moeller.
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
Stefan Moeller Revised XES April 7, 2005 Revised X-Ray Endstation Scope Stefan Moeller.
1 Stefan Moeller 1 AMO Instrument Schedule ARR AMO Instrument Schedule Stefan Moeller – XES Manager June 30, 2009.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
John N. Galayda LCLS Commissioning 22 September 2004 Welcome/Charge Welcome to the Workshop LCLS Status Since the January.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
M. White – June 28, 2004 LCLS Requirements Meeting In a project, we live or die by the schedule. After we’re “baselined” it is our plan for what we will.
John Arthur Photon October 18, 2005 LCLS Photon Systems Status John Arthur SLAC.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
John Arthur Photon October 27, Photon Systems Overview John Arthur SLAC.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
Sasha GilevichFacilities Advisory Committee October Injector Drive Laser Update 1 Facilities Advisory Committee Meeting.
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
John N. Galayda LCLS FAC October Linac Coherent Light Source Overview and Charge Facility Advisory Committee.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
John Arthur Photon April 20, 2006 Photon Systems Update John Arthur SLAC Photon Systems Manager.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
John N. Galayda LCLS Facility Advisory 29 October 2007 Linac Coherent Light Source Overview 29 October 2007  Project.
John Arthur X-Ray Endstation April 29, 2004 X-Ray Endstations Overview John Arthur.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Opening Comments and Charge 19 January 2004 Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear.
John Arthur PIXEL Project April 7, 2005 Status of the Proposed PIXEL Project John Arthur SSRL/SLAC Photon Instrumentation.
1 Low-energy RHIC electron Cooler (LEReC) Update November 17, 2014.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
Undulator System Review Closeout Erik Johnson, Kem Robinson, Dieter Walz 4 March 2004.
John Arthur X-ray April 20, 2006 X-Ray Beamline and Experiment Layout John Arthur LCLS Photon Systems Manager.
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
LCLS Undulator Systems TDR Charge Linac Coherent Light Source Stanford Linear Accelerator Center Technical Review, March 3, 2004.
David H. Dowell RF Gun Commissioning LCLS FAC April 16, RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.
Stefan Moeller XES Plan for FAC Review - April 20, 2006 X-Ray Endstation Systems (XES) Status and Plan for FY06 Stefan Moeller.
David H. Dowell Injector Physics/Diagnostics/Gun&L0 RF April 29-30, 2004 Injector Physics / Diagnostics / Gun & L0 Linac.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
M. Reichanadter LCLS Project November 2008 FAC Meeting Slac National Accelerator Laboratory Report to the LCLS.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
LCLS-II Project Overview David Schultz LCLS-II Deputy Project Director March 19, 2012.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
SuperB Injection, RF stations, Vibration and Operations
Injector Performance Requirements Conventional Facilities Update
LCLS Injector: Introduction D. H
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
WBS 5.0 LCLS Strategic Projects Division
John N. Galayda – Director of LCLS Construction March 30, 2009
Electron Beam Systems ETC and Methodology
X-Ray Endstations Update
Details supporting the increase
Project Management Issues John N. Galayda, SLAC April 24, 2002
LCLS Injector System Overview D. H
Linac Coherent Light Source Project Update
Department Of Energy Review Linac Coherent Light Source Project
X-Ray Endstation Design & Management/Commissioning
Electron Beam Systems ETC and Methodology
Injector Physics C. Limborg-Deprey, D. Dowell ,Z. Li. ,H. Loos, J
CF Scope, Management & Organization
X-Ray Endstation Systems (XES) 2006 Schedule
Injector/Linac RF Status
LCLS Photon Systems Overview
Presentation transcript:

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Linac Coherent Light Source Project Update Recent progress Enhancements of capability Conventional facilities cost

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Linac Coherent Light Source 1.1 Management, Global Controls 1.2 Injector 1.3 Linac 1.3 e-Beam Transport 1.4 Undulator Near Experiment Hall Far Experiment Hall ( underground) 1.5 X-Ray Transport/Optics/Diagnostics 1.6 Endstation Systems 1.9 Conventional Facilities

John N. Galayda LCLS Facility Advisory Committee 27 October 2005

John N. Galayda LCLS Facility Advisory Committee 27 October Injector RF Gun Load Lock Transverse RF Cavity Laser Heater DL1 Bend Straight Ahead Spectrometer L0-1 & L0-2 3-m SLAC Sections Gun Diagnostics 10/2005 Shutdown -Laser transport tubes -RF waveguide to injector Gun fabrication in process

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 LCLS RF Gun Fab. In SLAC Klystron Dept. Courtesy L.Xiao Dual Feed Suppresses the time dependent dipole kick Matching phase for 2 feeds by holding mechanical tolerances on both arms Z-coupling (instead of  -coupling) Pulsed heating reduced + easier machining Racetrack shape compensates for stronger quadrupole mode Overcoupling  =2 15 MHz mode separation adopted Push-Pull deformable tuners Replace plungers Shaping of RF pulse for reducing average power 4kW -> 1.8 kW ; cooling channels designed for handling 4kW Reduce reflected power from gun Gun fabricated at SLAC RF design complete Mechanical model in progress 120Hz heat calculations under way LCLS-TN-05-3.pdf L. Xiao, et al., “Dual feed RF gun for the LCLS”, SLAC-PUB-11213, May 2005, ; to be published in the proceedings of the 2005 Particle Accelerator Conference, May 2005, Knoxville, TN; also to be published at the Joint Accelerator Conference Website ( )

