CASE STUDY
THE INTERNATIONAL CHAMBER OF COMMERCE (ICC)
Introduction What is the International Court of Arbitration of the International Chamber of Commerce? Internet address: Legal basis: Rules of Arbitration
Vienna Rules and ICCRules What is different in the ICC Rules from the Vienna Rules (Main items): Terms of Reference (Art 18 ICC Rules) Procedural Timetable (Art 18 ICC Rules) Times limit for the Terms of Reference and for the award (Art 18 and 24 ICC Rules) Approval of Terms of Reference and of the award by the Court of Arbitration (Art 18/3 and 27 ICC Rules)
THE PERSONS INVOLVED
The Claimant Pesante & Grosso, Padova, Italy Distributor of food and beverages Abbreviation: „P & G“ Attorney (Avvocato): Prof. Dott. Paolo Sapiente Studio Sapiente & Montasio, Padova Arturo Vivarini, sales manager
The Respondent King´s Department Stores Ltd., London Owner of department stores Abbreviation: King's Attorney (Barrister): Mr. George Wise, Queen's Counsel London, England John Brown, sales manager
The Tribunal Co arbitrator, appointed by the Claimant: Avv. Maurizio Castellani, Milano, Italy Co arbitrator, appointed by the Respondent: Mr. Anthony Ferguson, Q.C., London, Engl. Chairman, appointed by the Secretary General of the International Court of Arbitration: Hon. Prof. Dr. Kurt Heller, Vienna, Austria
Other firm involved Alimentari di Parma S.r.l., Parma, Italy Producer of food, in particular of the famous Parma ham Abbreviation: Parma Carlo Quinto, amministratore delegato (general manager, president) Francesco Secondo, sales manager
THE CONTRACTUAL RELATIONS
Contracts : Sales Contract between King's and Parma
Main conditions of the contract of Parma to deliver to King's kg of ham for EUR , CIF Dover Advance payment of EUR within 2 weeks after signing EUR : 3 day after receipt of goods EUR : 60 days thereafter Arbitration clause No extension of delivery date (disputed by Claimant) Change of payment conditions (disputed by Claimant) by telephone on
Arbitration Clause ” Any dispute arising of this contract will be resolved by reconciliation. If the reconciliation would fail, the contracting parties agreed upon that arbitration will be done by the International Chamber of Commerce in Paris, in Vienna. Austrian law shall apply."
Further Contracts :Parma sells its distribution business to P&G :P&G informs King's of taking over of distribution business :Telephone conference: Change of payment conditions (disputed) Febr. 2007:Order for Whisky (disputed)
PERFORMANCE
Performance of the Sales Contract January: Claimant hands over goods to railway 22/2/07: Agreed delivery date in Dover 25/2/07: King's declares contract avoided (cancelled) 2/3/07: Goods arrive in Dover with a delay of delivery of one week 10/3/07: King's request that goods shall be taken back
SUBMISIONS OF THE PARTIES
Claimant's submissions Delivery of ham, but Respondent did not pay the remaining EURO. The parties agreed to postpone the delivery We did not place any order for whiskey Even if we had placed such order the Respondent is not allowed to set of the purchase price for the whiskey against our claim The payment conditions never were changed
Defendant's submission The tribunal has not jurisdiction There does not exist any valid arbitration agreement in writing between the parties The strike of the Italian railway falls within the sphere of responsibility of the Claimant We purchased the ham for the „Italian week“ of our department stores. Because of the delayed delivery we could not sell it any more
Set off The Claimant ordered bottles of whiskey by telephone on 5/2/2007 but refused to take it over and to pay the purchase price. We set off the purchase price of 2 Millions English Pounds against the claim of the Claimant.
