Bringing an Acquisition onto SAP: A Supply Chain Perspective Session: 2809.

Slides:



Advertisements
Similar presentations
A Presentation to the Cabinet A Presentation to Stakeholders
Advertisements

A Systems Approach To Training
A BPM Framework for KPI-Driven Performance Management
Account Planning The purpose of these slides is to describe the Account Planning Process, the methodology, and the workload involved in running an account.
MIGRATION MIGR-09. How to Run Your Next Implementation... Don't Let It Run You! Patricia Johnson Senior Systems Consultant Strategic Systems Group, Inc.
Intro. Website Purposes  Provide templates and resources for developing early childhood interagency agreements and collaborative procedures among multiple.
INITIAL ON BOARDING COACHING
Test Automation Success: Choosing the Right People & Process
Session 2.3: Skills for Supportive Supervision
Software Quality Assurance Plan
Large Company Technology Networking Conference Wes Smith Executive VP & Chief Operating Officer Mayer Electric Supply Company, Inc.
Ahsan Kabir Project Manager Ahsan Kabir Project Manager ………………………….
System Office Performance Management
1 Introduction to Workforce Planning and Development in State of Alaska Executive Branch Departments.
Implementation Audit and Control Background Internal Audit Role Go-Live Criteria Audit Approach - Systems Audit Approach - People Summary Agenda.
Copyright © 2003 Americas’ SAP Users’ Group Session 4904 SAPConsole an End-to-End Security Implementation Chris Kralovansky NIBCO INC. Technical Analyst.
By Saurabh Sardesai October 2014.
Tim Harris| Western Computer
Webinar #1 The Webinar will begin shortly. Please make sure your phone is muted. (*6 to Mute, #6 to Unmute) 7/3/20151.
Types of Systems  Impact of systems implementation on organization change? Transaction Processing Systems (TPS) Management Information Systems (MIS) Decision.
The Software Product Life Cycle. Views of the Software Product Life Cycle  Management  Software engineering  Engineering design  Architectural design.
IS&T Project Management: Project Management 101 June, 2006.
System Office Performance Management
Professional Facilitation
project management office(PMO)
ITPD PRODUCTION SUPPORT PROCESS OCTOBER 8, /15/2015 Guiding Principles 1.Support the business area’s needs to execute transactions and expand.
Meeting Skills.
NORMA GOMEZ, MBA, MSN, RN, CNN Unique Challenges for the Nephrology Professional in Managing Change.
Release & Deployment ITIL Version 3
Effective Methods for Software and Systems Integration
OSSE School Improvement Data Workshop Workshop #4 June 30, 2015 Office of the State Superintendent of Education.
Copyright Course Technology 1999
A Security Training Program through Transformational Leadership and Practical Approaches Tanetta N. Isler Federal Information Systems Security Educators’
Striving for Quality Using continuous improvement strategies to increase program quality, implementation fidelity and durability Steve Goodman Director.
OSF/ISD Project Portfolio Management Framework January 17, 2011.
Do it pro bono. Strategic Scorecard Service Grant The Strategy Management Practice is presented by Wells Fargo. The design of the Strategic Scorecard Service.
Organize to improve Data Quality Data Quality?. © 2012 GS1 To fully exploit and utilize the data available, a strategic approach to data governance at.
You’ve Got What It Takes: Peer Training and Mentoring for Staff Development You’ve Got What It Takes: Peer Training and Mentoring for Staff Development.
Systems Development AIMS 2710 R. Nakatsu. Overview Why do IT projects succeed and fail? Two philosophies of systems development –Systems Development Life.
Certification and Accreditation CS Phase-1: Definition Atif Sultanuddin Raja Chawat Raja Chawat.
Welcome to the San Bernardino Coach Quarterly Meeting.
1. Housekeeping Items June 8 th and 9 th put on calendar for 2 nd round of Iowa Core ***Shenandoah participants*** Module 6 training on March 24 th will.
普 华 永 道 Phase 1: Project Preparation Phase 1: Project Preparation Phase Overview Phase Overview.
© 2001 Change Function Ltd USER ACCEPTANCE TESTING Is user acceptance testing of technology and / or processes a task within the project? If ‘Yes’: Will.
 SAP Public Sector and Education, 10/26/2015, Slide 1 The University of Tennessee Change Management Business Blueprint.
Microsoft Office Project 2003: Selling EPM in your Organization Matt Wilson Business Solutions Specialist LMR Solutions.
Project Kick-off Meeting Presented By: > > > > Office of the Chief Information Officer.
The Value Driven Approach
Lecture 4. IS Planning & Acquisition To be covered: To be covered: – IS planning and its importance Cost-benefit analysis Cost-benefit analysis Funding.
Strategies for Knowledge Management Success SCP Best Practices Showcase March 18, 2004.
Chapter 6: THE EIGHT STEP PROCESS FOCUS: This chapter provides a description of the application of customer-driven project management.
Operational and Postimplementation
Paramjit Sharma building a balanced scorecard. Paramjit Sharma Imagine an excellent scorecard built by a staff executive or middle management without.
Info-Tech Research Group1 Manage the IT Portfolio World Class Operations - Impact Workshop.
Tyler Implementation Kick-Off Aaron Joyal, PMP Financials Project Manager.
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 2 Diploma of Project Management.
The Project Management Process Groups
Info-Tech Research Group1 Info-Tech Research Group, Inc. Is a global leader in providing IT research and advice. Info-Tech’s products and services combine.
IS&T Project Reviews September 9, Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.
Financial System Upgrade Agency Change Champion Deployment Session March 16 th, 2006.
Phase-1: Prepare for the Change Why stepping back and preparing for the change is so important to successful adoption: Uniform and effective change adoption.
Presenter: Igna Visser Date: Wednesday, 18 March 2015
BANKING INFORMATION SYSTEMS
SAMPLE Develop a Comprehensive Competency Framework
Identify the Risk of Not Doing BA
Guidance notes for Project Manager
IS&T Project Reviews September 9, 2004.
{Project Name} Organizational Chart, Roles and Responsibilities
Presentation transcript:

Bringing an Acquisition onto SAP: A Supply Chain Perspective Session: 2809

Background – NIBCO INC. Founded in Elkhart, IN in 1904 Family-owned company Annual sales ~ $420M SAP users ~ manufacturing plants throughout U.S., Mexico, Poland 5 distribution centers: (4) in U.S., (1) in Poland

Background – NIBCO INC. Employs associates world-wide. Websites:

Background – NIBCO INC. Manufacturer of:

SAP Implementation History 1996: SAP selected as the sole provider of business systems for NIBCO October 1996: Formation of SAP implementation team Dec. 31, 1997: Big-bang implementation Release 3.0F 19 Locations (plants) Modules: FI/CO/SD/MM/PP/WM

Upgrades performed: March 1999: Release 4.0B March 2001: Release 4.6C SAP Implementation History

Additional plants: May 2000: International Distribution Center May 2002: Manufacturing/Distribution Center in Lodz, Poland (2) In-bond inventories in Lodz, Poland (2) In-bond inventories in Budapest, Hungary (2) In-bond inventories in Ytomierz, Ukraine SAP Implementation History

Additional functionality: March 2000: Human Resource Management - U.S. May 2002: Polish localization In process: Human Resource Management – Reynosa, Mexico In process: Time & attendance, Reynosa, Mexico In process: Business Warehouse implementation SAP Implementation History

Company acquisition – Live on SAP November 2002 Corona, CA Sacramento, CA Houston, TX SAP Implementation History

Acquisition background Why did NIBCO acquire another company? Growth Expand product offering Meet customer needs Foster a progressive attitude within the company

Acquisition background

Product segmentation Standard inventory products that are shipped in box quantities and are managed using the “demand pull” process Specialty fabricated products that are made / designed to order - requires special ordering and manufacturing procedures to manage. Acquisition background

Implementation timeline

Project Management Methodology Project Initiation Analysis Design Development Testing / Training Implementation

Project Initiation Getting started

Initiation – Project Goal Successfully acquire TOLCO Inc, integrate business operations into NIBCO INC to support a positive long-term financial return on the investment. Understand the project goal

Initiation - Scope Define the scope... Completely integrate all TOLCO business processes and systems into core NIBCO business systems. Re-alignment of TOLCO organization to support NIBCO business management structure and processes – change management is critical.

