Hamid Shoaee LCLS FAC Controls June 17, 2008 1 LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.

Slides:



Advertisements
Similar presentations
Control and IT Systems status and strategy ALBA, Piotr Goryl on behalf of Michał Ostoja-Gajewski, Krzysztof Wawrzyniak, Łukasz Żytniak, Tadeusz.
Advertisements

Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys.
HPS MPS OVERVIEW Dan Sexton & the Safety Systems Group JLAB 1.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Stephen Norum LCLS FAC April 16, LCLS Machine Protection System Overview Interim MPS Full LCLS MPS Design Schedule.
Ernest Williams FAC November 2008 Control Systems Software Section 1 Controls System Installation Status Ernest Williams for Controls Department.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
Hal Tompkins FEE/FEL June 16, FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Hamid Shoaee Control System Installation 3/16/ Downtime Readiness Review Hamid Shoaee For LCLS Controls Group.
Patrick Krejcik LCLS April 16-17, 2007 Breakout Session: Controls Controls Commissioning Experience.
Jose Chan and Kathleen Ratcliffe FAC Review- LTU/DUMP installation Status & 6/16/08 1 Linac Installation Status, Schedule.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
Hamid Shoaee High Level Physics 20 April 2006 High Level Physics Applications Update on Plans, New Directions Fairley,
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
Hamid Shoaee LCLS Facility Advisory Committee April Control System Overview April 16, 2007 Hamid Shoaee for the LCLS Controls.
Dayle Kotturi Controls April 29, 2004 Injector Controls LCLS Facility Advisory Committee April 29-30, 2004 Outline Description.
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
1 E. Carrone 1 FEE PPS Status FAC FEE PPS Status Enzo Carrone June 8, 2009.
Hamid Shoaee LCLS Facility Advisory Committee 20 April Controls Overview April 20, 2006 LCLS Controls Group Outline Goals.
E. Michael Saleski PPS and April 20, 2006 LCLS Personnel Protection System and Beam Containment System E. Michael Saleski.
Dayle Kotturi Facility Advisory Committee Meeting October 12, 2004 Injector/Linac Controls An overview of the status of each of.
Dayle Kotturi SLC April 29, 2004 Outline Motivation Key Components Status Update SLC / EPICS Timing Software Tasks Hardware.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
Oct. 30, 2007 LCLS FAC D. Fairley MATLAB Feedback Phase II Commissioning.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
Diane Fairley High Level October High Level Applications FAC Review October 12, 2006 High Level Applications.
Stefan Moeller XES Plan for FAC Review - April 20, 2006 X-Ray Endstation Systems (XES) Status and Plan for FY06 Stefan Moeller.
Hamid Shoaee LCLS Control April 20, 2006 LCLS Control System Organization & Integration with the rest of the lab, Accelerator.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
Patrick Krejcik LCLS November 11-12, 2008 SLAC National Accelerator Laboratory 1 Post-commissioning Controls Enhancements.
Arturo Alarcon Undulator Controls Module Status 11/12/2008 SLAC National Accelerator Laboratory 1 Undulator Controls Module Status.
Hamid Shoaee Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory Controls Department LCLS Maintenance.
LCLS-II Linac LLRF Control System – L1, BC1 Zheqiao Geng Final Design Review May 7, 2012.
Hamid Shoaee LCLS Control April 20, 2006 LCLS Control System Controls Organization Overview A Progress Report Hamid Shoaee.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
Stephen Schuh Vacuum Controls SCR and 16 November 2005 Vacuum Controls System Concept Review and Preliminary Design Review.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
Magnet Controls GroupOctober 4, Scope, Cost Estimate and Schedule To Complete The LCLS Magnet PS Controls P Bellomo and Kristi Luchini.
K. Luchini LCLS Injector /BC1 Magnet PS Final Design Review, March 30, Injector and BC1 Magnet PS Controls K. Luchini.
MTCA use in Linac to replace CAMAC Tom Himel June 4,
1 The Cost & Schedule to Accomplish the Transition Proposed SLAC Controls Upgrade December 1, 2010 Ray Larsen.
Marjorie Widmeyer LCLS Injector Magnet Power March 30, LCLS Injector, Sector 21 and BC1 DC Magnet Power and Control.
Hamid Shoaee Control LCLS ARR Oct 31, LCLS Accelerator Readiness Review Control System for Injector Commissioning.
LCLS Control Group FAC – 06 Installation October 27/28, Plans for 2006 Installation October 27, 2005 Installation.
Patrick’s Updates - 8/30/11 (one slide for each of the following) 1.XTCAV Project 2.ASTA Gun Test Facility Instrumentation & Controls 3.Fast wire scanner.
Project X RD&D Plan Controls Jim Patrick AAC Meeting February 3, 2009.
31, LCLS Maintenance Personnel and Procedures Paul Bellomo.
LCLS MD Downtime William Colocho June 2014 to June 2016.
LLRF and Beam-based Longitudinal Feedback Readiness
LTU/Undulator Installation Status
Magnet PS Controls Hardware Status
e-Beams Systems Update
Electron Beam Systems ETC and Methodology
Electron Beam Systems Wrap-up
2007 Downtime Controls Installation
E-Beams Systems Manager
LTU/Undulator Installation Status
Control System Overview Hamid Shoaee LCLS Control System Manager
Installation Status & Operational Readiness Process
Electron Beam Systems ETC and Methodology
LCLS e- Beams System Overview
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
LINAC System Engineering / Design Status C.E. Rago
LCLS Control System Personnel Linac & BC2 Controls progress
Control System Overview Hamid Shoaee LCLS Control System Manager
Presentation transcript:

Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls Undulator Control System Summary

Hamid Shoaee LCLS FAC Controls June 17, New responsibilities in Controls Enzo Carrone, the new deputy in Controls Department, is now responsible for the LCLS control system

Hamid Shoaee LCLS FAC Controls June 17, Questions from Tom Himel H1: Any new problems which have come up or items where you would like our advice The immediate question of delivering of long term high level applications VS resource allocation to the linac upgrade … See Patrick Krejcik’s presentation H2: H2: MPS progress and schedule [S. Norum’s talk] H3: H3: A general overview of the schedule for hardware installation and software with emphasis on any problems [E. Carrone’s talk] H4: H4: How is the integration of the old controls group into LCLS going? How have the layoffs and shutdown of PEP effected things?

