LIGO-G060421-00-M 1 Advanced LIGO Status LIGO Scientific Collaboration Meeting August 15, Dennis Coyne LIGO Laboratory, Caltech.

Slides:



Advertisements
Similar presentations
Laser Interferometer Gravitational-wave Detectors: Advancing toward a Global Network Stan Whitcomb LIGO/Caltech ICGC, Goa, 18 December 2011 LIGO-G v1.
Advertisements

LIGO-G D Comments: Staged implementation of Advanced LIGO Adv LIGO Systems 17 may02 dhs Nifty idea: a way to soften the shock, spread cost, allow.
G R LIGO Laboratory1 Advanced LIGO Research and Development David Shoemaker LHO LSC 11 November 2003.
LIGO-G D Suspensions Update: the View from Caltech Phil Willems LIGO/Caltech Livingston LSC Meeting March 17-20, 2003.
LIGO-G W Status of LIGO Installation and Commissioning Frederick J. Raab, LIGO Hanford Observatory.
LIGO-G D partial ADVANCED LIGO1 Optical Layout Cavity Lengths Input Mode Cleaner (IMC) »IMC FSR = ~9 MHz »Length = ~16.6 m = ~HAM1 to HAM3 separation.
G R LIGO Laboratory1 Advanced LIGO Research and Development Update Dennis Coyne LSC Meeting at LLO 16 March 2004.
LIGO-G06xxxx-00-M Technical Progress Planned/Needed in FY07 Advanced LIGO Program Advisory Panel meeting, 30 November – 1 December 2006, MIT Dennis Coyne,
20 Nov 2008G v21 Optical & Vacuum Equipment Layouts Dennis Coyne Mike Smith Luke Williams 20 Nov 2008 Adv. LIGO Team Meeting, Caltech, Pasadena,
LIGO-G M April 5, 2006 Interferometer Sensing and Control (ISC) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project Richard.
LIGO-G D Suspensions Design for Advanced LIGO Phil Willems NSF Review, Oct , 2002 MIT.
GWADW 2010 in Kyoto, May 19, Development for Observation and Reduction of Radiation Pressure Noise T. Mori, S. Ballmer, K. Agatsuma, S. Sakata,
LIGO-G W Status of LIGO Installation and Commissioning Frederick J. Raab, LIGO Hanford Observatory.
Overview of Research in the Optics Working Group Gregory Harry, on behalf of the OWG Massachusetts Institute of Technology July 25, 2007 LSC Meeting –
Status of LCGT and CLIO Masatake Ohashi (ICRR, The University of TOKYO) and LCGT, CLIO collaborators TAUP2007 Sendai, Japan 2007/9/12.
4/25/11 G v3 1 Facility Modifications and Preparations (FMP) Technical Status Annual NSF Review of Advanced LIGO Project April , 2011 John.
LIGO-G D 1 Advanced LIGO Optical & Mechanical Layout Status Dennis Coyne, LIGO Caltech LSC Meeting, 21 Mar 2006 Version -01: with a couple of.
Design of Stable Power-Recycling Cavities University of Florida 10/05/2005 Volker Quetschke, Guido Mueller.
Optical Configuration Advanced Virgo Review Andreas Freise for the OSD subsystem.
LIGO-G M May 31-June 2, 2006 Input Optics (IO) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project David Reitze UF.
Conceptual Design for Advanced LIGO Suspensions Norna A Robertson University of Glasgow and Stanford University for the GEO suspension team +contribution.
LIGO-G M 1 Conceptual Design Review: Initial LIGO Seismic Isolation System Upgrade Development, Implementation Plan & Schedule Dennis Coyne April.
G M 1 Advanced LIGO Update David Shoemaker LSC/Virgo MIT July 2007.
LIGO-G Advanced LIGO Detector upgrade is planned for »Factor of 10 increase in distance probed (‘reach’) »Factor of 1000 increase in event.
Advanced VIRGO WG1: Status VIRGO, Cascina Andreas Freise University of Birmingham.
LIGO-G D Enhanced LIGO Kate Dooley University of Florida On behalf of the LIGO Scientific Collaboration SESAPS Nov. 1, 2008.
G v5 1 Core Optics Components Technical Status NSF Review of Advanced LIGO Project April 2011 GariLynn Billingsley.
LIGO-G D The LIGO-I Gravitational-wave Detectors Stan Whitcomb CaJAGWR Seminar February 16, 2001.
LIGO- G D The LIGO Instruments Stan Whitcomb NSB Meeting LIGO Livingston Observatory 4 February 2004.
LIGO-G M Major International Collaboration in Advanced LIGO R&D Gary Sanders NSF Operations Review Hanford February, 2001.
