MICE Project Board 28-08-2011 Alain Blondel 1 MICE running Preamble ISIS running Step I Step(s) IV Step V (and VI)

Slides:



Advertisements
Similar presentations
1 MICE Beamline: Plans for initial commissioning. Kevin Tilley, 16 th November. - 75days until commissioning Target, detectors, particle production Upstream.
Advertisements

Progress in the construction of the MICE cooling channel and first measurements Adam Dobbs, EPS-HEP, 23 rd July 2011.
1 Acceptance & Scraping Chris Rogers Analysis PC
Emittance definition and MICE staging U. Bravar Univ. of Oxford 1 Apr Topics: a) Figure of merit for MICE b) Performance of MICE stages.
FIGURE OF MERIT FOR MUON IONIZATION COOLING Ulisse Bravar University of Oxford 28 July 2004.
Neutrino physics: experiments and infrastructure Anselmo Cervera Villanueva Université de Genève Orsay, 31/01/06.
Changing the absorbers: how does it fit in the MICE experimental programme? Besides the requirement that the amount of multiple scattering material be.
CHIPP Sept 2005Jean-Sébastien GraulichSlide 1 What is MICE  Muon Ionisation Cooling Experiment  What is Ionisation Cooling ? Cooling = Reduction of Beam.
Alain Blondel MICE: Constraints on the solenoids 2.Field Homogeneity: or ? this will be dictated by the detector requirements. TPG will be.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
Kirk McDonald Monday, 28th May Report of the International Working Group on Muon Beamlines Bruno Autin, Roberto Cappi, Rob Edgecock, Kirk McDonald,
MICE analysis meeting Alain Blondel 5 August MICE -- what running strategy? disclaimer: of course we will evolve the running strategy as problems.
MICE Funding Agency Committee Alain Blondel 1 MICE: Present status and future plans Recall: Why MICE? Step I Step(s) IV Step V and VI.
MICE Experiments Introduction Introduction Disclaimers Disclaimers Assumptions Assumptions Baseline programme Baseline programme Full programme Full programme.
Mark Rayner, Analysis workshop 4 September ‘08: Use of TOFs for Beam measurement & RF phasing, slide 1 Use of TOFs for Beam measurement & RF phasing Analysis.
CMPB Alain Blondel 14 April STATUS OF MICE.
04/01/2006MICE Analysis Meeting1 MICE phase III M. Apollonio, J. Cobb (Univ. of Oxford)
MICE at STFC-RAL The International Muon Ionization Cooling Experiment -- Design, engineer and build a section of cooling channel capable of giving the.
17 March 2005Edda Gschwendtner1 MICE Cooling Channel: Can we predict cooling to ? Edda Gschwendtner Challenge Systematics Cooling Channel Beam Line.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices iteratively to determine trace.
Physics Program and Runs: Autumn 2011 & Step IV V. Blackmore MICE Project Board, 08/03/12.
CM37 Alain Blondel step IV physics success 1 « STEP IV operations : Physics »
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
Goals and Status of MICE The International Muon Ionization Cooling Experiment J.S. Graulich.
Status of the Muon Ionization Cooling Experiment (MICE) Yagmur Torun Illinois Institute of Technology April 1, 2013.
Particle Production in the MICE Beam Line Particle Accelerator Conference, May 2009, Vancouver, Canada Particle Production in the MICE Beam Line Jean-Sebastien.
MICE: The International Muon Ionization Cooling Experiment Ulisse Bravar University of Oxford ICHEP ‘04 1 MICE: The International Muon Ionization Cooling.
Paul Soler University of Glasgow MICE as a Step towards Cool Muon Beams for Particle Physics MICE Celebration Event RAL, 25 June 2015.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Results from Step I of MICE D Adey 2013 International Workshop on Neutrino Factories, Super-beams and Beta- beams Working Group 3 – Accelerator Topics.
MICE Step 1: First Emittance Results with Particle Physics Detectors Linda R. Coney EuCARD Meeting – 10 May 2011.
