Entergy Transmission Planning Summit New Orleans, LA July 31, 2007

Slides:



Advertisements
Similar presentations
Southwest Rhode Island Transmission Supply Study Long Term Needs and Solutions.
Advertisements

October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
March 6, 2008 Technical Advisory Committee Luminant Energy & Oncor Tyler Grande Autotransformer Addition and 138 kV Line Upgrade Project Jay Teixeira Manager,
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Regional Planning Group Project
Entergy Transmission Planning Summit New Orleans, LA July 10, 2003
La Crosse 161 kV Capacitor Addition Northern MAPP Subregional Planning Group April 3, 2007 Daniel Kline.
Entergy Louisiana, LLC (North) 2010 to 2012 Draft Construction Plan
1 Entergy Louisiana, Inc. (North) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Oncor Electric Delivery Company LLC TOGETHER WE DELIVER ODESSA UPDATE Jan 22, 2013 Presentation to ERCOT Regional Planning Group Austin, TX Mike Juricek.
1 1 Substation Asset Strategy Kevin Dasso, Senior Director Engineering and Operations IEEE/PES Annual Substations Committee Meeting April 7, 2008.
ICT 2011 Reliability Assessment and Construction Plan Evaluation Entergy Transmission Summit August 11, 2010 Sheraton New Orleans, Louisiana.
1 Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
© 2000 PACIFICORP | PAGE 1 WYOMING WEST AREA STUDY DECEMBER 2013 Seongtae Kim/Jeremy Viula.
1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit.
Xcel Energy Smaller Scale Transmission Projects Northern MAPP Subregional Planning Group April 3, 2007 Srinivas Vemuri, Jason Standing, and Daniel Kline.
New Richmond Load Serving Study Northern MAPP Subregional Planning Group August 16, 2006 Daniel Kline.
Entergy Transmission Planning Summit New Orleans, LA July 8, 2004
Jan 13, 2012 RPG Meeting El Campo – Vanderbilt 69 kV Project – Status report Ehsan Ur Rehman Planning Engineer ERCOT.
George Bartlett Director, Transmission Operations Economic Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting December 16, 2009.
1 Update on the 2006 Transmission Study LPSC B&E Meeting Baton Rouge, LA November 29, 2006.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Transmission Planning Summit.
1 Entergy Texas, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
Lyndonville Electric Department Feasibility Analysis Review December 2,
1 Entergy Arkansas, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Aug 17, 2012 RPG Meeting KEC & MEC – Load Addition Project – ERCOT Independent Review Ehsan Ur Rehman Planning Engineer ERCOT.
ISTEP Phase II Final Report Summary LTTIWG Meeting – January 27, 2009 Douglas Bowman, PE Lead Engineer, ICT Planning
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Local Area Study Local Area Study Mitigation Plan Update and Uncertainty Scenarios
1 Stability Issues in Entergy System Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
1 Entergy Gulf States Louisiana, L.L.C. Proposed Transmission Reliability Projects.
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
1 Entergy Louisiana, Inc. (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
1 Entergy Louisiana, Inc. (South) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting November 19, 2008.
1 Entergy Louisiana, Inc. (North) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Jeff Billo Manager, ERCOT Transmission Planning Kenedy to Nixon to Seguin Line Upgrade Project Regional Planning Group (RPG) Review; ERCOT Independent.
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
1 New Orleans, LA July 31, 2007 Randy Helmick Vice President, Transmission Business Entergy Transmission Planning Summit.
Glades Electric Cooperative Infrastructure Miles of Line 2,213  Overhead Dist.2,180  UndergroundDist. 33  Transmission 87 16,402 meters Average 7.
Transmission Capital Project Updates. Transmission Expansion Plan Sigurd to Red Butte 345 kV line in-service May, 2015 Permitting activities continue.
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
Jeff Billo Manager, Transmission Planning
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
2006 Preliminary Reliability Study Results Bryan Guy September 7, 2006.
1 Entergy Gulf States, Inc. (Texas) Approved & Proposed Transmission Reliability Projects Entergy/ETEC Subcommittee Meeting The Woodlands, TX November.
1 New Orleans, LA July 29, 2008 Randy Helmick Vice President, Transmission Entergy Services Inc. Entergy Transmission Planning Summit.
Freeport Area Master Plan Project
Barrilla Junction Area Transmission Improvements Project
Rocky Mountain Power Five Year Study Findings & Kick Off Meeting
Strategic Plan and Economic Upgrade Process
Presentation transcript:

Entergy Transmission Planning Summit New Orleans, LA July 31, 2007 Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007