Hamid Shoaee LCLS FAC Controls June 17, Questions from Tom Himel H5: What is your situation and policy as regards hardware spares? We have started the process of converting the old CAMAC maintenance shops to support VME and other LCLS type hardware. We are also reviewing our spares needs and developing a plan for long term inventory and maintenance. H6: How is the high level applications infrastructure coming? What were the results of the review we suggested? [see P. Krejcik’s presentation] H7: When do you need to move away from MATLAB based feedbacks, and how is the new feedback development coming? The plan is to test 120 Hz operation in July of We are looking at list of issues to address, including time slot feedback, etc. BC2 Commissioning

Hamid Shoaee LCLS FAC Controls June 17, LCLS MPS… [S. Norum’s talk] Great progress has been made developing the hardware and software Completed hardware MPS Link Processor MPS Link Node GbE Switches Beam Loss Monitor QADC and transition boards prototypes complete In progress QADC currently being tested Completed software EPICS PVs for fault status, bypass status and value Machine state buffer Machine protection logic (algorithm) handling Machine rate buffer Mitigation processing

Hamid Shoaee LCLS FAC Controls June 17, Undulator Magnet PS - PH4 Installation Program 54 MCORs - UND 18 QUAD 36 X/YCOR B913B MCORs – UND 15 QUAD 30 X/YCOR 03 Intermediate PS – DUMP 06 MCORs – DUMP

Controls Installation for LTU, Undulator, Dump LTU/Und/Dump Controls Install LTU/UndComm. Re-commission Inj/BC2 to SL2 First Light in FEE FEE/NEH Install PPS Cert. LTU/Dump CD-4 (7/31/2010) J J F F M M A A M M J J J J A A S S D D J J F F M M A A M M J J J J A A S S O O N N D D J J F F M M A A M M J J J J ON A A Down PPS A A M M Linac/BC2 Commissioning FEE Comm Comm. April 18, 2008

Hamid Shoaee LCLS FAC Controls June 17, Remaining Controls installation benefits greatly from the injector, linac & BC2 experience LTU Controls is similar in scope to Linac & BC2 We are past the engineering learning curve with very little development remaining Almost all procurement is complete including 100% of cable plant All IOCs and VME crates are on hand The order for over 95% of all required control modules (PLC, ADC, motion control, etc.) has been placed Some I&C rack delivery is being delayed, no impact on installation Racks are currently being loaded & tested in high bay area

Hamid Shoaee LCLS FAC Controls June 17, Rack Assembly Area (B024 )‏ B913 & B921 PS racks B911 & B912 PS racks

Hamid Shoaee LCLS FAC Controls June 17, INSTALLATION SCHEDULE

PPS cable plant installation is in progress

Hamid Shoaee LCLS FAC Controls June 17, Equipment Status / Rack Readiness – B921

Hamid Shoaee LCLS FAC Controls June 17, Schedule – B913

Hamid Shoaee LCLS FAC Controls June 17, Safety Systems BCS Mature design Project is on schedule MPS Concurrently developing new LCLS MPS Response time of less than one pulse at 120 Hz New hardware extended 1.2 km past current MPS Non-CAMAC Ready for photon section PPS The system design is based on the extension of the injector PLC- based architecture Need to now address the BSY area

Hamid Shoaee LCLS FAC Controls June 17, Undulator Motion Control Software delivered by ANL and is being checked out

Hamid Shoaee LCLS FAC Controls June 17, Undulator Control System is on schedule for field installation Magnets power supply and controls in very good shape Loaded racks are being tested in B024/B15 There is a detailed schedule covering bench testing, through field installation Software design is mature, requires little if any changes RF BPMs – production proceeding well Receivers will be shipped to SLAC June-July Timing, Vacuum, Networks are all on schedule Wire position monitor & hydrostatic leveling system will be interfaced to the control systemsystem

Hamid Shoaee LCLS FAC Controls June 17, Top Level CD Org Chart

Hamid Shoaee LCLS FAC Controls June 17, Software Engineering Section

CD-PCD Project Work Flow

Hamid Shoaee LCLS FAC Controls June 17,

Controls Status since the last review The Linac/BC2 Controls installation went very well The system was delivered in December 2007, within a week of the scheduled date (12/03/07)

Hamid Shoaee LCLS FAC Controls June 17, Summary of Controls Sub-Systems installed for Linac and BC2 Commissioning Cable Plant Networking Magnet power supply Vacuum Controls LLRF Timing system Laser control upgrade OTR/YAG imaging BPM Wire Scanners Faraday Cup Cerenkov monitor Moveable collimator BC2 beamline control Bunch length monitor MPS BCS Configuration software MATLAB feedback system Bunch length measurement

Linac & BC2 Controls in use by physicists & Operations

New Feedback framework & bunch length measurement applications are in operation

Hamid Shoaee LCLS FAC Controls June 17, Injector laser Controls has been upgraded for BC2 operation

Hamid Shoaee LCLS FAC Controls June 17, Conclusions The linac & BC2 control system is online & operational We are on schedule for the installation and completion of the electron control system The major risk for the above items is schedule rather than technical complexity detailed plans are in place for the undulator control in collaboration with ANL