Engineering 100: Bridge Project Group 6 (Team Bacardi) Jon Honari, Kevin Lam, Otis Chantharangsy, Ivee Ilao Group 6 (Team Bacardi) Jon Honari, Kevin Lam, Otis Chantharangsy, Ivee Ilao
Presentation Outline Design Ideas Prototype Bridge Process Testing/Results Prototype Analysis Flaws Improvements Design Ideas Prototype Bridge Process Testing/Results Prototype Analysis Flaws Improvements Final Bridge Design Testing/results Final Results Graph Analysis Failures Conclusion Final Bridge Design Testing/results Final Results Graph Analysis Failures Conclusion
Design Arch Design Proved to be strongest structure based on our research Base Flat and straight Supports Angle supports Evenly distributed force Arch Design Proved to be strongest structure based on our research Base Flat and straight Supports Angle supports Evenly distributed force
Prototype Design
Prototype Process Arch Supports Road Connections Structural Reinforcements Arch Supports Road Connections Structural Reinforcements
Prototype Process
Prototype Testing/Results
Prototype Analysis Flaws Uneven weight distribution Not supported where bridge met jig Ultimate reason for failure Weak road Sloppy design Unnecessary weight Flaws Uneven weight distribution Not supported where bridge met jig Ultimate reason for failure Weak road Sloppy design Unnecessary weight
Prototype Flaws Red: Excess WeightGreen: Lack of Support
Final Design Excess weight was removed Top section was more reinforced Used wood glue instead of hot glue for the majority Made sure weight was distributed evenly Reinforced the legs where the bridge met the jig Added more supports Excess weight was removed Top section was more reinforced Used wood glue instead of hot glue for the majority Made sure weight was distributed evenly Reinforced the legs where the bridge met the jig Added more supports
Prototype vs. Final Design Final BridgePrototype
Final Design (Completed)
Final Testing/Results
Final Design Failure Important joints were overlooked and were not supported correctly
Final Analysis Overall, very good improvement Bridge weighed 0.59 lbs Bridge held lbs Performance = Successful With more supports in the correct places we believe the bridge could hold much more weight Overall, very good improvement Bridge weighed 0.59 lbs Bridge held lbs Performance = Successful With more supports in the correct places we believe the bridge could hold much more weight
We conclude… Spending more time on the construction yielded better results About 170% improvement High efficiency ratio Endures a high amount of pressure Lasts under consistent amount of low pressure First Bridge:.56 pounds, held lb Final Bridge:.59 pounds, held lb Spending more time on the construction yielded better results About 170% improvement High efficiency ratio Endures a high amount of pressure Lasts under consistent amount of low pressure First Bridge:.56 pounds, held lb Final Bridge:.59 pounds, held lb