Approved 2007 & Proposed 2008-2012 ELL-South/ENOI Transmission Reliability Projects Hammond-Amite: Convert to 230kV (2007 ISD) Loblolly-Hammond: Build 230kV line (2011 ISD) DSG – Planned Carryover Phase I (completed 2004) Phase II (complete 2005) Phase III (2011 ISD) Napoleonville: Install Cap Bank (2010 ISD) Paterson: Restore 4 breakers (2008 ISD) Improve ASI Capability: Planned Carryover Phase I - Conway-Panama (completed 2005) Phase II- Panama-Dutch Bayou (2009 ISD) Phase III- Coly-Vignes (2009 ISD) Conway-Bagatelle(2009 ISD Peters Rd-Oakville : Build 230kV line & Station (2011 ISD) Oakville-Alliance: Build 230kV line & Auto (2012 ISD) ELL-South

Hammond-Independence-Amite 115kV: Convert to 230kV Scenario: The Hammond-Independence-Amite 115kV line is limited by the Hammond 230/115 kV, 168 MVA autotransformer and an 800 Amp circuit breaker at Amite. This circuit overloads for a single contingency loss of the Franklin-McKnight 500kV line or the loss of the Bogalusa-Franklinton 115 kV line. Solution: Convert the Hammond-Independence-Amite 115 kV line to 230 kV operation (line constructed to 230kV) and build a new Independence 230kV substation. Install a 230/115 kV, 400MVA autotransformer at Amite and remove the autotransformer at Hammond. Expected In-Service Date: By year end 2007 NOTE: This project needs to be in place prior to the Loblolly-Hammond 230kV line. Otherwise, overloads cited above will be exacerbated. Estimated Cost: $18 MM ELL-South 17

Hammond-Independence-Amite 115kV: Convert to 230kV McKnight To Franklin To SOCO’s Plant Daniel To Coly To Fancy Point Convert to 230kV ELL-South 1

Paterson: Restore 4 Breakers Scenario: Paterson substation was flooded during Hurricane Katrina resulting in all major transmission equipment being damaged. Prior to Katrina, Paterson 115kV bus terminated four 115kv transmission lines and operated as a hub for the transmission system in the New Orleans area. Presently, the Paterson 115kV bus has been temporarily restored to operate in a split, east / west bus configuration. The east bus is in series with the Chalmette 115kV and the Sherwood Forest 115kV substations. The west bus is in series with the Claiborne 115kV and the Pontchartrain Park 115kV substations. Various single contingencies in the New Orleans area now could result in overloads on portions of this west bus circuit. Recommended Solution: Re-build the Paterson 115kV substation to terminate four 115kV transmission lines from Pontchartrain Park, Sherwood Forest, Chalmette and Claiborne. The bus configuration should be configured in a double bus with shared breaker configuration (breaker and a 1/2). This arrangement will allow for station expansion, including power transformer additions and potentially the addition of a 230/115kV auto transformer as system conditions dictate. Proposed In-Service Date: 2008 Estimated Cost: $3 MM ENOI 17

Paterson: Restore 4 Circuit Breakers Restore Breakers

Napoleonville: Install Capacitor Bank Scenario: Entergy Louisiana serves load in portions of Iberville, Assumption and LaFourche Parishes from a 115kV transmission line traversing these parishes. The line includes the Addis, Plaquemines, McCall, Paincourtville, Napoleonville and Raceland substations. A single contingency loss of either the Addis 230/115kV autotransformer or the Addis to Plaquemines 115kV line results in depressed voltages from Plaquemine to Paincourtville. Recommended Solution: Install a 21.6MVAr capacitor bank at Napoleonville 115kV substation. Proposed In-Service Date: 2010 Estimated Cost: $850 k ELL-South 17

Napoleonville: Install Capacitor Bank Install Cap Bank

Loblolly-Hammond: Construct 230 kV Substation and Line Scenario: Entergy’s transmission system north of Lake Pontchartrain is primarily supported from the ELL 230kV system between Willow Glen and Waterford. Loss of the Franklin-McKnight 500kV line, or certain other transmission contingencies, causes overloads on the underlying transmission system, primarily on the Gypsy-Madisonville 230kV line. Adding another 230kV source from a location north of Willow Glen reduces loading on the existing system and improves load serving capability north of Lake Pontchartrain and into south Mississippi. Recommended Solution: Construct 230 kV line from Coly to Hammond using existing Coly–Loblolly 69 kV line (constructed for 230kV). Construct Coly-Loblolly 69 kV line to maintain existing loop service to Loblolly. Proposed In-Service Date: 2011 NOTE: This line cannot be connected until the Hammond-Amite line is converted to 230 kV operation. Estimated Cost: $75 MM ELL-South 17

Coly-Hammond: Build 230 kV Line To Franklin To Fancy Point McKnight To SOCO’s Plant Daniel To Coly Build new 230kV line Coly ELL-South / EGSI-LA 1