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Injector Laser Chosen - Thales Delivery expected in May LLNL (Brent Stuart, et al.) Studying temporal pulse shaping ANL ( Yuelin Lee) Studying transverse pulse shaping Bill White, LCLS Laser Group Leader Group will support facility lasers

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Architecture Thales Laser System 1.5mx3.75m footprint (~4.5’x11.5’) Spectra Physics MILLENIA Vs Femtolasers Oscillator Femtosource Scientific 20s (chirped mirrors) JEDI #1 100 mJ,120 Hz JEDI #2 100 mJ,120 Hz Amplifier 2-pass Bowtie CompressorTHG Pre-Amp 4-pass Bowtie RGA Regen Amp StretcherDAZZLER 20 mJ, 120 Hz 80 mJ, 120 Hz 100 mJ, 120 Hz 119MHz 400mW 5W, 119MHZ 150ps 80mW 119MHz 1mJ, 120Hz >20mJ, 120Hz >40mJ, 120Hz >25mJ, 120Hz>2.5mJ, 120Hz To cathode Amplifiers are not cryo-cooled IR stability <1%rms (short term)

John N. Galayda LCLS Facility Advisory Committee 27 October Linac LCLS Klystron Injector Quad BC-1 Dipoles Fab Complete first article ordered measured

John N. Galayda LCLS Facility Advisory Committee 27 October Undulator Systems Progress, Changes Magnet BlocksAwarded Magnet Poles Awarded StrongbackAwarded Assembly, first articlesAwarded Undulator Measurement Lab designed RFP issued for room On track for complete delivery of undulators by June 2007 Design Changes Electromagnet quadrupoles Aluminum surface in undulator vacuum chamber Fixed supports in ANL scope Planning production prototype tests Shim incorporated in undulator design – permits K reduction (significant shutdown required)

John N. Galayda LCLS Facility Advisory Committee 27 October 2005

John N. Galayda LCLS Facility Advisory Committee 27 October Baby Pictures (cont’d) Magnetized blocks Magnet Poles

John N. Galayda LCLS Facility Advisory Committee 27 October Conventional Facilities Sector 20 Injector Magnet Meas. 2/28/06 Completion

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 FFTB Shielding Sector 24 Stairs

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Next Steps Construction manager Cost estimate Construct road? Construct tunneling portal? Plan FFTB decommissioning Date will be between April and June

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 ~30m GAS ATTEN SOLID ATTEN STOP COLLIM Offset Mirrors STOP 1.5 New layout of FEE Incorporates Offset Mirrors 7 ft Fe 3 ft concrete 4 ft Fe

John N. Galayda LCLS Facility Advisory Committee 27 October XES instrumentation effort Old Plan: XES to build a generic set of instrument components (infrastructure PPS, MPS, network) New Plan: XES builds one instrument for soft x-ray Atomic Physics studies Experiment infrastructure, laser, chambers, PPS Pixel array detector spec’ed for cluster imaging

John N. Galayda LCLS Facility Advisory Committee 27 October Since the Last Review Scope modifications Soft X-Ray Atomic Physics Experiment Deletion of generic optics Re-program to functional near hall station Pixel Array Detector Specs address single molecule imaging

John N. Galayda LCLS Facility Advisory Committee 27 October ft tunnel 30ft transition 46ft tunnel 212ft 28x33ft hutch 29x33ft hutch 36x33ft hutch 10ft passage below beam pipe Fire door 10ft 6ft Toilets Future tunnel to other stations Entrance 14ft tunnel Sliding hutch door 15x25ft control cabin 1.9 New FEH design in baseline

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Recent Events SSRL User Meeting, 17 October 2005 Pat Dehmer presentation, 2007 Budget LCLS has high priority, high visibility, high likelihood of full funding BES must get funding above its “line” to do LCLS without shutting down some facilities BES is prepared to do this for LCLS IF we are ready

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Wouldn’t Be a Project Without Some Challenges… Conventional Facilities High bids Sector 20, Magnet Measurement Facility, Construction Management Jacobs Title-II (30%) estimate for future work is 50% above Title-I Electrical, Mechanical disciplines are 100% above Title-I Jacobs expects increased escalation

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 De-Scopes Undulator Hall A/C redesign ~$3.5M savings Other CF Economies - $ 7.5M Still looking for $5M further CF reductions might yield $1M-$2M Flipping Mirrors - $2M More to go, emphasis on: Reversible No impact on commissioning and early operation

John N. Galayda LCLS Facility Advisory Committee 27 October nd Undulator Line 3 rd Undulator Line Near Expt. Hall XR tunnel shortened from 250m to 230m

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Central Lab Office Complex (CLOC) Capacity >260 78,000 GSF Total 150-Seat Conference Room Leave 3 rd floor unfinished Delete 3 rd floor?

