Status at DORIS Hall June 28th start of mounting the Al- frames, progressig very fast, finished by July 9th All 8 coils pressure tested with 15 bar = O.K. After holiday break 4 coils installed by August 18th, Joe Dodge from Bates supported us Other 4 coil ready for installation Survey revealed that Al – frames are 19 mm too low, instead of expected 5 mm Now shimming work underway Jan Hauschildt, MEA1, August 31st, 2010
Status at DORIS Hall Power to container switched on(8 * 16 Amps. in the hut) looks very tight Power for coils to be connected in September Inner detector frame will be installed soon Pipes for gas supply about to be installed Cooling water pipes manufactured and tested from DORIS supply to the distribution area Cooling water control will be switched to DESY standards Jan Hauschildt, MEA1, August 31st, 2010
Status at DORIS Hall, Hall 1 First shielding blocs installed Further shielding design underway Rails for inner detector frame hamper opening of Al – frames ( they stick out of the CAD model) Solution ? Quadrupole- and vacuum- support design underway Still missing : guided multiton rollers Jan Hauschildt, MEA1, August 31st, 2010