US Tracker Group Status Sep. 1, 2005 J. Incandela For the US CMS Tracker Group.

Slides:



Advertisements
Similar presentations
Tracker Week – UCSB Gantry Status – April 20, 2004 – Dean White 1 Gantry Report University of California Santa Barbara Dean White.
Advertisements

US Tracker Production Meeting, March 8, 2005 J. Incandela 1 Slides for the US Si Tracker Weekly Production Meeting J. Incandela March 8, 2005.
Tracker Week – UCSB Gantry Status – July 20, 2004 – Dean White 1 Gantry Report University of California Santa Barbara UCSB Gantry Team: Andrea Allen Dave.
US Tracker Institutional Leaders Meeting, March 1, 2005 J. Incandela 1 Slides for the US Si Tracker Institutional Group Leaders Meeting J. Incandela March.
1 UCSB Module Assembly Week of 5/16-5/20. 2 UCSB Parts Inventory 5/23/05 Hybrids Sensors Frames STHPKITSTHPKIT L12pu L12pd
TOB Status Joe Incandela University of California, Santa Barbara For the TOB Group Tracker General Meeting Sep. 21, 2001 at CERN Slides courtesy of: A.
DOE REVIEW 1/20/04 – Dean White 1 Gantry Module Assembly TOB & TEC Dean White University of California, Santa Barbara.
1 Hybrid & Module Testing Status Week of 4/25-4/29.
Recent TOB Developments First LT failure and Stereo Module Status J. Incandela With slides provided by E. Chabalina, A. Affolder, Dean White.
Tracker Week – UCSB Gantry Status – Febuary 10, 2004 – Dean White 1 Gantry Status University of California Santa Barbara UCSB Gantry Team: Andrea Allen.
1 UCSB Module Assembly Week of 5/23-5/27. 2 FNAL & UCSB Inventory HybridsSensorsFrames FNALUCSBFNALUCSBFNALUCSB STHPKITSTHPKITSTHPKITSTHPKIT L12pu /
Status of the Tracker Outer Barrel J. Incandela University of California Santa Barbara for the illustrious TOB Group Tracker General Meeting October 26,
1 UCSB Module Assembly Week of 4/11 – 4/15. 2 UCSB Parts Inventory 4/4/05 Hybrids Sensors Frames STHPKITSTHPKIT L12pu ST193 L12pd ST193.
1 CMS week 15/03/05, Module Production Meeting, Dean White - UCSB Status of Sensor Bias Connection Dean White For the US CMS Group.
1 Hybrid & Module Testing Status Week of 6/6-6/10.
1 UCSB Module Assembly Week of 5/9-5/13. 2 UCSB Parts Inventory 5/9/05 Hybrids Sensors Frames STHPKITSTHPKIT L12pu L12pd L12su
US Module and Rod Production Overview and Plan For the US CMS Tracker Group.
1 US Testing Status-Anthony AffolderModule Testing Meeting, Dec. 11, 2003 Update of US Testing Status Anthony Affolder On behalf of the US testing group.
CMS Week – UCSB Gantry Status – June 8, 2004 – Dean White 1 Gantry Report University of California Santa Barbara UCSB Gantry Team: Andrea Allen Dave Staszak.
1 US Testing Update-Anthony AffolderTracker Meeting, Feb 10, 2004 US Module Testing Update Anthony Affolder (On behalf of the US testing group) Update.
Slide 1Susanne KyreDOE review, January 20, 2004 Wirebonding for TOB and TEC Susanne Kyre University of California, Santa Barbara.
Status of TOB Modules & Rods J. Incandela For the US CMS Tracking Group Tracker Week, Feb
Slide 1 Electrical Testing at UCSB -Anthony AffolderDOE review, January 18, 2005 Electrical Testing at UCSB: Hybrids & Modules Anthony Affolder On behalf.
US Module Production June 2, 2005 J. Incandela For the US CMS Tracker Group.
1 UCSB Module Assembly Week of 5/2-5/6. 2 UCSB Parts Inventory 5/9/05 Hybrids Sensors Frames STHPKITSTHPKIT L12pu L12pd L12su
1 UCSB Module Assembly Week of 4/25 – 4/29. 2 UCSB Parts Inventory 5/2/05 Hybrids Sensors Frames STHPKITSTHPKIT L12pu ST193 L12pd ST193.
1 TEC pilot run status Goal : test TEC module production rate capabilities - 15 R6 modules assembled on Brussels Gantry and bonded in Aachen I - 15 R7.
Status Brussels GANTRY Ê Assembly of R3 modules (36 modules) 4 precision of the modules 4 problems with DataBase (not adapted for single sensor modules)
Slide 1Susanne KyreTracker week, October 2005 TEC/TOB bias bonds Susanne Kyre University of California, Santa Barbara.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
Abe Seiden December 2003 SCT Week S USA SCT Barrel Module Assembly SCT Week CERN December 2003 Presented by Abe Seiden U.C. Santa Cruz.
DOE Rev of Run IIb Sep 24-26, Detector Production WBS James Fast Fermilab.
Fermilab PMG - Results from module testing - April 9, 2004 – E.Chabalina (UIC) 1 Results from module testing E.Chabalina University of Illinois (Chicago)
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)
G. Steinbrück 6/21/ Premounting of AOHs for the TEC in Hamburg Georg Steinbrück Hamburg University AOH Meeting, CMS Week 6/21/2005  Status of AOH.
CMS Tracker Week, CERN, Oct Oct 2005CMS Tracker Week - Module ProductionSalvatore Costa - Catania Report from Module Bonding Working Group.
A.Cheremukhin (JINR, Dubna) CMS Preshower PRR, July 5-6, 2001, CERN1 Micro-module assembly -  -module elements - alignment of the silicon sensors to the.
D0 PMG, May 04, 2000 Slide 1 Schedule DØ SMT Status Report.
Status Brussels GANTRY
FNAL Production Experience
Hybrid & Module Testing Status
US Module Production Status
Results from module testing
Vienna Module Production
FNAL Module Testing Status
UCSB Module Assembly Week of 11/28 – 12/2/05 Week of 11/28 – 12/2/2005.
FNAL Module Testing Status
Module Production in Brussels
Hybrid & Module Testing Status
FNAL LT Testing Status Modules – were tested during Aug 2 – Aug 9.
Passitivation Location
Module Testing Status Week of 6/14-6/20.
Electrical Testing at UCSB: Hybrids & Modules
UCSB Module Assembly Week of 12/5 – 12/9/05 Week of 12/5 – 12/9/2005.
Hybrid & Module Testing Status
TOB Module Production Overview and Plan
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
US Module Testing Progress Report
Status of Bonding R1N, R1S, R3 of TEC University of Hamburg
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
FNAL Hybrid Testing Status
Presentation transcript:

US Tracker Group Status Sep. 1, 2005 J. Incandela For the US CMS Tracker Group

Sep. 1, J. Incandela 2 US Hybrids Inventory (approx) Hybrids as of 5/7/05 FNALITUCSBIT L12pu L12pd L12su L12sd L34pu L56pu R5p 33- R5s 5541 R6 197 R7 20- Have maintained TEC production We have not built new TOB modules for several weeks Developed backplane wirebonding (see below). As a result of this stoppage, we now have a decent stock of TOB components Will allow us to sustain uninterrupted production for some time…

Sep. 1, J. Incandela 3 US Module Assembly (as of 8/29) Week Cumulative ABFABF% A or B L12pu % L12pd % L12su % L12sd % L34p % L56p % R5N % R5S % R % R % Total %

Sep. 1, J. Incandela 4 Module Assembly Issues Past Week Both sites had 2 F grade modules due to sensor angles slightly out of specifications. UCSB has only one operational wirebonder for modules. Repair scheduled for Sep.12. Need to improve speed of repair response from K&S (can do so with priority contract ~20k$/year). Machine is however usable for backplane bonds and we are using it for TEC modules now. Preparations for TEC at FNAL UCSB R7 plate designs have been adapted to FNAL gantry requirements. Manufacture of parts this month.

Sep. 1, J. Incandela 5 US Hybrid Testing Totals (8/29/05) Continue to recover previously failed hybrids by repairing them. Yield now 98.7%, was 97.1% in June.