PROCEDURE
Procedure before the constitution of the tribunal Filing of request for arbitration (2/6/07) Service of request to respondent Filing of answer to request for arbitration (28/8/2007) Appointment of chairmen and handing over of the file to the tribunal, fixing of advance on costs (5/9/2007)
Procedure of the tribunal before the taking of evidence Claimant and Respondent pay half of the advance on cost (or Claimant pays on behalf of Respondent) Drawing up of the „Terms of Reference“ and drawing up of a “Procedural Timetable” (in writing or in a hearing) Tribunal decides procedural issues still in dispute (language, place of arbitration) Further exchange of submissions by the parties (possibly)
Terms of Reference (Art. 18 of the ICC Rules) Full name and descriptions of the parties Notification and communication Summary of the parties respective claims Issues to be determined Arbitrators full names, descriptions and addresses Place of arbitration Particulars of the applicable procedural rules (rules of evidence, applicable law, minutes, filing of submissions and documents, copies, translations etc.)
Further procedure Taking of evidence (Hearing etc.) Conclusion of taking of evidence Final pleadings Deliberations of the arbitrators Draft award sent to Secretariat Secretariat determines amount of arbitrator's fees and expenses to be mentioned in the award Award in final form sent to the Secretariat Award approved by Court of Arbitration Award sent to the parties
MAIN ISSUES OF THE CASE
The procedural issues Law applicable to the arbitration clause Law applicable to the procedure The Tribunal's jurisdiction
Law applicable to the arbitration clause Does arbitration have a lex fori ? Law of the contract and of the arbitration clause Choice of law possible also for arbitration clauses
The Tribunal's jurisdiction Does a valid arbitration agreement exist for the claims raised by the parties? No written arbitration agreement between the parties. Signing authority Valid set off Contract was avoided (principle of separability) Why is the arbitration clause badly drafted ?
"Any dispute arising of this contract will be resolved by reconciliation. If the reconciliation would fail, the contracting parties agreed upon that arbitration will be done by the International Chamber of Commerce in Paris, in Vienna. Austrian law shall apply."
Why is the arbitration clause badly drafted ? Description of dispute to narrow (see standard clause: “All disputes arising out of or in connection with the present contract...”. Description of institution unclear Place of arbitration unclear (Paris of Vienna) Language not determined
Arbitration Clause "Any dispute arising of this contract will be resolved by reconciliation. If the reconciliation would fail, the contracting parties agreed upon that arbitration will be done by the International Chamber of Commerce in Paris, in Vienna. Austrian law shall apply."
Language of arbitration Claimant:Italian Respondent: English Who chooses language ? –Parties –Tribunal Criteria for determination of language: –Language of the contract –Language used during the performance under the contract –Fair language
Place of arbitration Claimant: Vienna Respondent: Paris Who chooses the place of arbitration? –Parties –Tribunal
Place of Arbitration Why is the place of arbitration important? Enforceability (New York Convention, bilateral treaties) Applicable law (choice of law rules) Nationality of the award (jurisdiction of ordinary courts regarding arbitration - setting aside of awards, legal assistance) Services on the place of arbitration Travelling problems (Visa etc.)
Issues of substantive law Applicable substantive law CIF Dover ? Avoidance of the contract Set off of claims
Applicable substantive law Choice of law: Austrian law Applicable law: CISG (Vienna Sales Convention or Austrian law ?)
CIF Dover ? What are incoterms ? CIF (cost, insurance, freight)means: Dover is the port of destination Sphere or responsibility (risks) of the seller passes on to the purchaser when the goods pass the ship's rail at the port of shipment (handing over to railway or to the ship in Genova ?)
Avoidance of the contract Claimant: Application of § 918 ABGB Respondent: Purchased for „Italian weeks“ (Fixgeschäft) Art 45 and 49 CISG
Set off Can Respondent set off with claims that are not subject to the same arbitration clause ? OGH , JBl 1957, 80
THE RESULT OF THE CASE
The result of the case The Tribunal shall take jurisdiction regarding the purchase price for the ham but may not allow the set off. The taking of evidence shall concentrate on the following issues: –Intention of the parties regarding the use of the incoterm CIF (handling over of ham to the railway or passing of the ship rail) –Nature of the contract regarding fix day of delivery (Fixgeschäft?)
The End