GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 1 GLAST Large Area Telescope LAT Pre-Shipment Review Systems.

Slides:



Advertisements
Similar presentations
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 5 of 12 Subsystem Acceptance 1 GLAST Large Area Telescope Pre-Environmental.
Advertisements

© 2007 General Dynamics. All rights reserved. Integrated Space Systems 1196 EB-R GLAST Pre-Ship Review (PSR) LAT Payload I&T Review CONTRACT NO.
GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
GLAST LAT Project June 6, 2007 NCRs and Waivers 1 GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall.
GLAST LAT ProjectGSFC Monthly, 15 Dec 2003 LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering.
GLAST LAT Project Aug 1, 2007 NCRs and Waivers 1 GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems.
Tracker Subsystem1 GLAST LAT Project FM7/9 PSR, Sept. 9, 2005 GLAST LAT Tracker Tower7/9 Pre-Ship Review INFN-Pisa.
GLAST LAT ProjectDOE Rebaseline Review, February 13, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Chief Engineer.
GLAST LAT Project Oct 5, GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems Engineering.
Tracker Subsystem1 GLAST LAT Project FM4/5 PSR, May 31, 2005 GLAST LAT Tracker Tower-4/5 Pre-Ship Review INFN-Pisa.
GLAST LAT ProjectGSFC Monthly, 5 January 2005 LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering.
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR-01967Section 15 Manufacturing & Processes 1 GLAST Large Area Telescope Manufacturing.
GLAST LAT Project4 April 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectSLAC Pre - Baseline Review, April 16, 2002 ` 1 GLAST Large Area Telescope: I&T Overview WBS: Elliott D. Bloom Stanford Linear Accelerator.
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
GLAST LAT ProjectMay 25, 2006: Pre-Environmental Test Review LAT Test Verification Process Presentation 4 of 12 GLAST Large Area Telescope Gamma-ray Large.
GLAST LAT Project28 March 2005 LAT System EngineeringLAT Test Planning Meeting GLAST LAT GLAST LAT System Engineering Gamma-ray Large Area Space Telescope.
ISOC Peer Review - March 2, 2004 Section GLAST Large Area Telescope ISOC Peer Review Test Bed Terry Schalk GLAST Flight Software
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
GLAST LAT Project Oct 5, GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems Engineering.
Tracker Subsystem1 GLAST LAT Project FM6 PSR, July 21, 2005 GLAST LAT Tracker Tower6 Pre-Ship Review INFN-Pisa.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
GLAST LAT Project May 2, 2007 NCRs and Waivers 1 GLAST Large Area Telescope Systems Engineering Test Status, NCRs and Verification Status Pat Hascall Systems.
GLAST LAT ProjectPDU/GASU MRR, February 3, DAQ & FSWV1 1 GLAST Large Area Telescope: B. Estey, G. Haller SLAC xxxx LAT Quality Engineer
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 3 of 12 SE Overview 1 GLAST Large Area Telescope Pre-Environmental Test Review.
GLAST Large Area Telescope LAT Flight Software System Checkout TRR Current Status Sergio Maldonado FSW Test Team Lead Stanford Linear Accelerator Center.
GLAST Large Area Telescope:
GLAST LAT ProjectDOE/NASA Mechanical Systems Peer Review, March 27, 2003 Document: LAT-PR-0XXXX Section 6.0 Subsystem Verif. Test Plan 1 GLAST Large Area.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
GLAST LAT ProjectCDR/CD3 Review May 12-16, 2003 Document: LAT-PR-01967Section XX 1 GLAST Large Area Telescope: LAT System Engineering WBS Dick Horn.
GLAST LAT ProjectI&T&C Pre PDR, October 2, 2001 E. do Couto e Silva1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