ICHEP 2012 Melbourne, 7 July 2012 Paul Soler on behalf of the MICE Collaboration The MICE Beam Line Instrumentation (Trackers and PID) for precise Emittance.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Alain Blondel. AIDA-Neutrino meeting AIDA Neutrino detector studies 1. News from the neutrino scene 2. Beam requirements for AIDA 3. Discuss.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MCTF 8/17/06 A. Bross MTA Activities and Plans MCTF August 17, 2006 A. Bross.
MICE at STFC-RAL The International Muon Ionization Cooling Experiment -- Design, engineer and build a section of cooling channel capable of giving the.
MICE CM16 Goals Alain Blondel 8 October MICE CM 16 Collaboration meeting 8-11 October 2006 at RAL Goals of the meeting thanks to John Cobb & Marco.
John Womersley Welcome Director of Particle Physics, CCLRC International Scoping Study Meeting, RAL April 2006.
MICE RF Workshop Alain Blondel MICE = critical R&D for neutrino factory and muon collider 1 neutrino factory: accelerate muons and store to produce.
MICE CC visit at CERN Alain Blondel 1   MICE The International Muon Ionization Cooling Experiment.
MICE CMPB Alain Blondel 1 Highlights on MICE.
Lithium Hydride Absorber Program Update Alan Bross MICE CM Sofia – October 5 th, 2010.
Alain Blondel -- After the ISS -- What did ISS achieve? 1. Established a « baseline » for the accelerator study 2. Rejuvenated simulation and study of.
MICE FAC open session Alain Blondel 1   MICE The International Muon Ionization Cooling Experiment.
29 September 2006M.Sakuda NuFact06 Asian Regional Outlook (Japan) -by Y.Kuno (Osaka) (1) SuperBeam (T2K) (2) J-PARC current upgrade plan (3) T2HK or T2KK.
Progress in the construction of the MICE cooling channel and first measurements Adam Dobbs, EPS-HEP, 23 rd July 2011.
CHIPP Aug 2010J.S. GraulichSlide 1 MICE and the Neutrino Factory Jean-Sebastien Graulich, Geneva.
- MICE - The Muon Ionization Cooling Experiment Jean-Sebastien Graulich, Univ. Genève o Introduction: Aims And Concept o Design o Infrastructure: Hall,
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
MICE RF review Alain Blondel 1   MICE The International Muon Ionization Cooling Experiment.
MICE CM32 Goals of the Meeting Alain Blondel 1 WELCOME TO MICE CM32! – Goals and Status - Many thanks to Victoria Blackmore, Stefania Ricciardi and Mary-Elizabeth.
Alain Blondel 4 March 2011 NEU2012 summary NEU2012: towards a concrete proposal by the neutrino community (emphasis on long baseline accelerator expts)
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
1 Status of the T2K long baseline neutrino oscillation experiment Atsuko K. Ichikawa (Kyoto univeristy) For the T2K Collaboration.
1 Neutrino detector test beam requirements 0. Disclaimer 1. News from the neutrino scene 2. Beam requirements for AIDA and others.
T2K Status Report. The Accelerator Complex a Beamline Performance 3 First T2K run completed January to June x protons accumulated.
ch/~bdl/lepc/lepc.ppt 1 MICE Status and Plans Rikard Sandström Université de Geneve International Scoping Study CERN,
MICE CM30 Goals of the Meeting Alain Blondel 1 MICE CM30 – Goals and Status.
MICE, Uni-Geneva and the transnational access to MICE (MICE-TNA)
(one of the) Request from MPB
MICE S TEP IV P HYSICS ‘D ELIVERABLES ’ V. Blackmore MAP 2014 Spring Meeting 30 th May, /15 AKA “What will we learn from Step IV?”
The MAP 3-Year Plan Mark Palmer Fermilab September 26, 2014.
K. Long, 28 June, 2016 Introduction to MICE — and the role of the Hydrogen Delivery System.
CM Nov 2009 DOES MICE NEED STEP III ? Somewhat hard to understand MICE Schedule… –If the gods are (un)kind it’s possible that SS1, SS2 & FC1 are.
MICE. Outline Experimental methods and goals Beam line Diagnostics – In HEP parlance – the detectors Magnet system 2MICE Optics Review January 14, 2016.
MICE. Outline Experimental methods and goals Beam line Diagnostics – In HEP parlance – the detectors Magnet system 2MICE Optics Review January 14, 2016.
MICE The International Muon Ionisation Cooling Experiment
MICE: First Beam Emittance Results w/Particle Detectors
Alain Blondel 11 October 2010 GDR NEU2012 summary
Presentation transcript:

MICE Project Board Alain Blondel 1 MICE running Preamble ISIS running Step I Step(s) IV Step V (and VI)

MICE Project Board Alain Blondel sin 2 2  13 90% C.L. new results from T2K (13 June) and MINOS (24 June) on   e appearance  indications that sin 2 2  13 is >0 old fit T2K MINOS note: different  CP axes!

MICE Project Board Alain Blondel 3 Needs confirmation but this is exciting for neutrino long baseline physics! Large values of sin 2 2  13 would give a chance for superbeams to have a shot at CP violation, but Neutrino Factory remains most precise and only device able to test oscillations very precisely -- precision measurements of angles and mass differences, -- tau appearance and unitarity tests -- detailed study of matter effects -- etc…  Physics is moving forward, no time to waste, Ionization cooling must be demonstrated

MICE Project Board Alain Blondel 4  Incoming muon beam Variable Diffuser Beam PID TOF 0 Cherenkov TOF 1 Trackers 1 & 2 measurement of emittance in and out Liquid Hydrogen absorbers 1,2,3 Downstream particle ID: TOF 2 KL, EMR RF cavities 1RF cavities 2 Spectrometer solenoid 1 Matching coils 1&2 Focus coils 1 Spectrometer solenoid 2 Coupling Coils 1&2 Focus coils 2Focus coils 3 Matching coils 1&2 10% cooling of 200 MeV/c muons requires ~ 20 MV of RF single particle measurements => measurement precision can be as good as  out /  in ) = never done before either…

MICE Project Board Alain Blondel 5 Quantities to be measured in a cooling experiment equilibrium emittance = 2.5 mm cooling effect at nominal input emittance ~10% curves for 23 MV, 3 full absorbers, particles on crest Measurements of TRANSMISSION EMITTANCE REDUCTION EQUILIBRIUM EMITTANCE for the standard Study II optics are the main deliverables beam line can deliver 3,,6,,10 mm (see Mark’s talk) other values can be reached by offline culling or reweighting

MICE Project Board Alain Blondel 6  MICE Steps STEP I STEP II STEP IV STEP V aim: April 2014 STEP VI STEP III/III.1 October March skip complete -- EMR comm.

MICE Project Board Alain Blondel 7 MICE RUNNING

MICE Project Board Alain Blondel 8 MICE Target -- Linear motor dips target at 80g -- in beam since Sept’09 571k dips -- reproducibility excellent -- tested regularly for reproducibility to test possible degradation. -- not-so-easy to build a second one that works that well!

MICE Project Board Alain Blondel 9 T2.X = linear motor 2, target mech. X motor 2 presumed inferior to motor 1 nevertheless almost there! Building two new linear motors with improved tolerances. Aim at having T3 and T4 targets to install in ISIS & Spare by end 2011

MICE Project Board Alain Blondel 10 MICE STEP I Superb data taking end 2009 and summer 2010! GOALS ACHIEVED See presentation by M. Rayner at FAC in Jan 2011 Rates limited by beam loss induced in ISIS.