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Continuing Resolution No slowdown unless CR extends past December CF, undulator assembly must go forward to stay on schedule Will ask for help.

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Response to Comments/Recommendations Members of the FAC had minor concerns about the organization chart as having a baroque appearance in that on the surface, lines of authority don’t appear to be that clear. However, throughout the course of the FAC meeting clear lines of responsibility and authority were in evidence and only a few issues on communication (notably between the physics requirements on the conventional facilities and the operations configurations and approaches) were apparent. Response: The LCLS organization chart has been revised to clarify roles and responsibilities.

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 LCLS Project Organization (Sep05)

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 The project should incorporate those risk or trade-off items identified in this and previous FAC meetings into the Project Risk Registry to ensure adequate tracking and resolution. The project may wish to also incorporate any such risk items cited in official DOE reviews as well. Response: The LCLS organization continues to use the Risk Registry on a monthly basis as a key management tool to proactively address its known risks. The undulator floor stability risk has now been retired as it has now been shown that expected stability issues can be addressed with the alignment systems and BBA at acceptable intervals. internal.slac.stanford.edu/projectspace_L2/Project_Office/Risk_Registry_Document s/LCLS_risk_registry_September_05.pdf

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 The project is entering into its boost phase where it is undergoing its maximum gradient: staffing, effort and procurement. During this phase, the timeliness of decisions often becomes critical and delays can quickly accumulate that can impact the overall progress of the project without specific attention. This is a concern to the FAC as the decision making process is not transparent and may need to accelerate to ensure avoiding unnecessary delays. Response: The decision making process has been made more transparent with the Change Control Board (CCB). With the CD-2b (Approve Performance Baseline), LCLS has enacted the CCB to deal with technical, cost and schedule issues on a timely basis. The CCB forum ensures that decisions are communicated uniformly across the project and formally documented in a manner consistent with good configuration control. Since CD-2b (April 2005), LCLS has approved 77 changes to the project and allocated ~$7M of contingency to the baseline cost of the LCLS.

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 The critical path of the project, likewise, may be extremely fluid during this phase and near critical paths can quickly become critical paths, and so those efforts which at present are not on the critical path, must understand that they can quickly become the pacing activities. Response: The LCLS has significantly increased its staffing since April 2005 and with that some time for assimilation of new staff into the project is required. The LCLS is now nearly complete on its staffing plan so the inefficiencies due to assimilation can be expected to drop off. Critical path is monitored regularly and has not shown any appreciable degradation since established at 215 days.

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 …However, an insightful planning exercise is to evaluate all activities for early starts up to the point where all of the budget authorization (BA) in each fiscal year would be used. In addition, exceeding this optimistic BA plan by 5 to 10% would also be helpful in evaluating potential resource demands. This planning assures that there are “swing items” identified in order to accomplish other work if planned activities are delayed. If the project doesn’t have swing items identified to work in the available time and with the available BA, the CD-4 milestone may be at greater risk than necessary. “Swing procurements” are procurements that can be advanced should budget become available due to delays in other areas. This is of primary importance between FY06 and FY07. Since civil construction sets the critical path, LCLS will plan to use its budget flexibility in this area to best advantage, based on advice from the Construction Manager.

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 A useful plot that can illustrate this phenomenon, and serve as both a leading and lagging indicator, is the contingency as a percent of the estimate to complete (ETC) budget as a function of the percent of the project complete. Generally, this should be roughly a horizontal line above 20%. Early in the project life it would likely start out at a higher number and depending upon the remaining risks within a project, the percentage can also be less than 20%. Response: Currently, the LCLS holds ~32% contingency on work remaining. This number may fall lower as the conventional facilities estimates become more mature and LCLS approaches the start of construction.

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 There is a need for a central database containing and controlling the complete configuration of the LCLS project. Work has begun on defining the detailed needs of the central database effort for the LCLS project. An IT Manager (Andrea Chan from the SLAC SCS group) has been hired into the LCLS Division and bringing significant experience in setting up databases in a project environment. At the same time Sergei Chevtsov in the LCLS Controls Group has been looking at the relational database needs for the control system, in particular the RDB requirements for online modeling for the accelerator.

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 The LCLS Project should consider giving the FAC access to the LCLS internal website. This would allow the FAC to view other reviews and important work that can have an impact on the scope and details of FAC meetings. It will also allow the LCLS Project to exploit the full potential of the FAC. LCLS is in the process of exploring a different data management system, which would make access control but the system is not likely to become operational in this calendar year. At present, LCLS is working with Kem Robinson to do it the hard way now or wait until the simpler solution is in place.

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 Charge to Committee Consider responses to last review Consider planned/proposed scope changes to accommodate conventional facilities costs

John N. Galayda LCLS Facility Advisory Committee 27 October 2005 End of Presentation