GLAST LAT ProjectCDR/CD3 Review May 12-16, 2003 Document: LAT-PR Section 15 Manufacturing Process 1 GLAST Large Area Telescope Manufacturing Process.
GLAST LAT Project – Cost and Schedule ReviewJanuary 27, 2004 AntiCoincidence Detector 1 GLAST Large Area Telescope: Cost/Schedule Review January 27, 2005.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware December 2004 Status Marc Campell, Subsystem Manager.
GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 8 of 12 Thermal Vacuum Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review.
GLAST LAT Project April 27, 2006: LAT Pre-Ship Review Presentation 3 of 12 SE Overview 1 GLAST Large Area Telescope LAT Pre-Shipment Review Systems Engineering.
GLAST LAT ProjectSeptember 15, 2006: Pre-Shipment Review 1 Integration and Test Presentation 11 of 12 GLAST Large Area Telescope: LAT Pre-Shipment Review.
Reliability Assessments Scope Per paragraph of the MAR and PAIP “ When necessary/prudent or when agreed upon with the GSFC Project Office, Glast.
GLAST LAT ProjectMonthly Status Review – June 30, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT ProjectLAT Muons at NRL 28 Feb 2006 J. Eric Grove Naval Research Lab Washington DC LAT Muon Data Taking During Environmental Test at NRL J. Eric.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST Large Area Telescope LAT Flight Software System Checkout TRR Systems Engineering Mike DeKlotz GSFC Stanford Linear Accelerator Center Gamma-ray Large.
GLAST Large Area Telescope LAT Flight Software System Checkout TRR Test Suites (Backup) Stanford Linear Accelerator Center Gamma-ray Large Area Space Telescope.
GLAST LAT ProjectDOE/NASA Stratus Review, March 30 & 31, 2004 Systems Engineering 1 GLAST Large Area Telescope: Pat Hascall SLAC System Engineering Manager.
GLAST LAT ProjectGSFC Monthly, 24 May 2005 LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering.
GLAST LAT ProjectCDR/CD-3 Review May 12-16, 2003 Document: LAT-PR Section 5 IOC Subsystem 1 GLAST Large Area Telescope: IOC Subsystems WBS: 4.1.B.
GLAST LAT ProjectDOE/NASA Baseline-Preliminary Design Review, January 8, 2002 Document: #1 GLAST Large Area Telescope: I&T Overview Elliott D. Bloom Stanford.
GLAST LAT ProjectFace to Face, 14 April 2004 LAT System Engineering 1 GLAST Large Area Telescope: EGSE and Interface Verification Pat Hascall SLAC System.
GLAST Large Area Telescope Instrument to Spacecraft Interface Simulator (ISIS) Test Readiness Review 15 December 2004 Jana Thayer Eric Hansen Stanford.
SwCDR (Peer) Review 1 UCB MAVEN Particles and Fields Flight Software Critical Design Review Peter R. Harvey.
GLAST LAT ProjectPeer Review & CDR Preparation Document: LAT-PR Preparation Schedule Subsystems Peer Reviews –ACD January 7-8, 2003 –CALMarch.
GLAST LAT ProjectDOE/NASA Peer Critical Design Review, March 19-20, 2003 D. Nelson 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Instrument.
GLAST LAT ProjectSLAC Internal Review, April 16-18, 2002 LAT-PR Electronics and Flight Software WBS GLAST Large Area Telescope: Electronics,
GLAST LAT Project May 25, 2006: Pre-Environmental Test Review Presentation 11 of 12 Thermal Vacuum Test 1 GLAST Large Area Telescope LAT Pre-Shipment Review.
EMI/EMC GLAST Large Area Telescope LAT Pre-Shipment Review
GLAST Large Area Telescope:
GLAST Large Area Telescope
GLAST Large Area Telescope:
Electrical Ground Support Equipment Verification Test Support
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Thermal Vacuum Test: Plans and Procedures
GLAST Large Area Telescope:
GLAST Large Area Telescope:
GLAST Large Area Telescope
Introduction and Overview
Overview Cost to Complete
Integration & Test Instrument Operations Coordination
GLAST Large Area Telescope:
Presentation transcript:

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 1 GLAST Large Area Telescope LAT Pre-Shipment Review Systems Engineering Pat Hascall Systems Engineering Stanford Linear Accelerator Center Gamma-ray Large Area Space Telescope

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 2 LAT System Engineering Overview Requirements Baseline Maintenance –Specifications –Interface Control Documentation –Waiver Requests (See Section 10) Design Baseline Maintenance –Design Documentation Configuration Management –Design Changes Since PER Requirements Verification Plan (See Section 5) –Traceability to tests, analysis, inspection –Running Sell Process with GSFC Project Office

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 3 Documentation Status The SE related documentation: see next chart (s) –LAT Specification Current –Traceability to verification complete –Verification Cross Reference Matrix Released –LAT Test Plan Released –Three pending changes to LAT-S/C ICD: See later chart –Several Waivers in Process: See NCRs and Waivers –One pending requirement update in 433-IRD-0001 I&T documentation status: See I&T presentation QA documentation status: See QA presentation No significant documentation liens

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 4 Documentation Status (continued) RFAs from previous reviews –See Systems Engineering Web site for dPDR, PDR, and CDR RFA closures glast.slac.stanford.edu/systemengineering/RFAS/RFAS.htmhttp://www- glast.slac.stanford.edu/systemengineering/RFAS/RFAS.htm –Two PER RFA’s open #1: Alignment Verification –Response: Updated response provided #8: NCR/Waiver Review for Unidentified Current and Residual Risks –Response: LAT project/NASA review and update included in this package

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 5 Key Documentation Mission Level Documents 433-SRD-0001: GLAST Science Requirements Document 433-IRD-0001: GLAST Science Instrument – Spacecraft Interface Requirements Document 433-SPEC-0001: GLAST Mission System Specification 433-OPS-0001: GLAST Operations Concept 433-MAR-0001: Mission Assurance Requirements (MAR) for GLAST LAT 433-RQMT-0005: GLAST EMI Requirements 433-ICD-0001: GLAST LAT-GBM Burst Interface Control Document 1196 EI-Y46311: SC-LAT Interface Control Document 1196 EI-S46310: 1553 Interface Control Document LAT Level Documents LAT-SS-00010LAT-SS-00010: LAT Performance Specification LAT-SS-00778LAT-SS-00778: LAT Environmental Specification LAT-SS-00115LAT-SS-00115: Mechanical Subsystem Specification (in final release cycle) LAT-SS-00715LAT-SS-00715: TCS Performance Specification LAT-SS-00019LAT-SS-00019: Trigger & Dataflow Subsystem Specification LAT-TD-00399LAT-TD Software Requirements Specification LAT-SS-00016LAT-SS-00016: ACD Subsystem Specification LAT-SS-00017LAT-SS-00017: Tracker Subsystem Specification LAT-SS-00136LAT-SS-00136: Power Subsystem Specification LAT-SS-00018LAT-SS-00018: CAL Subsystem Specification LAT-MD-00446LAT-MD-00446: LAT SVAC Plan LAT-MD-00408LAT-MD-00408: LAT Performance Verification Plan LAT-MD-02730LAT-MD-02730: LAT Performance and Operations Test Plan LAT-MD-07658LAT-MD-07658: LAT Verification Cross Reference Matrix

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 6 SC-LAT ICD Pending Changes ICN #TitleDescriptionStatus -096 Unregulated Power Voltage For shorts periods of time, the SC will be unable to provide the minimum 25V for the unregulated feeds. The voltage may get as low as 23V.GSFC review -099LAT Integration This is an appendix to the ICD that is meant to capture agreements for Observatory I&T activities.Approved -100LAT Impedance Incorporate into ICD the as-measured LAT differential impedance. Pending SC PRU Measurement -109LAT VCHP Overvoltage The SC limits the voltage on the SIU and DAQ feeds but not on the VCHP feeds.In review -111MLI InterfaceMinor changes to the MLI interface, i.e. velcro sizeIn sign off – SC-LAT ICD EIY C is released –The table below lists pending changes

