Paul drumm; 3rd December 2004; AFC MM 1 Why? Goal: Ultimate (CCLRC defined) Safety & Design Review –How do we get there? We need a Process –What is needed?

Slides:



Advertisements
Similar presentations
MICE: Hall Infrastructure Chris Nelson CEng CM15 8 th June 2006.
Advertisements

Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
AFC engineering group meeting on the 26 th of Jan 2004 MICE Absorber Focus Coil work schedule for the next 6 months By Wing Lau, Oxford.
On MICE Coordinate System Yury Ivanyushenkov RAL.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 paul drumm; ; FAC-PR MICE Project Status Funding Agency Committee 19 th September 2005.
March 2003 Paul Drumm MICE Collaboration Meeting, CERN 1 Beam Line & Installation Plans Paul Drumm CLRC Rutherford Appleton Laboratory.
MICE Safety Review Process and Schedule Elwyn Baynham Tom Bradshaw Iouri Ivaniouchenkov Columbia Meeting June 2003.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
paul drumm; 3rd December 2004; AFC MM 1 Cost & Schedule Review I Terms of reference: –To review the Cost and schedule of the MICE Muon beam –To review.
1 RAL Integration Issues MICE Collaboration Meeting, Osaka, August 1-3, 2004 Elwyn Baynham, Paul Drumm, Yury Ivanyushenkov, Tony Jones RAL.
Gateway process Gateway Process: ‘owned’ by UK Office of Science and Technology Essentially the mechanism by which UK involvement in large projects gets.
1 MICE Radiation Shutter Description Present status Plans, schedule and remaining work MICE CM26, 24-27th March, 2010.
MICE Project Report Paul Drumm ~ Sunday August 1 st 2004.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 MICE Project Report, paul drumm, 9 march 2005 CM Highlights & Tasks… –Tracker base line – scintillating fibres – performance validated –TOF performance.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
MICE Collaboration meeting RAL 21 – 24 Oct 2005 Summary of Design & Safety review progress By Wing Lau – Oxford University.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
1 MICE Hall Layout MICE Collaboration Meeting, LBNL, February 12, 2005 Paul Drumm for Yury & the RAL team.
MICE Collaboration Meeting Harbin, China 13 – 17 January 2009 Integration Issues By Wing Lau, Oxford University.
Purpose of the Standards
Conducting the IT Audit
IAEA International Atomic Energy Agency Human Resources Development for Nuclear Safety J. Bastos NSNI/RAS.
SHE Code 34: Electrical Safety Safety, Health and Environment (SHE) Group.
MICE VIDEO Conference 17 th December 2003 Report on AFCSWG Safety Review -- Future Plan By Wing Lau -- Oxford.
APPRAISAL OF THE HEADTEACHER GOVERNORS’ BRIEFING
Introduction to ISO New and modified requirements.
Main progress on Design & Safety Review: EmCAL -- Received the revised TRD write up from Ludovico Design & Safety Audit sheets need to be revised to correspond.
MICE Status (with a UK slant) Paul Drumm, MICE Collaboration UK-NF June 2003.
OHT 25.1 Galin, SQA from theory to implementation © Pearson Education Limited 2004 The quality assurance organizational framework Top management’s quality.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
MICE Collaboration Meeting Frascati 26 – 29 June 2005 Work Group report On Design & Safety Review.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
© 2006 Cisco Systems, Inc. All rights reserved.Cisco Public 1 Version 4.0 Gathering Network Requirements Designing and Supporting Computer Networks – Chapter.
Hydrogen Delivery System Schedule MICE Schedule Review 23 rd -25 th May 2011 M Hills STFC.
RSSO refresher meeting J. Pedersen M. Tavlet, T. Otto.
1 MICE Collaboration meeting at Berkeley 9 – 12 February 2005 Integrated Design & Safety Review Presented by Wing Lau & Paul Drumm.
APPRAISAL OF THE HEADTEACHER GOVERNORS’ BRIEFING.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Internal environmental audit procedure Purpose: To ensure that the environmental management system is used and is effective Scope: The entire environmental.
1 MICE Radiation Shielding MICE Phone Conference, 28 January 2004 Yury Ivanyushenkov Engineering Department, RAL.
Design & Safety Review Work Group meeting 10 March 2005 Progress update Wing Lau, Oxford.
Hall clearance completed Revisiting Water & Cryo Plant Prepare for shutdown ’04 –beam tube –Contract hole cutting Negotiating with DF to help target work.
MICE Collaboration Meeting Frascati 26 – 29 June 2005 Work Group report On Design & Safety Review.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
WBS ? Proposed by IPRP … –Preparation for a review –MICE Costs & Time Scales need to be more accurate & Justified –Technical Leaders arranged by technology.
1 Status of infrastructure MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 How the Muon Ionization Cooling Experiment Found a Home MICE hall at RAL in Spring
1 MICE UK meeting at RAL 05 May 2005 Integrated Design & Safety Review Presented by.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 paul drumm; Date; Title …project report …more comments paul drumm february 2005.
Rob Connatser NSS Instrument Work Packages and XLPM.
Status of the MICE Construction Project
Introduction Jason Tarrant – Integration Engineering Step IV Removal
Cisco Lifecycle Services Advanced Security Exam Code: practice-questions.html.
SHE Code 34: Electrical Safety
1 Stadium Company Network. The Stadium Company Project Is a sports facility management company that manages a stadium. Stadium Company needs to upgrade.
Presentation transcript:

paul drumm; 3rd December 2004; AFC MM 1 Why? Goal: Ultimate (CCLRC defined) Safety & Design Review –How do we get there? We need a Process –What is needed? Full Safety & Design assessment –How do we ensure success? Assessment within MICE but outside of the working groups Propose Design & Safety Working Group –Based on group involved in AFCSWG¹ –Expanded to cover all MICE – in a timely manner ¹ but with fewer letters – easier to repeat!

paul drumm; 3rd December 2004; AFC MM 2 AFCSWG – as was Original Concept for Absorber and Hydrogen System Process* heavy for most of MICE Ultimate goal stands *

paul drumm; 3rd December 2004; AFC MM 3 Morph to D&SWG… Role of existing working groups unchanged Character and role of the “review panel” is different: –Internal “audit” process unless D&SWG advises that an independent review is needed (matter of risk & competence within MICE) –D&SWG guides documentation preparation through a series of audits –D&SWG to assess the documentation Not the same as a review (less overhead) –Informs TB & EB on readiness for final review

paul drumm; 3rd December 2004; AFC MM 4 From Document... to Presentation by Video? Task Leader Task Members Process Wing Design & Safety Group Agree Procedure Develop Concepts & Design Prepare documentation Review fit for purpose Documents ok Pre-manufacture Acceptance Document Review Review FINAL Document Audit Detail Design & Safety… Manufacture & Install Operate Rehearsal RAL Review RAL Audit & Advise Support Audit & Advise You are here! Agree when ready Invitees? Task Leader Task Members Task Leader Task Members Advice?

paul drumm; 3rd December 2004; AFC MM 5 Phase 1 Time Scales Beam Line needs to be in place end of 2006 –Complete beam line review by end 2005 –Radiation shielding is a more delicate matter –Target is a potential risk to ISIS operations –Beam Line is (probably low risk) ISIS/EID engineering staff Following established & proven practices Spectrometer & Tracker –Low risk R&D activities –Medium - Potentially High – design to achieve Low Risk