ASI Improvement Plan - Phases 2 & 3 Scenario: When generation in the Amite South area is low, loss of the Waterford–Willow Glen 500 kV line is the most severe contingency that establishes the Amite South Import (ASI) capability. The ASI capability improved to approximately 2,450 MW upon completion of Phase 1 of the ASI Improvement Plan (Conway-Panama) in 2005. Phase 2 (Panama-Dutch Bayou) and Phase 3 (Coly-Vignes, Conway-Bagatelle) were expected to provide economic benefits and were to be completed by 2007 prior to Hurricane Katrina. Post Hurricane Katrina and the subsequent loss of load within southeast LA, Phases 2 and 3 were determined to be needed for reliability by 2015 or by 2010 for economics. Through the 2006 Transmission Study, Entergy determined that accelerating Phases 2 & 3 could yield economic benefits sufficient enough to advance the in-service dates to earlier than 2010. Recommended Solution: Recommence the construction of Phases 2 & 3. Proposed In-Service Date: 2009 (Phases 2 & 3) Estimated Project Costs: Phase 2: $38 MM Phase 3: $20 MM ELL-South / EGSI-LA 17

ASI Improvement Plan - Phase 2 Panama Build 230kV line ELL-South 1

ASI Improvement Plan - Phase 3 Coly Vignes Panama Upgrade 230kV line Upgrade 230kV line ELL-South / EGSI-LA 1

Downstream of Gypsy (DSG) Area Scenario: During high load conditions, the loss of certain generation within the DSG area results in inadequate voltage support and thermal overload to area lines. To address the voltage and thermal reliability issues, Entergy proposed the following projects. Recommended Solution: Phase 1, completed in 2004, installed one 151.2 MVAr capacitor bank at Ninemile 230kV and two 84.6 MVAr capacitor banks at Michoud 230kV. Phase 2, completed in 2005, constructed multiple projects across the DSG area. Phase 3, includes various upgrades, system reconfigurations and a voltage conversion in the DSG area. See next slide. Based on current load projections within the DSG area, the DSG Phase 3 projects are expected to be in service by 2011. However, this in-service date could change depending upon the location and rate of load return within the New Orleans metro area. Through the 2006 Transmission Study, Entergy determined that accelerating Phase 3 would not yield economic benefits sufficient enough to advance the in-service date. ELL-South / ENOI 17

2011 DSG Area Transmission Improvements Phase 3 Upgrade 115 kV line segment (Little Gypsy-Claytonia) Upgrade Waterford-Gypsy river crossing #2. Re-terminate reactor on to Waterford–UCC 230kV line Reconfigure Hooker–Waterford 230kV loop into Hooker–Little Gypsy 230kV Upgrade / convert one Gypsy-Luling 115kV double circuit line segments to 230 kV from Waterford to Luling (bypass Luling) Convert Luling-Waggaman-Ninemile 115 kV to 230 kV. Replace underrated switches and breakers. Convert Waggaman Substation to 230kV. Replace under-rated 115kV breakers at Little Gypsy Rebuild Luling-American Cyanamid 115 kV Install 108 MVAr of capacitor banks at Paterson and Snakefarm ELL-South / ENOI

Southeast Louisiana Coastal Improvement Plan: Construct New Peters Road-Oakville-Alliance 230 kV Line Scenario: The primary transmission sources to lower Lafourche, Lower Jefferson, and Plaquemines Parishes are the Ninemile and Valentine substations. Although lower Plaquemines Parish experienced heavy damage during Hurricane Katrina, it is expected that oil refining and pumping facilities in the area will be restored. Additionally, upper Plaquemines Parish, including Belle Chasse and the Naval Air Support facility, is experiencing growth. For the contingency loss of the Ninemile-Barataria 115kV or the Valentine-Clovelly 115kV lines, potential low voltages and line overloads exists. Recommended Solution: Peters Road-Oakville 230kV Build a new 230kV substation at Oakville and a new radial 230kV line from Peters Road to Oakville Substation. Proposed In-Service Date: 2011 Estimated Cost: $21.3 MM Oakville-Alliance 230 kV Construct a new 230kV transmission line from Oakville substation to Alliance substation. Add a 150MVA 230/115kV auto at Alliance substation. This project also provides support for the Fourchon area. Proposed In-Service Date: 2012 Estimated Cost: $35 MM ELL-South 17

Build 230kV Line & Sub Build 230kV Line & Auto Build 230kV Line & Auto Peters Road-Oakville 230kV: Build new line and substation Oakville-Alliance 230 kV: Build new line Peters Rd. Oakville Build 230kV Line & Sub Build 230kV Line & Auto Build 230kV Line & Auto ELL-South

ELL-South and ENOI Target Areas 2012 and Beyond Bogue Chitto: Build 500kV Switching Station and 500kV Line Paterson: Install 230/115kV auto Golden Meadow - Fourchon: Build 115kV Line