G Z LIGO R&D1 Input Optics Definition, Function The input optics (IO) conditions light from the pre- stabilized laser (PSL) for injection into.
DFG-NSF Astrophysics Workshop Jun 2007 G Z 1 Optics for Interferometers for Ground-based Detectors David Reitze Physics Department University.
LIGO-G D LIGO and Industry Capability/ProductCompany Ultra-high Vacuum TechnologyCB&I Passive Seismic IsolationHytec Inc. Active Seismic IsolationBarry.
Advanced Virgo Optical Configuration ILIAS-GW, Tübingen Andreas Freise - Conceptual Design -
G R 1 Advanced LIGO Update David Shoemaker LSC LHO March 2006.
G R LIGO R&D1 Advanced LIGO Update Dennis Coyne LSC LLO March 2005.
LSC August G Z Gingin High Optical Power Test Facility (AIGO) 1 High Optical Power Test Facility - Status First lock, auto-alignment and.
Status of the Advanced LIGO PSL development LSC Virgo meeting, Caltech, March 2008 LIGO G Z Benno Willke for the PSL team.
AIGO 2K Australia - Italy Workshop th October th October 2005 Pablo Barriga for AIGO group.
LIGO LaboratoryLIGO-G R Coatings and Their Influence on Thermal Lensing and Compensation in LIGO Phil Willems Coating Workshop, March 21, 2008,
Nov 3, 2008 Detection System for AdV 1/8 Detection (DET) Subsystem for AdV  Main tasks and requirements for the subsystem  DC readout  Design for: the.
Status of the Advanced LIGO PSL development LSC meeting, Baton Rouge March 2007 G Z Benno Willke for the PSL team.
Advanced LIGO Simulation, 6/1/06 Elba G E 1 ✦ LIGO I experience ✦ FP cavity : LIGO I vs AdvLIGO ✦ Simulation tools ✦ Time domain model Advanced.
Paolo La Penna ILIAS N5-WP1 meeting Commissioning Progress Hannover, July 2004 VIRGO commissioning progress report.
ACIGA High Optical Power Test Facility
Advanced LIGO Status Report
LIGO-G M LIGO Status Gary Sanders GWIC Meeting Perth July 2001.
Initial and Advanced LIGO Status Gregory Harry LIGO/MIT March 24, 2006 March 24, th Eastern Gravity Meeting G R.
LIGO-G M Overview of LIGO R&D and Planning for Advanced LIGO Detectors Gary Sanders NSF R&D Review Caltech, January 29, 2001.
LSC Meeting March ‘07 1 LIGO ADVANCED SYSTEMS TEST INTERFEROMETER (LASTI) LASTI Progress and Plans LSC Meeting, LLO Dave Ottaway/Richard Mittleman March.
Optical Spring Experiments With The Glasgow 10m Prototype Interferometer Matt Edgar.
G R LIGO R&D1 Advanced LIGO Update David Shoemaker LSC LHO August 2004.
LIGO Scientific Collaboration
Advanced Advanced Virgo BASELINE DESIGN advanced Giovanni Losurdo – INFN Firenze Advanced Virgo Coordinator for the Virgo Collaboration.
GEO Status and Prospects Harald Lück ILIAS / ETmeeting Cascina November 2008.
LIGO-G D Core Optics Components (COC) Polishing Pathfinder Kickoff Advanced LIGO Project GariLynn Billingsley Caltech.
The Proposed Holographic Noise Experiment Rainer Weiss, MIT On behalf of the proposing group Fermi Lab Proposal Review November 3, 2009.
G R 2004 Plan Update LIGO Systems meeting 22 Jan 04 dhs.
THE NEXT GENERATIONS OF GRAVITATIONAL WAVE DETECTORS (*) Giovanni Losurdo INFN Firenze – Virgo collaboration (*) GROUND BASED, INTERFEROMETRIC.
LIGO-G d April 24, 2007 Auxiliary Optics System (AOS) Technical Breakout Presentation NSF Review of Advanced LIGO Project Mike Smith, Phil Willems.
LIGO-G v1 Inside LIGO LIGO1 Betsy Weaver, GariLynn Billingsely and Travis Sadecki 2016 – 02 – 23 at CSIRO, Lindfield.
Characterization of Advanced LIGO Core Optics
The Proposed Holographic Noise Experiment
Auxiliary Optics System (AOS)
First Lessons from the Advanced LIGO Integration Testing
Update on the Advanced LIGO PSL Program
Design of Stable Power-Recycling Cavities
Flat-Top Beam Profile Cavity Prototype: design and preliminary tests
Status of LIGO Installation and Commissioning
Auxiliary Optics System (AOS)
Presentation transcript:

LIGO-G M 1 Advanced LIGO Status LIGO Scientific Collaboration Meeting August 15, Dennis Coyne LIGO Laboratory, Caltech

