The KM3NeT Neutrino Telescope Uli Katz ECAP / Univ. Erlangen 04.05.2010 7th International Workshop on Ring-Imaging Cherenkov Detectors (RICH 2010) Cassis,

Slides:



Advertisements
Similar presentations
May 2009KM3NeT1 What is KM3NeT ? Future cubic-kilometre scale neutrino telescope in the Mediterranean Sea Exceeds Northern- hemisphere telescopes by factor.
Advertisements

CDR Feb 2006Mar 2008Dec 2009 Mar Design Study Preparatory Phase TDR tendering construction data taking governance legal entity pre-production.
Trigger issues for KM3NeT the large scale underwater neutrino telescope the project objectives design aspects from the KM3NeT TDR trigger issues outlook.
Jan 2009 U. Katz: Astroparticle Physics 1 What is KM3NeT – the Vision  Future cubic-kilometre sized neutrino telescope in the Mediterranean Sea  Exceeds.
The Multi-PMT Optical Module P.Kooijman, University of Amsterdam University of Utrecht Nikhef.
Kay Graf Physics Institute 1 University of Erlangen ARENA 2006 University of Northumbria June 28 – 30, 2006 Integration of Acoustic Neutrino Detection.
R. Coniglione INFN-LNS TEV PA Paris July 2010 KM3NeT: a project for an underwater cubic kilometre neutrino telescope R. Coniglione INFN-LNS for KM3NeT.
The KM3NeT Project Uli Katz ECAP / Univ. Erlangen Astroteilchenphysik in Deutschland: Status und Perspektiven Zeuthen, Februar 2010.
Status of the ANTARES Neutrino-Telescope Alexander Kappes Physics Institute University Erlangen-Nuremberg for the ANTARES Collaboration WIN´05, 6.–11.
Neutrino Astronomy with KM3NeT  The KM3NeT physics case  What happened so far  The KM3NeT Conceptual Design Report  The Preparatory Phase: Towards.
A. BELIAS, NESTOR Institute, Pylos, Greece TeVPA 2009, July 13-17, SLAC1 KM3NeT, a deep sea neutrino telescope in the Mediterranean Sea KM3NeT objectives.
Status of the KM3NeT Project  The Challenge  Technical solutions: Decisions an options  Physics sensitivity  Cost and implementation  Summary 4th.
Status of the KM3NeT Project  What happened so far  The KM3NeT Conceptual Design Report  The Preparatory Phase: Towards Implementation 3rd Workshop.
P. Sapienza, NOW 2010 The KM3NeT project  Introduction & Main objectives  The KM3NeT Technical Design Report  Telescope physics performance  New developments.
Neutrino Astronomy with KM3NeT Uli Katz ECAP / Univ. Erlangen Vulcano Workshop 2010: Frontier Objects in Astrophysics and Particle Physics Vulcano,
Neutrino Astronomy with KM3NeT was: Mediterranean Neutrino Telescopes - Status and Future Uli Katz ECAP / Univ. Erlangen International School.
A feasibility study for the detection of SuperNova explosions with an Undersea Neutrino Telescope A. Leisos, A. G. Tsirigotis, S. E. Tzamarias Physics.
Antares/KM3NeT M. de Jong. neutrinos  p Scientific motivation: – origin cosmic rays – birth & composition relativistic jets – mechanism of cosmic particle.
Introduction to future synergy options Uli Katz ECAP, Univ. Erlangen Deep Ocean Cabled Observatories Amsterdam, May 2012.
Deep-sea neutrino telescopes Prof. dr. Maarten de Jong Nikhef / Leiden University.
KM3NeT IDM/TeVPA conference 23  28 June 2014, Amsterdam, the Netherlands Maarten de Jong on behalf of the KM3NeT collaboration The next generation neutrino.
Paolo Piattelli - KM3NeTIAPS - Golden, 6-8 may 2008 KM3NeT: a deep-sea neutrino telescope in the Mediterranean Sea Paolo Piattelli - INFN/LNS Catania (Italy)
KM3NeT The Birth of a Giant V. Popa, KM3NeT Collaboration Institute for Space Sciences, Magurele-Bucharest, Romania.
Hanoi, Aug. 6-12, 2006 Pascal Vernin 1 Antares Status report P.Vernin CEA Saclay, Dapnia On behalf of the Antares collaboration P.Vernin
Status and performance R. Coniglione for KM3NeT collaboration INFN- Laboratori Nazionali del Sud Catania - Italy R. Coniglione Marseille 4-6 April
C.DistefanoCRIS 2008 – Salina, September The KM3Net Consortium Istituto Nazionale di Fisica Nucleare Laboratori Nazionali del Sud Towards a km3-scale.
Status of KM3NeT (Detector Design Optimisations) Christopher Naumann, CEA Saclay – IRFU / SPP for the KM3NeT consortium 44 th Reconcontres de Moriond,
Neutrinos as Cosmic Messengers in the Era of IceCube, ANTARES and KM3NeT Uli Katz ECAP / Univ. Erlangen Vulcano Workshop 2012 Frontier Objects.
Piera Sapienza – VLVNT Workshop, 5-8 october 2003, Amsterdam Introduction and framework Simulation of atmospheric  (HEMAS and MUSIC) Response of a km.
SINP MSU, July 7, 2012 I.Belolaptikov behalf BAIKAL collaboration.
