Target: K. Long, 21Dec2009. Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Continuing delay in material delivery! » Vespel delivery.

Slides:



Advertisements
Similar presentations
Establishing Performance Standards for PARCC Assessments Initial Discussion PARCC Governing Board Meeting April 3,
Advertisements

MICE Magnetic Investigation of T2 MICE/ISIS Target Meeting 17 th September 2010 P J Smith – University of Sheffield.
MICE MICE Target Mechanism Paul Smith University of Sheffield 8 th June 2010 (Based upon talk given by Chris Booth at CM26)
Target Operation and Status Report Chris Booth for Target Team 20 th October 2008.
MICE TARGET HARDWARE C. Booth, P. Hodgson, R. Nicholson, P. J. Smith, Dept. of Physics & Astronomy University of Sheffield, England. 1 - The MICE Experiment.
Target Paper Status Summary 13 th December 2011 Chris Booth 1.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
K. Long, 14 June, 2015  Target K. Long, Friday, 24 th April 2009.
Target: K. Long, 16Nov2009. Schedule for T2 re-instatement: T2#2: – Inspection of T2#2 documented in MICE Note 272 Some issue with Notes site … couldn’t.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
MICE Video Meeting, 10 Jan 081 Spectrometer Magnet Progress Michael A. Green Lawrence Berkeley Laboratory.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
A Tale of Two Targets … 7 th September 2009 Chris Booth The University of Sheffield.
Target: K. Long, 16Nov2009. Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Delay in material delivery: » Torlon delivery expected.
Target: K. Long, 16Nov2009. Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Continuing delay in material delivery! » Vespel and.
MICE TARGET WORKSHOP – SHEFFIELD 2 nd December Target vibration and general design issues 2. Simple Vibration - causes and forces. 3. Not so simple.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
G.Barber Mice Target Stator Field Mapping March Mice Target Stator Field Mapping G Barber, E Longhi, C MacWaters, P Smith, J Tarrant & Many others.
MICE Target Report Video Conference 05/07/07 Chris Booth Sheffield 5 th July 2007.
Target Design – Status and Plans Chris Booth Sheffield 12 th January 2005.
PRODUCTION PROCESS SchedulingInventory Incoming QC BinningPre-assemblyCalibration Final Assembly Final QA Packaging & Shipping.
The Generator. Electricity Generator Energy: The ability to do work Two Examples: Mechanical Energy: Energy that comes from the motion of an object Electrical.
Target Report Introduction Chris Booth Sheffield 20 th November 2008.
1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College.
MICE Target – Design Update and Test Plans Chris Booth Sheffield 22 nd October 2005.
K. Long, 14 October 2003 MICE-UK: progress report Progress: WP1: B&I: Target u/g (Sheffield) … PD Focus coil assembly Spectrometer Software Issues: Scientific.
Welcome to Everybody. পরিচিতি দিলীপ কুমার পাল টেকনিক্যাল টিচার্স ট্রেনিং কলেজ ইইই বিভাগ.
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
Three-phase Cage Rotor Induction Motors Resource 2 Three-Phase AC machines.
MICE Target - Risk Lara Howlett University of Sheffield.
S. Caspi, LBNL HQ Progress and Schedule Shlomo Caspi LBNL LARP Collaboration Meeting – CM13 Port Jefferson November 4-6, 2009.
Superconducting Corrector Magnet Progress Report P. Wanderer Superconducting Magnet Div; Dec. 15, 2007 T2K US B280 collaboration meeting.
Jason Tarrant / November 2008 MICE Target Mechanical Design l Jason Tarrant – STFC l Introduction »Investigations into target shaft failure »Current suspicions.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
MICE Target Installation Chris Booth & Paul Smith Sheffield 26 th July 2007.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
Motors and Generators.
Elec467 Power Machines & Transformers Electric Machines by Hubert, Chapter 12 Topic: Self-excited and compound generators, load distribution.
CERN adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of Production of support panels - Things to be settled.
Focusing Lens for PXIE SSR1 Cryomodule Summer 2012 Status 7/10/2012I. Terechkine1.
E.Guschin (INR,Moscow) 9 December 2008LED system meeting CERN Plans: PS/SPD LED monitoring system tuning Online histograms. Presenter for group of 16(64)
Capstone Design - Personal mobility - Group name : 올라가 조 박경원 정태산 이효진 강석우.
1 Estimation of Dynamic Force Coefficients from a Wet (Foamy) Annular Seal Progress Year 1 May rd Turbomachinery Research Consortium Meeting Gary.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
How Does a Wind Turbine Work?
Hi-Lumi Conductor Procurement A.Ballarino, B. Bordini, L. Oberli HL-LHC/LARP International Review of Superconducting Cable for the HL-LHC Inner Triplets.
Engineering Operations Outage Schedule Center Stack casing is scheduled to go back in the vessel today Complete NB armor, Diagnostic calibrations, clean/photo/close,
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
SBS Magnet and Support Status Robin Wines June 2013.
Programme for “Target 3” – test of alternative bearing materials (from Jason Tarrant) –Drawing updates by 11 th November –Bearings: Material approval –
Target Status Report Chris Booth & Paul Hodgson Sheffield 18 th Sept ember2008.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Chris BoothUniversity of Sheffield 1 Target Status & Progress 1 st February 2006 Disappointingly slow progress over last 2 months. However, progress is.
親愛的吉姆舅舅: 今天吃完晚餐後,奶奶說,在家 裡情況變好以前,您要我搬到城裡跟 您住。奶奶有沒有跟您說,爸爸已經 好久沒有工作,也好久沒有人請媽媽 做衣服了? 我們聽完都哭了,連爸爸也哭了, 但是媽媽說了一個故事讓我們又笑了。 她說:您們小的時候,她曾經被您追 得爬到樹上去,真的嗎? 雖然我個子小,但是我很強壯,
MICE Target – Status & Plans Chris Booth Sheffield 28 th February 2006.
Chris Booth Sheffield 29th March 2006
BSS Prep work at CERN and Acceptance of Parts
MANUFACTURING PROCESS OF TRANSFORMERS
MICE Target Report Video Conference 29/11/07
ERMC/RMM activities May 2017
Oversight Board Meeting October 3, 2017 Rob Michnoff
SIS100 quadrupole status S. Kostromin, H. Khodzhibagiyan, G. Trubnikov, FAIR 11th MAC, GSI, May,
Turing Machine
قوانين برگزاري مناقصات و آيين نامه مالي و معاملاتي دانشگاه علوم پزشكي و خدمات بهداشتي ،درماني تهران
One Coil Gun Magnet February 2, 2016.
Globus-M2 will be constructed by the end of 2015

PS magnet status D Bodart 25/06/2019.
Presentation transcript:

Target: K. Long, 21Dec2009

Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Continuing delay in material delivery! » Vespel delivery expected 23 December To progress in January 2010: – Checking forces generated with mis-aligned coils using OPERA model (PS, TB) – Devising magnetic QA rig (GB + Shf) – Devising concept for winding coils that is more precise Schedule T3: – Machining of parts (except plastic) done – Coils for T3 prepared in Sheffield: » Will consider whether to use new coils or present coils based on: magnetic analysis; Magnetic QA on T2 stator

T3 schedule: – Now awaits completion and test of T2#3 Which is ready except for plastic bearing inserts and assembly Looks like this work will start in the New Year