LIGO-G M 2 Seismic Isolation (SEI) for the BSC Chamber Assembly of the Two-Stage, Internal Seismic Isolation (ISI) is well underway at LASTI Expect ‘dirty’ assembly & testing completion this fall & clean assembly early 2007 Joined to the “Noise” Prototype 2 nd Quarter 2007 RequirementHAM Chamber ValueBSC Chamber Value Payload mass510 kg800 kg Range± 1 mm, ± 0.5 mrad Optics table noise4 x m/√Hz Hz)3 x m/√Hz Hz) Angular noise100 nrad RMS10 nrad RMS

LIGO-G M 3 Seismic Isolation (SEI) for the HAM Chamber Optics table Spring box assy. Support table Inverted Pendula (4) Geometric Anti-Spring (GAS) Filter Assy. (4) Mass representing payload Relaxed Seismic requirements established Baseline design approach »Optimized (now single stage internal to vacuum system) »Prototype conceptual design nearing completion; detailed design to start soon Alternative HAM-SAS approach »Prototype fabrication expected to be completed October »LASTI Experimental Results due by 4/2007 Decision & AdL Prototype fabrication start 4/2007

LIGO-G M 4 Suspensions (Combined US and UK Effort) Test Mass (Quad) Suspension »‘Controls’ Prototype installed at LASTI & under Test »Preliminary Results in June for Concurrent “Noise” Prototype Development »The UK Group delivers the “Noise” Prototype (close to final design) ~3/2007 »Installation ~5/2007 Other suspensions (extensions of existing designs): Input Mode Cleaner mirror (triple) – prototype installed Recycling mirror (triple) –full design Beamsplitter (triple) –conceptual design Folding Mirror (triple) –conceptual design Output mode cleaner (double) –conceptual design underway – emphasis for Enhanced LIGO Mode matching telescopes, steering mirrors etc (single) Quad Suspension in LASTI BSC Chamber

LIGO-G M 5 New Elements/Aspects of the “Noise” Prototype, Quadruple Suspension Silica Fiber/Ribbon Pulling »R&D on computer controlled CO 2 laser system proceeding well »Fibers up to 570 mm long, 184  5 microns diameter (15 microns dia. repeatability) »3 GPa breaking stress (factor of safety  4) Fiber/Ribbon Welding »Fiber & ribbon welding demonstrated »Working to improve welded strength Electronics »Improved Optical Sensing & Electro-Magnetic actuator (OSEM) assembly »New Control & Data Systems (CDS), Bus & Network Topology at LASTI implemented Motion Limiters (‘earthquake stops’) »Fused silica contact tips, improved adjustment capability Welding 3mm silica rod with 9W CO 2 laser Modified Hybrid OSEM Design

LIGO-G M 6 Core Optics Components Substrate procurement Substrate polishing Dielectric coatings Metrology Continuing coating R&D for lower mechanical and optical loss coatings »Silica/Silica-doped titania shows reduced mechanical loss, but not likely as good as Silica/titania-doped tantala for optical properties »Silica/Silica-doped tantala coatings are being tested currently »LMA working on minimizing loss in Silica/titania-doped tantala Test Masses: 34cm  x 20cm 40 kg BS: 37cm  x 6cm Recycling Mirrors: 26.5cm  x 10cm ITM T = 0.5% Large beam size on test masses (6.0cm radius), to reduce thermal noise SRM T = 7% PRM T = 7% Round-trip optical loss: 75 ppm max Compensation plates: 34cm  x 6.5cm

LIGO-G M 7 Core Optics Components Polishing »Analysis of Radius-of-Curvature sensitivity –FFT Optical Analysis code development to be completed ~Aug –Will define ROC tolerance for nearly de-generate (baseline) and stable (alternative) recycling cavities for ‘Pathfinder’ effort »Analysis of ‘Orange Peel’ residual polishing figure error suggests 2 ppm loss »Analysis of surface figure PSD suggests ~0.5 nm rms required for 20 ppm loss budget »Preparing ‘Pathfinder’ procurement specifications/bid-package to qualify polishing sources on larger optics Scatter requires improvement over Initial LIGO levels »Exploring improved particulate cleanliness techniques/requirements Electrostatic charging »Kelvin probe development underway (Trinity College) »Commercial Kelvin probe purchase/development being investigated ‘orange peel’ residual polishing error In an Initial LIGO Core Optic (0.18 nm rms) Requirements Surface figure< 1 nm rms Micro-roughness< 0.1 nm rms Coating absorption< 0.5 ppm (required) < 0.2 ppm (goal) Coating scatter< 2 ppm (required) < 1 ppm (goal) Coating mechanical loss < 2 x (required) < 3 x (goal)