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 7 Overview of Subsystem Changes Since PER Design Changes Flowed From LAT MRB Process –Changes incorporated in final design documentation –All changes consistent with LAT-SC ICD Residual Design Liens Against Flight Software discussed in FSW presentation Mechanical –Minor blanket modifications Flight Software –Boot code updated

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 8 LAT End Item Data Package The LAT Project provides an EIDP consisting of the following documents, data, and other materials –LAT-level subsystem-level requirements specifications Acceptance test data packages for subsystems –Requirements verification plans and test plans –LAT-level test procedures and reports, and links to test execution logs and records –Open nonconformance reports and waivers –Integration and test records Assembly and Inspection Data Sheets Integration records: mate/demate, installation logs, material mix records –EGSE and MGSE documentation All LAT project documentation is maintained in hardcopy and electronic form at SLAC –The EIDP is a subset EIDP posted on the Pre-Shipment Review Agenda Page: – tmlhttp:// tml EIDP is currently being populated

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 9 Residual Risks ID # Risk Rank Risk Description Risk MitigationStatus SE Low If individual tracker towers do not meet performance requirements due to manufacturing issues (e.g. wire bond breaks) then the LAT may not meet science requirements Reduced On Orbit temperature excursions Optimized placement of towers A/B based on individual tower performance Trending tracker efficiency/dead channels throughout integration testing No current concern for mission performance over life expected Proj Mgt Low If Tracker Noise Flares (NCR684), increase an order of magnitude and spread then some risk to overall tracker noise performance Monitor for occurrence Verified no significant change during TVAC Continue trend in Observatory Test Observed noise is an order of magnitude lower than a concern level and isolated No increased trend during system test to date Elect Low If spare GASU (AEM) FPGA failure (NCR897) is inherent in the design then mitigation on flight unit could impact schedule Complete part failure analysis Survey of part failure records Complete assessment of root cause Part failure analysis & survey complete Root cause identified, no known flight issue

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 10 Residual Risks (Cont) ID # Risk Rank Risk Description Risk MitigationStatus Elect Low If SIU reboot (NCR 880) is an inherent design flaw then loss of data until reboot completed Completed existing data analysis Additional diagnostics/data gathering plan in place Data gathering plan in place should another reboot occur SE- 014 Low If ACD PMTs become noisy again (NCR626), then ACD ability to perform background rejection may be reduced More stringent PMT high voltage screening All noisy tubes were replaced in the flight ACD Flight PMTs are operated at voltages less than voltages that produced noise No new noisy PMTs have appeared after thousands of tube-hours of screening at high voltage Conservative Wiebull prediction shows extremely low chance of potentially noisy PMTs making it through the screening. Elec- 007 Low If the unused QCLK floating pins on PCI FPGA impacts part reliability then mission redundancy may be reduced Completed vendor analysis indicating no known failure mode or impact on reliability Completed LAT analysis indicating no known failure analysis Consider risk of grounding pins should alternative need to open box occurs GSFC Mission Office review and concurrence, no known risk at this time

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 11 Residual Risks (Cont) ID # Risk Rank Risk Description Risk MitigationStatus Elect Low If EPU reboot (NCR 881) is an inherent design flaw then loss of data until reboot completed Completed existing data analysis Additional diagnostics/data gathering plan in place Data gathering plan in place should another reboot occur Elect Low If EPU 0 reboot (NCR 902) is an inherent design flaw then loss of data until reboot complete0 Completed existing data analysis Additional diagnostics/data gathering plan in place Data gathering plan in place should another reboot occur Elect- 012 Low If LATC Verify Errors (NCR855) re- occur on orbit then LAT will not execute science run until corrected Completed existing data analysis Additional diagnostics/data gathering plan in place Consider FSW changes to allow science run with these specific Errors No re occurrence reported since FSW Data gathering plan in place should another LATC verify error occur

