DCal Meeting 12-16-09.

Slides:



Advertisements
Similar presentations
D-Cal production preparations in Japan Dec. 16, 2009, D-Cal meeting at CERN Tatsuya Chujo (Univ. of Tsukuba) for the D-Cal Project 1.
Advertisements

February 11, DCal Technical Meeting 1 DCal Funding and Start up in the US.
L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
ALICE © | RRB | 17 April 2013 | Catherine Decosse 24 th meeting of the ALICE Resources Review Board CERN-RRB
Fermilab E906 Schedule Paul E. Reimer 20 June 2008.
Report from TB CB, July 2 nd 2010 W. Riegler. TF – P2 issues, shutdown plans2 Next LHC technical stops Dates: 19 th to 22 nd July 30 th August.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
EMCAL: project update - Italy - LNF - Frascati Fixture production Module assembly (proto) WLS fibers processing Lead procurement (proto) CT- Catania APD.
EMCal Meeting CERN – July 2 nd 2007 LPSC Status 1 J-F Muraz LPSC Status LPSC Status.  Assembly Hall. - Removal starts and is in progress. - Main infrastructure.
LIGO-G D partial ADVANCED LIGO1 Development Plan R&D including Design through Final Design Review »for all long lead or high risk subsystems »LIGO.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
GLAST I&T January T Borden 1 Tracker EM Mechanical Mock-up T Borden I&T Tracker Mock-up.
E. Michael Saleski PPS and April 20, 2006 LCLS Personnel Protection System and Beam Containment System E. Michael Saleski.
L. Greiner 1IPHC meeting – September 5-6, 2011 STAR HFT Plans for the next year A short report on review results and plans for TPC – Time Projection.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
12 Dec 2005 J. Schukraft1 ALICE USA ALICE position towards US participation EU participation in emcal Requirements Formal steps & schedule.
ECFA European Committee for Future Accelerators ECFA ACTIVITIES Lenny Rivkin, EPFL & PSI CHIPP Plenary meeting Fribourg, 30 June – 2 July, 2014.
+ STAR HFT Upgrade – Installation and Integration Rahul Sharma Brookhaven National Laboratory.
October 2010CERN-Korea J. Schukraft1 ALICE Status 8 th CERN-Korea meeting Collaboration News Korean participation General ALICE status report on Wednesday.
WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/ SBS DOE Review.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
15/2/2006 LHCC Status Report J. Schukraft General News LHC progress & Schedule  now recent news on schedule  ‘closure of beam on 31 August’, first injected.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
GEM chambers for SoLID Nilanga Liyanage University of Virginia.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
STATUS OF MUV3 CONSTRUCTION A joint IHEP Protvino – Mainz – Pisa project MUV3  Proposed by Italo Mannelli: Thick scintillator tiles with direct light.
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
15/07/2008 EMCAL Meeting Nantes A. Palmeri - F. Noto I.N.F.N. Catania1 EMCAL CATANIA A. Palmeri - F. Noto.
EMCal Status ALICE Technical Board November 20, 2008 News Schedule.
Comment on the LHCb upgrade cooling plan Paolo Petagna Meeting on CO 2 Cooling CERN 11 March 2015.
UCSC August 12, 2008 U.S. Upgrade R&D Meeting: Strip Detector  Seiden.
Global Design Effort Introduction and goals of the meeting Andrei Seryi, Toshiaki Tauchi Fifth ATF2 Project Meeting December 19-21, 2007.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
Plan to go forward Peter Wilson SBN Program Coordinator 27 September 2014.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
ALICE EMCAL CATANIA FACILITY The assembly Lab Assembly Team Catania Team is composed: 1 Ricercatore Armando Palmeri 1 Assegnista Tecnologo Francesco.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Tom Egebo PPPL Review of the NSTX TF Coil Repair Effort September 3 - 4, 2003 Cost & Schedule to Completion Supported by Columbia U Comp-X General Atomics.
DCal Insertion Tooling 24/02/ DCal Insertion Tooling DCal Insertion System feature following main components 1. One rotator : cylindric welded structure.
CENF meeting 5 th February STATUS CE engineering contract running : – phase 1 : tender drawings – phase 2 : execution drawings – Phase 3 (option)
ECFA - European Commitee for Future Accelerators Tatsuya Nakada – EPFL, Switzerland– prepared for CERN September Council presented by.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
EMCAL Calibration & Assembly at Yale University Mark Heinz, Project Mgr EMCAL Meeting Nantes July 15, 2008.
1 Status of infrastructure MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
SPHENIX MECHANICAL D. Lynch September 11, AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Status of the Spanish contribution to CTF3 L. García-Tabarés, F. ToralCERN, 17/9/2006.
Single-Phase ProtoDUNE Construction Planning Jim Stewart LBNC January 11, 2016.
Time to resolve Design Issues 1. Disclamer Due to the engineering meeting last week I have not had time to coordinate this material with Tim or the L3.
DCal-ALICE integration and installation plan and status A. Tauro.
News about the WA104 Programme C. Montanari – INFN and CERN technical working group meeting, September 16,
RFQ Installation Plan PIP-II Meeting, 14-July-2015 C. Baffes for R. Andrews, A. Chen, Y. Czajkowski, S. Kazakov, R. Pasquinelli, D. Peterson, O. Pronitchev,
On detector electronics: High voltage part Tilecal session in ATLAS upgrade week (Tuesday 10 November 2009) François Vazeille  What are the constraints.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
Resource Loaded Schedule and Budget Profile
Jim Fast Pacific Northwest National Laboratory
Complementary ISTC Projects #3888, 3889p
Mini-drawers, FE-ASIC , Integrator
Olof Bärring LCG-LHCC Review, 22nd September 2008
EMCal – France Status report, July 2008 Manpower Technical activities
MicroMegas Mechanical Meeting --- Cern April 2014
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Presentation transcript:

DCal Meeting 12-16-09

DCal Collaboration China Huazhong Normal University Finland University of Jyvaskyla France LPSC Grenoble, Subatech Nantes, IPHC Strasbourg Italy INFN Catania, LNF Frascati, Japan Hiroshima University, University of Tokyo, University of Tsukuba, Switzerland CERN USA Lawrence Berkeley National Laboratory, Wayne State University, University of Houston, University of Tennessee, Lawrence Livermore National Laboratory, Yale University, Oak Ridge National Laboratory, Creighton University, Cal Poly San Luis Obispo, Purdue University

Major Meetings and Discussion Sessions Upgrade Forum June 29th July 9th Joint EMCal + DCal Technical Meeting July 23rd DCal + ALICE Engineering Discussion September 16, 17 Joint EMCal + DCAL Design Progress Meeting October 14 DCal Engineering Discussion Upgrade Forum October 19th Weekly discussions between DCal Engineering and ALICE Technical Coordination DCal Planning and Coordination Meeting 12-16-09

Technical Developments Define single scope objective = B-6. Now the focus of all physics studies and subsequent discussions with ALICE and with funding agencies. Adopt D-Cal super module concept (16 strips) Meeting 2. Engineering Constraints - Define construction, assembly and installation procedures to minimize interference with operational ALICE sub-systems 3. Adopt common support structure for D-Cal super module cradle and new PHOS cradle. Adopt common installation scheme for D-Cal and PHOS. Identify D-Cal/PHOS interface issues – weekly meetings 4. Examine access issues - Adopt design concepts to guarantee general subsystem access and and personnel safety access and egress

DCal Conceptual Design 1. B6 Configuration Now Selected DCal – 6 super modules Dh~0.7 4 3 2 PHOS – 5 modules shown B6 Configuration allows largest possible jet radii in DCal

B6 Configuration - Super Module Concept DCal EMCal Shortened DCal Super Module - 16 strip modules (3 shown) Installed h= 0 to ~0.7 (including PHOS) Df ~20 degrees Standard EMCal Super Module - 24 strip modules (3 shown) Installed h= 0 to ~0.7 Df ~20 degrees Most labor intensive part of the project Design finalized – ready to start

DCal + PHOS common cradle conceptual design DCal + PHOS Cradle Existing PHOS rails – required modification discussed below

Critical Path: Common PHOS-DCal cradle Tentative schedule End of November : conceptual design frozen Early January 2010 : order of raw material End of January 2010 : fabrication drawings completed Early February : design review End of February : tender Early April : start of order administrative procedure Mid October : fabrication completed in workshop, preassembly, tests, delivery procedure. Early November 2011: shipping to CERN

Other integration issues PHOS rails As designed, PHOS rails cannot be loaded with both PHOS_5 and DCal, but only one rail needs to be stiffer. Tube shaped rail, roughly 500 x 425 x 25, OK for deflection, stress, stability, slightly more expensive than I-Beam rail A rail of these dimensions Preserves the clearance for ALICE Services under PHOS Rails. Services under existing PHOS rail

Funding Status Japan: Funding in place. Very good progress on preparations for module construction. – critical path -scintillator delivery China: Wuhan. Partial funding promised. Critical path - A lot of preparatory work still needed, finalize funding France: Subatech, Grenoble and Strasbourg. Funding discussions with IN2P3 November 13th. Very Positive response. Construction and assembly facilities ready. Support cradle design nearing completion USA: Funding discussion with DOE November 30th. Very positive response Final proposal due in February. Construction and assembly facilities ready. Critical path - finalize funding

Funding Status, Near term plans and schedule Schedule Objective: completion of full DCal in time for winter 2010 – 2011 shutdown Schedule realities: completion of all detailed design and integration work including new PHOS rail and cradle is on schedule. No “show stoppers” foreseen in the remaining work. Procurement process of cradle and new PHOS rail must start very soon. Most of the required detector production capability is already in place. The balance (if any) can easily be added in time for a late summer 2010 completion Materials procurement may be the biggest problem

Extra Slides

Rail system on the cradle to move detectors along Z axis (like EMCal) PHOS module carriage. DCal super modules Carriage Rails

PHOS cradle conceptual design DCal rails New PHOS cradle allows independent z-motion of individual PHOS module on DCal rails

Note: The scope of the DCal project includes replacing only a single PHOS rail. If Future addition of other HEAVY detectors is contemplated, then both rails should be replaced at this time providing funding can be found.

Note: The scope of the DCal project includes replacing only a single PHOS rail. If Future addition of other HEAVY detectors is contemplated, then both rails should be replaced at this time providing funding can be found. Example of HEAVY: A first step toward full Azimuthal EMCal coverage

4. Other integration issues Personnel Access inside L3

4. Other integration issues Personnel Access inside L3 New access locations New stairway locations

4. Other integration issues Personnel Access inside L3 New access locations No perturbation of critical services

4. Other integration issues Safety Access inside L3 Shuttle for evacuation of injured people from C to A side