Tools and Methods for simulation and evaluation of Very Large Volume Cherenkov Neutrino detectors: Optimization and Evaluation of proposed KM3NeT designs.
A sensor architecture for neutrino telescopes on behalf of the KM3NeT consortium Els de Wolf Thank you, Claudio!
The KM3NeT Project Uli Katz ECAP / Univ. Erlangen Conference on Recent Developments in High Energy Physics and Cosmology 25–28 April 2013, University.
KM3NeT International Solvay Institutes 27  29 May 2015, Brussels, Belgium. Maarten de Jong Astro-particle and Oscillations Research with Cosmics in the.
KM3NeT ‑ The Next Generation Neutrino Telescope Alexander Kappes IceCube Particle Astrophysics Symposium Union South, Madison, May 13, 2013.
Disk WP-4 “Information Technology” J. Hogenbirk/M. de Jong  Introduction (‘Antares biased’)  Design considerations  Recent developments  Summary.
News from KM3NeT Uli Katz ECAP / Univ. Erlangen MANTS Meeting, Garching, October 2013.
The KM3NeT consortium ( - supported through the European Union's 6th framework programme in a 3-year Design Study - aims at the construction.
Time over Threshold electronics for an underwater neutrino telescope G. Bourlis, A.G.Tsirigotis, S.E.Tzamarias Physics Laboratory, School of Science and.
VLVnT11 - Erlangen 12-14/10/ Giorgio Cacopardo NEMO Phase2 mechanical design G. Cacopardo on behalf of NEMO collaboration.
R. Coniglione, VLVnT08, Toulon April ‘08 KM3NeT: optimization studies for a cubic kilometer neutrino detector R. Coniglione P. Sapienza Istituto.
Neutrino Astronomy with KM3NeT  The KM3NeT physics case  What happened so far  The KM3NeT Conceptual Design Report  The Preparatory Phase: Towards.
Mechanical design of the Pre-Production Detector Unit Model of KM3NeT Mario MUSUMECI and Riccardo PAPALEO KM3NeT PP DU subgroup coordinators on behalf.
Sebastian Kuch, Rezo Shanidze Preliminary Studies of the KM3NeT Physics Sensitivity KM3NeT Collaboration Meeting Pylos, Greece, April 2007.
Neutrinos and the sea Els de Wolf NIKHEF Ilias Meeting, Prague, February 8 th 2005.
The ORCA option for KM3NeT Uli Katz ECAP / Univ. Erlangen XV International Workshop on Neutrino Telescopes, Venice 15 March 2013.
The ORCA option for KM3NeT Uli Katz ECAP / Univ. Erlangen XV International Workshop on Neutrino Telescopes, Venice 15 March 2013.
STATUS AND PHYSICS GOALS OF KM3NET Paolo Piattelli P. Piattelli, ICHEP14 Valencia INFN – LNS, Catania (Italy)
KM3NeT – Stautus and Future Uli Katz ECAP / Univ. Erlangen th International Workshop on Next Generation Nucleon Decay and Neutrino Detectors.
WP F/L Dom production. KM3Net meeting 2012 Erlangen - Edward Berbee - Nikhef22/06/20121.
KM3NeT WPF/L NIKHEF- MECABAR 1 A.Cosquer on behalf of the KM3NeT consortium MECABAR PROJECT PLAN 1- Context 2- 3D views and responsibilities 3-
Response of the KM3NeT detector to neutrinos from Fermi bubbles.
Antares/KM3NeT M. de Jong. Antares  2000NL joined collaboration (3.3 M€)  2006 ‒ 2008construction  2006 ‒ todaydata taking 24h/day  2012MoU signed.
Towards the TDR KM3NeT-DS WPx Meeting, Paris, Feb , 2009 Uli Katz ECAP / Univ. Erlangen  My private views  Basis for discussion  Decisions taken.
Mechanical design of the Pre-Production Detector Unit Model of KM3NeT Mario MUSUMECI and Riccardo PAPALEO KM3NeT PP DU subgroup coordinators.
The Neutrino Telescope of the KM3NeT Deep-Sea Research Infrastructure Robert Lahmann for the KM3NeT Consortium Erlangen Centre for Astroparticle Physics.
WP F/L Detection Unit Mechanical Structure and Deployment R. Papaleo 130/03/2011.
Alexander Kappes ECAP, Universität Erlangen-Nürnberg for the KM3NeT Consortium 2009 EPS HEP, Krakow, 16. July 2009 The KM3NeT project: Towards a km 3 -scale.
KM3NeT Neutrino conference 2-7 June 2014, Boston, U.S.A. Maarten de Jong on behalf of the KM3NeT collaboration The next generation neutrino telescope in.
Status of the NEMO tower validation Integration Tests Improvements Deployment program M.Anghinolfi- km3-day meeting )
Overview of the KM3NeT project: an underwater multi ‐ km 3 detector M. Spurio University of Bologna and INFN RICAP Roma, May
KM3NeT P.Kooijman Universities of Amsterdam & Utrecht for the consortium.
Write-up and Definitions for Cost Model
P.Kooijman, UVA-GRAPPA, UU, Nikhef
Pasquale Migliozzi INFN Napoli
Els de Wolf, Nikhef/UvA KM3NeT WP345-meeting 23 February 2009
Istituto Nazionale di Fisica Nucleare Laboratori Nazionali del Sud
Els de Wolf 20 February 2012, Catania
KM3NeT: where are we and where do we go
KM3NeT: a project for an underwater cubic kilometre neutrino telescope
Presentation transcript:

The KM3NeT Neutrino Telescope Uli Katz ECAP / Univ. Erlangen th International Workshop on Ring-Imaging Cherenkov Detectors (RICH 2010) Cassis, France, 3-7 May 2010

U. Katz: KM3NeT (RICH 2010) 2 Technical solutions: Decisions and options Physics sensitivity Cost and implementation Summary

U. Katz: KM3NeT (RICH 2010) 3 The Neutrino Telescope World Map NEMO ANTARES, NEMO, NESTOR joined efforts to prepare a km 3 -size neutrino telescope in the Mediterranean Sea  KM3NeT

U. Katz: KM3NeT (RICH 2010) 4 What is KM3NeT ? Future cubic-kilometre scale neutrino telescope in the Mediterranean Sea Exceeds Northern- hemisphere telescopes by factor ~50 in sensitivity Exceeds IceCube sensitivity by substantial factor Focus of scientific interest: Neutrino astronomy in the energy range 1 to 100 TeV Provides node for earth and marine sciences

U. Katz: KM3NeT (RICH 2010) 5 South Pole and Mediterranean Fields of View > 75% > 25% 2  downward sensitivity assumed In Mediterranean, visibility of given source can be limited to less than 24h per day

U. Katz: KM3NeT (RICH 2010) 6 The Objectives Central physics goals: Investigate neutrino “point sources” in energy regime TeV Complement IceCube field of view Exceed IceCube sensitivity Implementation requirements: Construction time ≤5 years Operation over at least 10 years without “major maintenance”

U. Katz: KM3NeT (RICH 2010) 7 Objective: Support 3D-array of photodetectors and connect them to shore (data, power, slow control) Optical Modules Front-end electronics & readout Readout, data acquisition, data transport Mechanical structures, backbone cable General deployment strategy Sea-bed network: cables, junction boxes Calibration devices Shore infrastructure Assembly, transport, logistics Risk analysis and quality control Technical Design Design rationale: Cost-effective Reliable Producible Easy to deploy Unique or preferred solutions

U. Katz: KM3NeT (RICH 2010) 8 Further Challenges Site characteristics Objective: Measure site characteristics (optical background, currents, sedimentation, …) Simulation Objective: Determine detector sensitivity, optimise detector parameters; Earth and marine science node Objective: Design interface to instrumentation for marine biology, geology/geophysics, oceanography, environmental studies, alerts, … Implementation Objective: Take final decisions (technology and site), secure resources, set up proper management/governance, construct and operate KM3NeT;

