PEP-II Overview & Ramp Down Plan J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007.

Slides:



Advertisements
Similar presentations
NuMI Radiation and Environmental Protection NBI th International workshop on Neutrino Beams and Instrumentation September 5-9, 2006 Mike Martens.
Advertisements

Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
PEP-II Ramp Down to a Minimum Maintenance State J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
PEP- II Linac Accelerator Systems Department The PEP-II B-Factory Accelerator John T. Seeman Assistant Director Particle and Particle-Astrophysics Division.
June 2-4, 2004 DOE HEP Program Review 1 M. Sullivan for the PEP-II Team DOE High Energy Physics Program Review June 2-4, 2004 PEP-II Status and Plans.
Accelerator Systems Division FACET Project Management John Seeman for the FACET Study Group PPA Directorate Stanford Linear Accelerator Center DOE FACET.
Page 1 PEP-II D&D Planning & Costing Exercises John Seeman Accelerator Systems Division SLAC National Accelerator Laboratory.
July 7, 2008SLAC Annual Program ReviewPage 1 PEP-II DND Engineering Planning S. DeBarger Accelerator Systems Division.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
PEP-II and BaBar DND Review M. Sullivan Mar 23-24, 2009Page 1 PEP-II Overview and MMS Status Michael Sullivan SLAC National Accelerator Laboratory.
SLAC Accelerator Department The PEP-II Accelerator John T. Seeman Assistant Director of the Technical Division Head of the Accelerator Department SLUO.
Accelerator Systems Division FACET Accelerator Overview John Seeman for the FACET Study Group PPA Directorate Stanford Linear Accelerator Center DOE FACET.
Re-commissioning the Recycler Storage Ring at Fermilab Martin Murphy, Fermilab Presented August 10, 2012 at SLAC National Laboratory for the Workshop on.
Future Very High Luminosity Options for PEP-II John T. Seeman For the PEP-II Team e+e- Factories Workshop October 13-16, 2003.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
PIP Update Linac Utilities for 2014 shutdown Matthew Gardner, 4/23/14.
ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
WAO, Trieste, 24th - 28th September 2007 An Overview of the Reliability and the Fault Trends of the SRS Cheryl Hodgkinson Daresbury Laboratory Synchrotron.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II EFAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron.
Material Disposition Planning Olga Ligeti Radiation Protection Department MARCH 24, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II ASAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
Beam Dump Upgrade Planning Keith Welch 2/5/13. Drivers for Upgrade Historical Problems – Hardware failures Helium system Windows, diffusers Dehumidifiers.
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
PEP-II Disassembly Technical Systems PEP-II D&D Review 6-Aug-2007 S.DeBarger S.Ecklund, A.Hill, D.Kharakh, M.Zurawel.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Civil Engineering and Services - drawings for CDR - CDR chapter J.Osborne and M.Gastal for CES WG 1.
July 7, 2008SLAC Annual Program ReviewPage 1 PEP-II in Run 7 and Transition Planning John T. Seeman Assistant Director PPA/LCLS.
1 Target Station Design Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory EuroNu Annual Meeting 2012.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
SABER, “maybe” a new facility in the South Arc (South Arc Beam Experimental Region) End Station A (ESA) in 2007 ILC Test Beams in 2008 Test Beams beyond.
Calder Hall Sellafield Decommissioning Martin Adam Heriot-Watt Edinburgh 2008.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
B Factory D&D Review: March 23, 2009 Page 1 Overview of re-use requests and related issues D. MacFarlane Deputy Director, PPA.
Spreaders & Recombiners Beam Transport Michael Bevins May 30, GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation.
D&D Review 6 August PEP-II Minimal Maintenance State Upkeep Stan Ecklund (J. Seeman, S. DeBarger, D. Kharakh, M. Zurawel)
B Factory D&D Review: March 23, 2009 Page 1 B Factory D&D: Strategy Overview S. Kahn Director, PPA.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
S UPER B site status report S. Tomassini INFN-LNF On behalf of SuperB Collaboration SuperB general meeting– Frascati – December 1-5, 2009.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
WBS – 30 Straight Section Reconfiguration g-2 Accelerator – 30 Straight Section Reconfiguration D. Still Fermilab Muon g-2 IDR, June 5-7.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Mini MAC II PEP-II hardware M. Sullivan Apr 23-24, 2009Page 1 PEP-II Hardware Status M. Sullivan SLAC National Accelerator Laboratory Mini-MAC II Frascati,
November 12-13, 2007 Super-B Factory: Accelerator Costing, PEP-II Hardware and Schedule J. Seeman SLAC International Review Committee meeting November.
Report Technical Director Storage-Ring-Installation Completed
SUPERB site status report for layout v12
CBETA Technical Review
John T. Seeman DOE PEP-II Operations Review April 26, 2006
SuperB Injection, RF stations, Vibration and Operations
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Michael Sullivan and John Seeman SLAC National Accelerator Laboratory
Potential Use of PEP-II Magnets by Project X
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
SuperB RF and Other Components
MEIC Cost Estimate Overview
Accelerator R&D Results from the B-factory
J. Seeman Assistant Director for PPA/LCLS
FACET Accelerator Overview
Status of RF at HZB: BESSY II, MLS, bERLinPro and BESSY VSR
Linac LLP Outline LINAC Long Lead Procurements
FACET Accelerator Overview
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

PEP-II Overview & Ramp Down Plan J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007

Topics Overview of the PEP-II Collider –PEP-II turns off September 30, General list of components and buildings Categories of issues Overview of Ramp Down Plan Overview of Minimum Maintenance State (MMS)