Sep. 1, J. Incandela 6 US ARCS Testing Results 2675 Total Tested 2640 Grade A 10 Grade B 25 Grade F This week: 34.5 of channels bad (0.072%) Total Production: 1057 of channels bad (0.061%) WIEN BOX: 3 modules have failed in LT

Sep. 1, J. Incandela 7 Module Quality Total Production: 1057 out of channels are bad (0.061%)

Sep. 1, J. Incandela 8 Completed fractions

Sep. 1, J. Incandela 9 Ag Epoxy Issues: HV Resistance

Sep. 1, J. Incandela 10 Ag Epoxy biasing data: 2 months on the shelf

Sep. 1, J. Incandela 11 Backside Bonding – TEC Modules We have backside bonding fixtures built for R5N, R5S, R6 and R7 modules. Modules are placed on the bonding fixture without carrier plate. Much care was taken to make sure teflon blocks are free of metal chips since the front side of the sensors are very delicate. 5 – R7, 18 – R5S and 21 – R5N modules (46 total) have been backside bonded and arcs tested without problem.

Sep. 1, J. Incandela 12 Backside Bonding – TEC Modules Bonds height average.30 mm. Last box of 20 modules were bonded in less than 1 hour. We are putting on 15 bonds. This is what the TIB people have done. Bond pull strengths have all been over 7 grams.

Sep. 1, J. Incandela 13 Backside Bonding – TEC Modules We encapsulate the backside bonds for protection from damage. Single wire bonds have been encapsulated on test pieces with sylgard 186 and DC They are being thermal cycled from -30C to +50C. After 30 cycles both still conduct fine. We will continue thermal cycling them for at least 50 cycles. They are held at the extremes of -30C and +50C for 30 minutes during each cycle. The encapsulant height can be close to the frame thickness. To make sure we do not go outside this envelope, we will squeegee off any excess to constrain to.80 mm height.

Sep. 1, J. Incandela 14 New TOB Modules Solder a gold plated 100  m thick Kapton tab to the frame circuit. Initial bonding tests of bonding show no problems. Built fixtures for SS and DS-r  frames that hold the Kapton tabs in place while they are soldered. Assures minimal gap. One small recess and one block of Teflon must be added to our assembly plates to accommodate these tabs and allow them to be glued to the back of the sensors during assembly. The blocks were made and glued on some assembly plates yesterday. They will get machined today. Will restart TOB production next week

Sep. 1, J. Incandela 15 Backside Bonding – New TOB Modules

Sep. 1, J. Incandela 16 Backside Bonding UCSB – Old TOB Modules For most modules we can silver epoxy a wirebond tab to the portion of the frame Kapton bias ring (photo). For modules that already have epoxy all around the ring, we will run a wire to the other side of the frame as proposed by FNAL.

Sep. 1, J. Incandela 17 FNAL: Wire Connection to Backside FNAL to use magnet wire with acceptable insulation rating soldered to HV on topside, then run to back side where it connects to a Au- plated Kapton piece that bridges the 2 sensors. No interference problem with the carrier plates or with double-sided rod construction.

Sep. 1, J. Incandela 18 ROD Workshop We had a US rod production workshop Aug at UCSB Focused on electrical testing, since mechanical issues under control Goal was to firm up details of procedures, tests, etc., so that we will be really ready for production when the new ICC cards show up Generated set of 22 action items Minutes at Several items need actions taken a by CERN experts: Awaiting optical FECs from CERN Should make system more robust! We will likely need help from Europe for installation Digital Tests Still waiting for CERN experts to help us define these! ICC cards swap Have many rod frames in US that need to have ICC cards swapped We prefer this is done at CERN. We can send manpower.

Sep. 1, J. Incandela 19 Integration team evolution US integration team starting to build up J. Spalding will be my deputy at CERN (resident as of Oct.) S. Tkaczyk will also be resident and will help oversee testing group J. Lamb who is my graduate student at UCSB and who has substantial rod testing experience will arrive in Sep. and stay resident indefinitely. We expect to have a post-doc and another student coming by January and several excellent and very experienced people have been contacted and are considering residence at CERN.