U. Katz: KM3NeT (RICH 2010) 9 The KM3NeT Research Infrastructure (RI) (DU)

U. Katz: KM3NeT (RICH 2010) 10 OM “classical”: One PMT, no Electronics Evolution from pilot projects: 8-inch PMT, increased quantum efficiency (instead of 10 inch) 13-inch glass sphere (instead of 17 inch) no valve (requires “vacuum” assembly) no mu-metal shielding

U. Katz: KM3NeT (RICH 2010) 11 OM with many Small PMTs 31 3-inch PMTs in 17-inch glass sphere (cathode area~ 3x10” PMTs) 19 in lower, 12 in upper hemisphere Suspended by compressible foam core (D)31 PMT bases (total ~140 mW) (D) (B,C)Front-end electronics (B,C) (A)Al cooling shield and stem (A) Single penetrator 2mm optical gel (ANTARES-type) X A B C C D PMT

U. Katz: KM3NeT (RICH 2010) 12 Front-End Electronics: Time-over-Threshold From the analogue signal to time stamped digital data: … Threshold 1 Threshold 2 Threshold 3 Time Amplitude t1t1 t2t2 t3t3 t4t4 t5t5 t6t6 Front End ASIC System on Chip (SoC) Analogue signal Digital data Ethernet TCP/IP data link Shore FPGA+processor Scott chip

U. Katz: KM3NeT (RICH 2010) 13 N/k thresholds for k PMTs Mem 1Mem 2 FIFO + ZS SoC Scott Mem 1Mem 2 FIFO + SZ SoC Scott Same Readout for Single- and Multi-PMT OMs N thresholds for 1 PMT

U. Katz: KM3NeT (RICH 2010) 14 Data Network All data to shore: Full information on each hit satisfying local condition (threshold) sent to shore Overall data rate ~ 25 Gbyte/s Data transport: Optical point-to-point connection shore-OM Optical network using DWDM and multiplexing Served by lasers on shore Allows also for time calibration of transmission delays Deep-sea components: Fibres, modulators, mux/demux, optical amplifiers (all standard and passive)

U. Katz: KM3NeT (RICH 2010) 15 DUs: Bars, Strings, Triangles Flexible towers with horizontal bars Simulation indicates that “local 3D arrangement” of OMs increases sensitivity significantly Single- or multi-PMT OMs Slender strings with multi-PMT OMs Reduced cost per DU, similar sensitivity per Euro Strings with triangular arrangements of PMTs Evolution of ANTARES concept Single- or multi-PMT OMs “Conservative” fall-back solution Reminder: Progress in verifying deep-sea technology can be slow and painful Careful prototype tests are required before taking final decisions This is a task beyond the Design Study!

U. Katz: KM3NeT (RICH 2010) 16 The Flexible Tower with Horizontal Bars 20 storeys Each storey supports 6 OMs in groups of 2 Storeys interlinked by tensioning ropes, subsequent storeys orthogonal to each other Power and data cables separated from ropes; single backbone cable with breakouts to storeys Storey length = 6m Distance between storeys = 40 m Distance between DU base and first storey = 100m

U. Katz: KM3NeT (RICH 2010) 17 Mooring line: Buoy (empty glass spheres, net buoyancy 2250N) Anchor: concrete slab of 1m 3 2 Dyneema ropes (4 mm diameter) 20 storeys (one OM each), 30 m distance, 100m anchor-first storey Electro-optical backbone: Flexible hose ~ 6mm diameter Oil-filled 11 fibres and 2 copper wires At each storey: 1 fibre+2 wires Break out box with fuses at each storey: One single pressure transition Star network between master module and optical modules The Slender String New concept, needs to be tested. Also for flexible tower if successful

U. Katz: KM3NeT (RICH 2010) 18 Triangle Structure 100 m 40 m 19X40 = 760 m Evolution from ANTARES concept 20 storeys/DU, spacing 40m Backbone: electro- optical-mechanical cable Reduced number of electro-optical penetrations Use ANTARES return of experience 2.3m

U. Katz: KM3NeT (RICH 2010) 19 Deployment Strategy All three mechanical solutions: Compact package – deployment – self-unfurling Eases logistics (in particular in case of several assembly lines) Speeds up and eases deployment; several DUs can be deployed in one operation Self-unfurling concepts need to be thoroughly tested and verified Connection to seabed network by ROV Backup solution: “Traditional” deployment from sea surface