Project Initiation Keys to successful integration: Support core business during integration Address change management issues Business processes Organizational transition Define and populate master data to support business systems processes in SAP Develop TOLCO specific functionality where required Commit necessary resources!

Initiation – Assemble the Team Project sponsor Steering committee Core project team Change management team Extended / training team

Initiation – Assemble the Team Project sponsor (NIBCO) Visible, executive support Project vision Retain focus Provides resources Overcomes resistance to change

Initiation – Assemble the Team Steering committee (NIBCO & TOLCO) Comprised of IT and business leaders Empowered to make quick-hit decisions to keep project moving forward. Provide guidance. Ensure success!

Initiation – Assemble the Team Core project team (NIBCO & TOLCO) Business / IT members Perform majority of the SAP integration work Define and implement business processes Define and prepare training needs Implementation support

Initiation – Assemble the Team Extended / training team (NIBCO & TOLCO) Functional experts IT Developers Trainers Technical support

Initiation – Assemble the Team Change management team (NIBCO & TOLCO) Effective transition Build & execute formal change programs Monitor progress Job Impact Analysis

Initiation – Team Considerations Select a team to deliver a quick hit, comprehensive implementation of SAP Team composition: Business leadership (parent and acquired company) SAP systems leadership (parent) Commitment of team to the project Release from other obligations Sequester physically to focus effort to project and away from interruptions Management authority – decision making without the red tape Communication is key!

Initiation – Team Ground Rules Be candid. Encourage healthy debate. Active participation is expected. Respect each other and their opinions. Listen without interruption. Keep confidentiality of discussions within the team. Mistakes happen. We learn from them and move on. Strive for consensus in decision making. Honor our commitments. Fully support decisions outside of the room. Ask for help when needed. Have fun. FOCUS on RESULTS.

Initiation – Kick-off Meeting Communicate project goal. Communicate project scope. Communicate team structure / introduce members. Communicate project team responsibilities. Communicate project timeline and milestones. Reinforce management’s commitment to the project. Introduce acquisition associates to project management methodology.

Analysis Determining what needs to be done.

Analysis – “As Is” Process Mapping Map existing high-level business processes: Examples: Sales order to cash process Purchase requirements to payables process Production requirements to inventory process Drill down on each high level process to define subtasks. Functional assessment of subtasks to determine: What is accomplished? How it is accomplished? Who does it? Why is it done?

Analysis – “As Is” Process Mapping Document minor processes as well. Example: Physical inventory / cycle counting Use process mapping sessions to: Encourage communication between all associates. Collect thoughts about shortcomings of current practices. Confirm understanding by feedback to those who provided the information Begin to formulate thoughts of SAP solutions. Review output documents (production orders, shipping documents,...) Review existing master data. Review existing job roles and responsibilities. Assess associate process knowledge and computer literacy.

Analysis – Sample “As Is” Map

Analysis – “As Is” Process Mapping In a nutshell... The purpose of the “as is” portion of analysis is to gain an understanding of the existing processes in order to identify the SAP functionality required to support the business in the ultimate “to be” environment.

Analysis – “To Be” Vision Definition of SAP driven, integrated processes that support business operations. Performed primarily by NIBCO participants Define integrated business processes that: Effectively accomplish the business objectives Incorporate SAP systems functionality in the office and onto the shop floor. Eliminate unnecessary, non-value added work.

Analysis – “To Be” Vision Document “to be” vision as a series of business processes. Determine the master data required in SAP to support the “to be” business processes. Determine the delta: “as is” processes vs. “to be” processes. Compare master data needs to master data available to determine the deficit of data that has to be addressed.

Analysis – “To Be” Vision Document job roles that support the “to be” environment. Determine the delta between the existing organizational structure and the one required to support the “to be” environment.