LIGO-G M 8 Chamber Airflow Profile – Preliminary Computational Fluid Dynamics Simulation (Flomerics Inc.) Plane taken at centerline of the chamber We see that when the supply and exhaust in the chamber are turned off natural convection caused by the workers dominates the airflow patterns View Orientation

LIGO-G M 9 Input Optics Optical layout in vacuum Preliminary Design for Advanced LIGO Isolators and Modulators held in April Modulation »Mach-Zehnder modulation –set-up converted to high power –  L Requirements derived »Complex Modulation –Cross-product free SB synthesis done Power Control »High power beam dump developed Mode Cleaner »MC design finesse reduced from 2000 to 500 –Based on PSL pointing performance –Reduced thermal effects Faraday Isolator »Characterization of angular drifts at 100 W »Vacuum testing starting –Second generation housing needed Adaptive Mode Matching Telescope »Examination of MMT incorporation into stable power recycling cavity

LIGO-G M 10 Auxiliary Optics & Thermal Compensation System AOS & TCS Preliminary Designs proceeding well »Thermal Compensation Review to be held this Thursday »AOS review this fall Thermal compensation testing on the quad to be incorporated into the LASTI program ETM Transmission Telescope Arm Cavity Baffle TCS Ring heater & Recycling Cavity Baffle on ITM Quad

LIGO-G M 11 Control & Data System DATA ARCHIVE CONTROL ROOM INTERFEROMETER ENVIRONMENT DIAGNOSTICS New Realtime Network Topology »Star fabric vs Serial loop »Deterministic GigE/PCIe from ADC/DAC I/O chassis to computers PCIe and custom ADC/DAC I/O Multi-CPU computers »Arbitrary Waveform Generator (AWG) and Test Point Manager (TPM) built in »EPICS interface via CPU memory instead of networked Supports higher infrastructure data rates (to 128 kHz) Realtime Linux Testing »Previous systems use vxWorks »Move away from Solaris for Framebuilders and operator stations New Timing System tests Generation of realtime code from Matlab model files »LASTI quad & HEPI systems have code automatically generated from Matlab model files Prototype PCI-X System »Completed Installation at LASTI for Suspension Testing »Balance of infrastructure & seismic support installation is in-process

LIGO-G M 12 Pre-Stabilized Laser Max-Planck Institute, Hannover leads the PSL development, working with Laser Zentrum Hannover and CIT Injection locked 180W Laser Prototype Proceeding well on the preliminary design Started bench prototype Laser Achieved »180W output power »Good spatial profile »Power fluctuations close to reqmnts PSL Achieved: »Frequency noise requirement »RIN=3 x /sqrt(Hz) above 20 Hz (in table top experiment) »Diagnostic breadboard in final design phase

LIGO-G M 13 Interferometer Sensing & Controls Continuing 40M work: »DC readout system with Output Mode Cleaner expected in place by late Aug »“Deterministic locking” works well with power recycled interferometer. To be applied to dual recycled interferometer, soon. »Testing new PCIx data acquisition architecture for the readout. Pursuing early deployment of a DC readout & OMC suspension for Enhanced LIGO (2007) Modeling angular alignment sensitivity & control with E2E and other tools

LIGO-G M 14 Project Baseline Successful NSF Review of cost and schedule for AdL Project held 5/31-6/2 »Baseline review ~5/2007 Issued Project Execution Plan (PEP), Risk Management Plan, Revised & reviewed Cost & Schedule

LIGO-G M 15 Advanced LIGO Schedule Summary Cartoon Return to Operations Funds MREFC Funding Start Oct 2007 FY09FY08FY10FY11FY12FY13 FY14 FY07 Start Installation Development Development / Prototype Testing Integrated Prototype Testing at LASTI IFO1 Shutdown IFO1 Fab. / Procure / Assemble IFO1 installation IFO1 Integration/ Test IFO1 AEI PSL Procure / Assemble IFO2 & IFO3 Shutdown IFO2 & IFO3 Installation DCS Assembly / Install IFO2 & 3 Fab. / Procure / Assemble IFO2 & IFO3 Integration/ Testing IFO1 UK Suspensions Production IFO2 & 3 UK Suspensions Production IFO1 Acceptance IFO 2&3 AEI PSL Procure / Assemble IFO2 Acceptance IFO3 Acceptance FY15 Start of Commis -sioning Construction

LIGO-G M 16 Summary R&D proceeding reasonably well »a little behind schedule, but recoverable and not threatening readiness for AdL construction funds »Staffing limited in most cases (except coating R&D) Need to begin to staff up »Accelerate development »Anticipation of Adv. LIGO project funding start in FY08 Completion of the pacing R&D efforts to be ready for AdL construction funds will be a challenge in the coming ~2 years Successful NSF Review of Advanced LIGO proposed cost & schedule!