U. Katz: KM3NeT (RICH 2010) 20 A Flexible Tower Packed for Deployment

U. Katz: KM3NeT (RICH 2010) 21 Compactifying Strings Slender string rolled up for self-unfurling: DU 3 triangles

U. Katz: KM3NeT (RICH 2010) 22 DUs move under drag of sea current Currents of up to 30cm/s observed Mostly homogeneous over detector volume Deviation from vertical at top: Torsional stability also checked Hydrodynamic Stability d Current [cm/s] flexible tower d [m] slender string d [m] triangles d [m]

U. Katz: KM3NeT (RICH 2010) 23 Different DU designs require different DU distance differ in photocathode area/DU are different in cost Detector Building Blocks } different „building block footprints“ Bars, triangle: 127 DUs, distance 180/150 m Slender string: 310 DUs, distance 130 m 2 km Footprint optimisation is ongoing

U. Katz: KM3NeT (RICH 2010) 24 Example: Sensitivity dependence of point-source search on DU distance for flexible towers (for 2 different neutrino fluxes ~E - , no cut-off) Optimisation Studies  = 2.0  = 2.2

U. Katz: KM3NeT (RICH 2010) 25 Investigate distribution of angle between incoming neutrino and reconstructed muon Dominated by kinematics up to ~1TeV Angular Resolution kinematics < 0.1°

U. Katz: KM3NeT (RICH 2010) 26 Effective Areas (per Building Block) Results very similar for hard quality cuts Flexible towers with bars and slender strings “in same ballpark” Driven by overall photocathode area Symbols: Flexible towers, different quality cuts Lines:Slender lines, different quality cuts

U. Katz: KM3NeT (RICH 2010) 27 Cost Estimates: Assumptions Estimate of investment cost no personnel costs included no contingency, no spares Assumptions / procedure: Quotations from suppliers are not official and subject to change Common items are quoted with same price Sea Sciences and Shore Station not estimated Estimates worked out independently by expert groups and carefully cross-checked and harmonised thereafter

U. Katz: KM3NeT (RICH 2010) 28 Result of cost estimates (per building block): Assembly man power (OMs, DU…) is roughly estimated to be 10% of the DU cost Cost Estimates: Results Concept DU Cost (M€) No. of DUs Total DU Cost (M€) Seafloor Infrastr. (M€) Deploy- ment (M€) TOTAL COST (M€) Flexible towers Slender strings Triangles

U. Katz: KM3NeT (RICH 2010) 29 KM3NeT: Full Configuration 2 “building blocks” needed to achieve objectives Increases sensitivity by a factor 2 Overall investment ~220 M€ Staged implementation possible Science potential from very early stage of construction on Operational costs 4-6 M€ per year (2-3% of capital investment), including electricity, maintenance, computing, data centre and management

U. Katz: KM3NeT (RICH 2010) 30 Point Source Sensitivity (1 Year) Aharens et al. Astr. Phys. (2004) – binned method R. Abbasi et al. Astro-ph (2009) scaled – unbinned method  Observed Galactic TeV-  sources (SNR, unidentified, microquasars) F. Aharonian et al. Rep. Prog. Phys. (2008) Abdo et al., MILAGRO, Astrophys. J. 658 L33- L36 (2007) KM3NeT (binned) IceCube Expected exclusion limits:

U. Katz: KM3NeT (RICH 2010) 31 Candidate Sites Locations of the three pilot projects: ANTARES: Toulon NEMO: Capo Passero NESTOR: Pylos Long-term site characterisation measurements performed Site decision requires scientific, technological and political input

U. Katz: KM3NeT (RICH 2010) 32 Next Steps and Timeline Next steps: Prototyping and design decisions TDR public in 3-4 weeks final decisions require site selection expected to be achieved in 18 months Timeline:

U. Katz: KM3NeT (RICH 2010) 33 Conclusions A design for the KM3NeT neutrino telescope complementing the IceCube field in its of view and surpassing it in sensitivity by a substantial factor is presented. Readiness for construction expected in 18 months An overall budget of ~250 M€ will be required. Staged implementation, with increasing discovery potential, is technically possible. Within 18 months, remaining design decisions have to be taken and the site question clarified. Installation could start in 2013 and data taking soon after.