MICE Project Board Alain Blondel required muon rate is ~50/200 per pulse without (stepI-IV)/with (StepV-VI) RF -- limitation is irradiation in ISIS due to beam losses induced by MICE target measured in Volts on Beam Line Monitors -- observed rates in MICE 2010 (6mm beam) 5 TOF1/ms/V_BLM for  - beam, 30 TOF1/ms/V_BLM for  + beam following a series of dedicated irradiation runs and measurements of activation ISIS allowed us to run routinely at 2V and even tried up to 10V. We are within range for STEPS I-IV further studies on how to get more muons per losses are ongoing (beam bump, timing, faster dip, etc..) muon rates

MICE Project Board Alain Blondel 12 High beam loss (up to 10 V) tests (14 Aug.) zhttps://micewww.pp.rl.ac.uk/elog/MICE+Log/1449https://micewww.pp.rl.ac.uk/elog/MICE+Log/1449 zhttps://micewww.pp.rl.ac.uk/elog/MICE+Log/1447https://micewww.pp.rl.ac.uk/elog/MICE+Log/1447

MICE Project Board Alain Blondel 13 How MICE Measures  in Step 1 (t0,x0,y0) (t1,x1,y1) TOF0 TOF1 Use TOF0 and TOF1 to determine phase space parameters of the muon beam Tof m 10 x 4cm scintillator bars  x = 1.15 cm  t = 50 ps Tof m 7 x 6cm bars  x = 1.73 cm  t = 50 ps Momentum-dependent matrix relates (t0,x0,y0,t1,x1,y1)  (t1,p,x1,x’1,y1,y’1) solved by iteration

MICE Project Board Alain Blondel 14  Measurement Result: Data vs MC Reconstructed transverse phase space of the baseline MICE beam (6-200) at TOF1 Data MC M.Rayner OxfordU y (mm) vs x (mm) x (mrad) vs x (mm)y (mrad) vs y (mm)

MICE Project Board Alain Blondel 15 STATISTICS See John Cobb MICE note 268: Statistical error on relative change of emittance is 1% with 10 5 muons Presently allowed running with beam loss of 2-3 V (assume 50  + /Spill) for STEP IV: 1 measurement = spills ~ 2 hours. (full matrix in 3 days) for step V and VI need 12 times more statistics (match RF phase!) 1 measurement = spills ~ 20 hours. We would aim at higher rates for step V, rate is sufficient for step IV

MICE Project Board Alain Blondel 16 ISIS running periods, MOM Rota and MICE runs in 2011 First semester Second semester

MICE Project Board Alain Blondel 17 EMR installed in MICE hall First 3 modules, running cosmics now. Start run on 30 June. Full detector to run in Feb 2012

MICE Project Board Alain Blondel 18 ISIS running Typical year consists of 5 ISIS ‘user runs’ of ~35 days each + run-ups, MP. 5 periods April 2013 to April 2014  priority to Step V installation Some additional step IV running not ruled out but lower priority Next Long Shut Down envisaged: Aug to February 2015 new target, full EMR LiH wedge + reserve no running Step IV Installation Step IV: empty/LH2/(LHe) no absorber flat LiH

MICE Project Board Alain Blondel 19  MICE Steps STEP I STEP II STEP IV STEP V STEP VI STEP III/III.1

MICE Project Board Alain Blondel 20 The point was raised (Cobb) that 1.. The optics of step III is not easy to match for conservation of emittance 2. The logistics of changing from Step III to step IV is not trivial. 3. we can execute the physics program of step III and step III.1 with the magnetic channel of step IV effect on Schedule is a balance = time gained by suppressing specific installation of step II and step III time lost by required push-pull operations in replacing solid absorbers >4 mo --vs-- 3 to 6 x 8 days = Winner! Skipping steps

MICE Project Board Alain Blondel 21 Amplitude Cooling... in empty channel Step 3 empty Step 4 empty Amp OUT Amp IN Amp OUT Amp IN 6mm beam, SigPz = 1 MeV/c, 100k muons (T.Carlisle)

MICE Project Board Alain Blondel 22 Clearly the optics of step III leads to ‘heating’ up to 5% (mis-beaviour of dispersive beam?) Step IV is much cleaner from this point of view (~0.2%)