Analysis – “To Be” Vision In a nutshell... The purpose of the “to be” portion of analysis is to determine the delta that has to be overcome to transition from the pre- SAP environment to the new SAP process driven model. This provides the basis for the next step …

Design Phase How are we going to get this done (in the time we have been given to do it)?

Design Phase Design business processes that describe the flow of information and integration of SAP into the business activity. Design SAPscript form layouts for all output documents. Design reports required to support business activity. Design product labels Design warehouse bin labels.

Design Phase Design processes to convert master data from existing systems into SAP as possible. Design processes to create master data elements not available in old system but required to support SAP going forward. How is the master data to be generated? Who will do the work*? How will the master data be loaded into SAP? * Note: It is likely that those who are knowledgeable to create the master data are also key resources in other aspects of the project.

Design – Business Process Business process contains: Process description Business rules that apply to the process Name of process owner Step-by-step walk-through of the process Who performs each step Step description If SAP is used within the step, include the transaction code for that step.

Design Phase Design reports required to support business activity. Design product labels Design warehouse bin labels. Design building layout with placement of workstations and printers required to support SAP usage. Design required new job roles.

Design Phase Design a training plan tailored to the needs of the associates: Computer literacy training Microsoft Outlook / Scheduler Functional training Lay the foundation for ongoing training through the use of online training tools such as On Demand. Language specific training needs (classes, materials, trainers).

Design Phase In a nutshell... The purpose of the design phase is to develop the roadmap to be used to accomplish the SAP implementation.

Development Phase Building the solution: From plans and specifications to the tangible.

Development Phase Develop: SAPscripts / programs Reports Master data load programs Training materials Training schedules (w/ job role assignments) Cut-over plan (week before go-live date) Security activity groups and profiles.

Development Phase Create a schedule to load master data Begin to load master data Development includes unit testing of each task.

Testing Integration test concept: 3 integration tests each targeted to accomplish a different aspect of testing. Business involvement must increased throughout the test phase. Success factors must be defined for each stage of the testing process. Must have focused testing sessions to accomplish a thorough test.

Integration Test 1 Goal: Verify that the major processes function as required.

Integration Test 1 Performed performed by NIBCO associates at the world headquarters. Performed by NIBCO Core Team and Extended Team members. Test end-to-end integrated functionality of processes that run 75% of the business activity. Limited master data load. Test security. Validate training materials. Document issues – 2 weeks to fix before next test.

Integration Test 1 Results... We know major processes function as required.

Integration Test 2 Goal: Verify that the all processes function as required.

Integration Test 2 Issues from Integration Test 1 have been addressed and resolved. Balance of processes have been prepared and are ready for integrated functionality test. Performed by NIBCO Core Team and Extended Team members at the Corona, CA facility. Used as a demonstration of SAP functionality for TOLCO associates. Test end-to-end integrated functionality of all business processes.

Integration Test 2 Validate TOLCO associate security. Reinforce change management. TOLCO associates get their first look at the “new” world with SAP. Document issues – 2 weeks to resolve before final test.

Integration Test 2 Results... We know all processes function as required. We know security will allow the associate to perform their job.

Integration Test 3 Goal: Verify system functionality. Evaluate TOLCO associate readiness.

Integration Test 3 Issues from Integration Test 2 have been addressed and resolved. Performed by TOLCO team at the Corona, CA facility (with support by NIBCO team members). Final test of assignment of security profiles to associates. Departmental managers and supervisors attended the testing sessions to evaluate associate readiness to use SAP to perform their job roles.

Integration Test 3 Associate readiness: Departmental managers did the evaluation. Was presented to the associates as an opportunity to determine if we needed to do more training. Associates were provided scripts that would be used for integration testing. (Business Process Documents) The NIBCO team committed to spend time with the TOLCO associates to help prepare for the integration test.

Integration Test 3 Results... We know all processes function as required.

Integration Test 3 Results... TOLCO associates spent many hours practicing and far exceeded our expectations! They were ready!