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 12 Residual Risks (Cont) ID # Risk Rank Risk Description Risk MitigationStatus Elect Low If EPU reboots (NCR 948) are an inherent design flaw then loss of data until reboot completed Completed existing data analysis Additional diagnostics/data gathering plan in place Data gathering plan in place should another reboot occur Elect Low If EPU reboots (NCR 949) are an inherent design flaw then loss of data until reboot completed Completed existing data analysis Additional diagnostics/data gathering plan in place Data gathering plan in place should another reboot occur

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 13 Residual Risks (Cont) ID # Risk Rank Risk Description Risk MitigationStatus Proj Mgt Low If decision to conduct tracker environmental tests with non flight cable configurations (Waiver ) results in future failure then tracker redundancy may be compromised Tracker cables are redundant Full CPT’s conducted in flight configuration Trackers to be tested at LAT and Observatory Environmental tests No failures to date Continue to monitor thru test program Proj Mgt Low If Tracker flex cables/MCM’s fail that had failed coupons (Waiver ) then Tracker redundancy may be impacted Tracker cables/MCMs are redundant Trackers to be tested at LAT and Observatory Environmental tests No failures to date Continue to monitor thru test program Proj Mgt- 018 Low If finalization of FSW Science Algorithms is delayed or impacts LAT functional performance then Observatory Test Schedule could be impacted FSW build (B1.0) plan in place to add Science requirements New Science Algorithms do not impact established LAT performance Significant CPU/Memory margin to accommodate minor growth Plan to maximize early LAT runtime at SASS Well defined build planning with Proj Office involvement in change control TVAC eval of CPU peak performance indicate small (acceptable) temperature increase with worst case utilization Non interference LAT runtime planning in work

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 14 LAT Mass Properties

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 Page Number 15 LAT Power Status

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 16 LAT Power Status (Continued) Survival Power ComponentCurrentSubsystem Power Estimates (W) Alloc.PARACALCMEASTotalMargin On-Orbit Average Power Total % Regulated VCHP Power Total % Unregulated Passive Survival Power % 1 Power status reflects the LAT steady state orbit average. Numbers do not reflect transition into or out of survival mode, i.e. early orbit operations.

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 17 FSW Resource Usage ResourceTotal AvailableCurrent Usage Margin Factor Source EPU Boot EEPROM (SUROM) 256 kB62 kB*4*B SIU Boot EEPROM (SUROM) 256 kB62 kB*4*B EPU EEPROM6 MB0.59 MB10B SIU EEPROM6 MB0.73 MB8.2B EPU CPU cycles200% in 2 EPUs40%> 5Estimate SIU CPU cycles100% in 1 SIU25%4Estimate EPU memory128 MB16-32 MB4-8Estimate SIU memory128 MB< 16 MB8Estimate * Storing multiple copies (4 currently to use available memory) for risk mitigation

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 18 Instrument Bandwidth Resources ResourceMax Total BW limited by Hardware Max limited by SC- ground transmissi on Ave current BW at 10 KHz max trigger rate* Ave current BW at 2 KHz nominal trigger rate* Margin Factor (for 10 KHz rate) Detector to GASU-EBM45N/A GASU-EBM to EPU-CPU20N/A514 EPU-CPU to GASU-EBM *0.02*2 GASU-EBM to SIU-CPU *0.015*2 SIU-CPU to Spacecraft *0.015*2 EBM: Event-Builder Module EPU: Event-Processing Unit SIU: Spacecraft Interface Unit LAT communication, bandwidth (BW) in Mbyte/sec * Present performance of event filter for EPU- CPU, still being optimized. Eventually the physics filter will be adjusted/loosened to take advantage of the max average bandwidh

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 19 Unit Run Time These unit run times start after the LAT was completely integrated and cover through the completion of the CPT after TV –Does not include integration testing –Does not include unit testing

GLAST LAT Project September 15, 2006: Pre-Shipment Review Presentation 3 of 12 SE Overview 20 LAT System Engineering Summary Process for verification closure with GSFC in place SE Review of LAT Environmental Tests and verification status indicate ready to ship