PEP-II B Factory at SLAC Located at the Stanford Linear Accelerator Center

PEP-II e + e - Collider BaBarDetector Feedbacks Diagnostics LER RF 476 MHz HER RF 476 MHz 3.1 GeV positrons x 9 GeV electrons C = 2200 m

Beam Line Lengths HER = 2200 m LER = 2200 m HER injection line = 2300 m LER injection line = 2900 m Total length of beam line = 9600 m –(  6.0 miles)

Other components ~10 miles of cable trays ~200 miles of cable (typically 1 inch dia) ~7 miles of water distribution lines 15 klystron–cavity systems ~900 electro-magnets per ring (~1800) ~6 miles of vacuum chambers Thousands of supports

PEP-II Arc Section LER HER

B-Factory RF Klystrons C. Pearson

PEP-II RF Cavities

Magnets Vacuum chambers Lights Cable trays Sprinkler pipes Fire sensors Utility pipes Supports

Document Items 1) The components in the tunnel should be technically documented and the data stored and correlated to the components. 2) Spare parts should be documented and collected. 3) The components should be offered to other DOE projects and/or facilities.

My list of valuable components RF systems Electro-magnets Power supplies Vacuum pumps and diagnostics Some beam instrumentation (e.g. streak camera at ~180 k$) Feedback amplifiers Water pumps, pump motors, heat exchangers

PEP-II Interaction Region (IR) Halls (six)

PEP-II IR Hall 12 (on tour today)

PEP-II IR2 with BaBar (on tour)

PEP-II RF High Voltage Pads and Water Pump Stations (three)

Support Buildings of PEP-II (six)

PEP-II Buildings Outside the “Radiation Fence” (two)

PEP-II Water Pump Pads (three)

PEP-II Power Distribution (~five)

PEP-II External Cable Trays

PEP-II Klystron High Voltage Power Supplies (15 total)

PEP-II Air Vents (seven)

Cut and Cover Region of PEP-II

PEP-II Klystron Building (three)

PEP-II Power Supply Buildings (nine)

PEP-II Cable Distribution

PEP-II injection line in Linac Linac LER injection line HER Injection Line

Injection Line (South)

PEP-II Injection Line

PEP-II Injection Septa (two)

PEP-II dipoles in 1994 ready for installation

PEP-II tunnel ceiling

PEP-II ground water wall leaks

PEP-II Sump Pumps

Wall Corrosion

PEP-II Utility work in late March 2007 (3 days) for LCLS PEP-II cooling water and air lines Transite pipes

Transition & DND planning Transition plan white paper: input to FY09 budget process –Describes transition from fully operational state to a minimal- maintenance state in FY09-FY10 Outlines major tasks and timelines for this transition Extrapolations from existing PEP-II and BABAR operational experience –Outlines scenarios for dismantle and disposal phase that emerged from discussions with OS/HEP in early May –Input to FY09 budget development, FY10-FY11 planning Transition and D&D task force: in progress –Established at beginning of May to review and refine transition plan and develop next level of planning for D&D in light of white paper scenarios –Feedback from this review will be used to develop a more refined and detailed D&D plan in fall 2007

Transition planning assumptions FY09-FY10: Transition minimal maintenance state –B Factory will immediately transition to minimal-maintenance state following end of operations FY10-FY14: Minimal maintenance state –Kept in minimal-maintenance state to prevent deterioration of equipment –Envision possibility for strategic re-use of components For example, potential interest in equipment as contribution to an off-shore Super B Factory. About FY15: Dismantle and dispose –Equipment scheduled for removal, and storage or disposal –Costs to be borne by DOE Scenarios for disposal depend on whether existing moratorium on recycling metals from accelerator housing remains in effect or not

Minimal Maintenance State (MMS) PEP-II –Cooling systems of magnets and vacuum drained & dried –Documentation of parts and spares –Vacuum system vented and secured –RF systems, including power supplies, klystrons, cavities, circulators, and dumps drained and secured –Fire protection, tunnel lighting, water seepage system all maintained –Estimate ~$1 million/year in manpower, M&S, and electricity costs for tunnel maintenance (not equipment) –Security watches over the system –Crane inspections –Controls maintenance for safety issues (PPS/Fire)

Tasks and timelines: FY09-FY10

Manpower and budgets for transition Budget for MMS state is almost entirely building maintenance costs (sump pumps, lights, tunnel integrity) and not directly the cost of maintaining the equipment

Ramp Down Work Scheduling There are other items going on in October 2008: –LCLS final construction –SABER initial preparations –Routine down maintenance repairs for next Linac run –PEP-II ramp down will have lower priority during down! Is it best for many people to work for a short period (~ 1 month) or a few people for many months (~14)? It is likely that the PEP-II ramp down work will be delayed until the linac turns on later in the fiscal year, which avoids overlap with intense linac work period and allows leveling of man power loading. –Thus, likely that a slower approach will be better.

Dismantling and disposal Major factor: DOE moratorium on removal for salvage of volumetrically contaminated metals from accelerator areas –In effect since 2000, waiting for National Regulatory Commission to establish standards –Possible to move equipment to other laboratories, but not to recycle commercially; options for disposal may be expensive and/or limited Scenario I: –Provision for development of onsite storage of BABAR and/or PEP-II components removed from IR halls or tunnels –Moratorium does not apply to service buildings and regions in IR halls outside controlled access area Scenario II –Moratorium resolved, so that material with no residual activity can be removed and recycled

FFTB Metals Storage (FY2006)

FFTB Shielding Storage (FY2006)

SPEAR-II Metals Storage (~FY2001)

Conclusions The PEP-II ramp down scope has been identified. An initial transition plan has been made. Initial budget and manpower estimates have been made. A resolution of the Metals Moratorium would help this process.