Testing Calendar August – First Integration Test Resolve issues uncovered in Integration Test 1 September – Second Integration Test Resolve issues uncovered in Integration Test 1 Training begins – September 22 Training complete – October 7 October – Final Integration Test October 18 – Final assessment – Go/No-Go decision

Training Training is a major key to success in delivering a “smooth” SAP integration on time.

Training The execution of an effective training plan begins back in the development stage.

Training Methods of delivery: CBT course from SAP to train basic SAP navigational skills. This was a requirement for every associate. Online training for SAP transactions (On Demand). Classroom, One-on-One, and OJT training for processes and transactions. Various templates to deliver concepts / processes: Quick references Business processes

Training Classes List MM01Introduction to Materials Management & Materials Management Master Data MM02Procurement – Purchase Requisitions MM03Procurement – Purchase Documents and Master Data MM04Inventory Management – Material Movements MM05Inventory Management – Outside Services MM06Inventory Management – Cycle Counting and Physical Inventory PP01Introduction to Production Planning and Production Planning Master Data PP02Logistics – Finished Goods Inventory Management and Planning PP03Production Scheduling – Standard Materials PP04Production Scheduling – Standard Item Modified (SIM) PP05 Production Scheduling – Fabricate to Order (FTO) PP06Production Order Completion and Analysis – Month End Process PP07Production Planning & Materials Management Reporting SD01Shipping and Delivery WM01Warehouse Management

Sample Training Schedule

Training Delivery Assessment

Training The key to effective training is to deliver the same material / concepts in multiple formats, multiple times to allow associates to utilize what is effective for them.

Implementation Go / No-Go Decision: Two weeks before the targeted go-live date NIBCO & TOLCO leadership meet to discuss readiness to go live. Identify any last-minute issues. Review the cut-over plan. Commit to a strong finish.

Implementation November 1, 2002 – Successful Implementation NIBCO support team on-site for the next two months to assure a smooth transition.

Lessons from the project... 1.Master data is king! It is never too early to work on master data. Include your master data guru in with you early analysis team. As much as we tried to attack master data as early in the project, we still struggled to get “acceptable” master data into SAP. Prioritize your master data. Define acceptable levels of data integrity.

Lessons from the project Start your SAPscript work early. It may take several iterations to get it right. 3. Listen closely. There is a big difference sometimes between what you think you heard and what was really said. 4. Feed back your thoughts to others (both NIBCO and TOLCO) to make sure you are on the right train of thought. With a tight implementation schedule, a misunderstanding can cost valuable time.

Lessons from the project Process is also king! SAP does not perform well in an environment where the user “shoots from the hip” when it comes to process. Spend a lot of time designing and clearly documenting all business processes. Spend a lot of time training the business process. People will learn to execute transactions quickly, but they must understand what they are doing within the integrated process. (How what they do affects others.)

Lessons from the project Management of critical people’s time is important. The same person who knows master data best is also the guru who can test the new process and answer questions about existing process. Identify these people early and attempt to off load duties and make time for them to participate in the project. Be sensitive to associate burn out when running a high stress, high expectation project such as this.

Lessons from the project Communication is also king! Develop a plan to inform all associates of the acquired company what is going on. It helps to relieve the stress and worry of the unknown. It was our experience that most of the TOLCO associates were eager to get started with the SAP training. They spent personal time to polish skills and practice competencies. “TOLCO Talks” were held monthly with all associates to review various aspects of the project and answer questions.

Lessons from the project Training is also king! Training plan is started in the design phase. Training must address the particular audience. If language is a factor, arrange for training materials and training sessions to be delivered in multiple languages. Plan to allow associates to have adequate classroom time and plenty of practice opportunity. Provide the same information in a myriad of ways to reinforce the learning.

Lessons from the project Use the project to develop a template that can be used again when the next acquisition comes along. Project management methodology can be reused. Process templates and training materials can be reused. Spreadsheets, etc. that are used to evaluate job roles, etc. can be reused. Review constructive comments in the training delivery evaluation to improve training skills for the “next time”.

Lessons from the project A smooth go-live period does not mean the work is done. Plan to staff a support team to insure continued success for at least two months after the go-live date.

Thank you for attending! Please remember to complete and return your evaluation form following this session. Session Code: 2809