MICE Project Board Alain Blondel 23 Step IV Time to install Step IV – 168 days (about six months) Step IV running time – ~10 days Time to substitute solid absorber in FC – 8 days Important assumptions at this stage: AFC module is ready and tested LH2 infrastructure in MICE Hall is ready Hayler, Nichols

MICE Project Board Alain Blondel 24 STEP IV  in  out 1.liquid H2 absorber, empty commission system, tracker, detectors, optics compare  in /  out for various values of momentum, emittance and beta function  systematic errors 2.liquid H2 absorber, full measure cooling properties of liquid Hydrogen At that point will have measured ionization cooling! can also measure LHe (lower priority) STEP IV configurations

MICE Project Board Alain Blondel 25 STEP IV configurations 3.Vacuum (only He and window for trackers) execute STEP III program; compare  in /  out  information on systematic error of final experiment information on effect of windows by comparison with STEP IV  in  out

MICE Project Board Alain Blondel 26 STEP IV configurations 4.Solid absorbers execute STEP III.1 program; compare track in /track out compare  in /  out for various values of momentum, emittance and beta function  information on emittance generating properties of materials STEP IV  in  out

27 The MICE Energy Absorber  New Hanger Arrangement  3 SS straps  1 Machined SS clamp  45 cm, t= 65 mm Y12 is producing the LiH Produced by Hot Isostatic Pressing (150 oC, 30,000 psi) Final parts will be Tested for Chemical composition and purity Radio-graphed to ensure no voids Machined to size Dimensional inspection Coated with epoxy completely

MICE Project Board Alain Blondel 28 Absorber measurements thickness  10 MeV energy loss will measure: Liq H2 330 mm LiH 65 mm Also possible (used in NuFACT beams) Liq He 410 mm Be 34 mm Al 23 mm with low priority: Plastic 50 mm Fe 9 mm Cu 8 mm Will study wedge absorbers (change 6D emittance)

MICE Project Board Alain Blondel 29 Step V STEP V “sustainable” cooling: cooling happens in the absorbers but production of cool beam requires acceleration with RF cavities old simulation (at 88MHz) RF phase E out -E in -1- running with shutters to commission RF cavities (no beam needed) -1’- running with LH2 and RF first with no beam to check RF noise -2- running with beam with no RF and no LH2 to check optics -3- running with beam with LH2 no RF -4- running with beam with LH2 and RF -5- or running with solid absorbers? limited in optics and performance  step VI!

Slide 30 FINAL COMMENTS Steady progress towards demonstration of Ionization Cooling Already demonstrated validity of beam line principle and emittance measurements with particle detectors On daily basis: LHe test of LH 2 system, 1MW in RF unit, EMR prototype, SS repair plan, etc… Progress on global MICE Project management (Thanks Andy!)  On solid ground for running step IV in Oct. 2012, aiming to start step V in 2014 before long shutdown (tough but everyone on board!) Looking forward to significant cooling measurement results!

Slide 31 T2KK: T2K 1.66 MW beam to 270 kton fid volume Water Cherenkov detectors in Japan (295km) and in Korea (1050 km); DUSEL: a WBB from Fermilab to a 300 kton WC in Dusel (1300km); SPL 4 GeV, EU-BB and BB+SPL: CERN to Fréjus (130km) project; NF bl is the Neutrino Factory baseline (4000km and 7000km baselines) and NF Py+INO represents the concrete baseline from CERN to Pyhasalmi mine in Finland (2285 km) and to INO in India (7152 km); PS2-Slanic is a preliminary superbeam study at 1500km based on an upgrade of PS2 to 1.66MW and a 100kton Liquid Argon TPC CERN – SPC panel report, SPC meeting, Figure 2 A representative compilation of sensitivities of some future long baseline projects. Here the fraction of  CP where CP violation can be observed at 3 standard deviations is plotted as a function of  13.

Slide 32 From IDS-NF Intermediate Design Report IDR

Slide 33 High-power target. 4MW. good transmission MERIT experiment (CERN) Major challenges tackled by R&D expts Fast muon cooling MICE experiment (RAL) Fast, large aperture accelerator (FFAG) EMMA (Daresbury)