MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO April 6, 2009.

Slides:



Advertisements
Similar presentations
MOM Report October 9- Now Linda R. Coney UCR. October 15 th Running Target Target Beamline Magnets Beamline Magnets Detectors? Detectors? Could not turn.
Advertisements

K. Long, 18 April, 2015 Beam-line status — red sky at night?
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
MOM report 23/9 – 28/9 G.CECCHET. MOM report Hall PPS commissioning Target tests last night MOM laptop.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
MOM Report Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory MICO March 16, 2009.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 21 September, 2009.
Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009.
MICO 1 st February 2010 Terry Hart (MOM). MICO 1 st February June 2015 Decay Solenoid DS will not be ready for Machine Physics. Matt Hills spent.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO March 23, 2009.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
MICE FAC Alain Blondel 1 Summary of run meeting 8 August 2011 Present: Andy Nichols Tim Hayler Pierrick Hanlet Gail Hanson Linda Coney Victoria.
MICO 22 nd February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
Computing Panel Discussion Continued Marco Apollonio, Linda Coney, Mike Courthold, Malcolm Ellis, Jean-Sebastien Graulich, Pierrick Hanlet, Henry Nebrensky.
MICO Meeting, 1 st March 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - March User Runs Plans - Suggestions.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 14 September, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
MOM Report. Shield Wall – Gone Before During After 2.
Detector Systems Update MICO March 3, MICE Detector Systems  CKOV u CKOV humidity (HIH4000) and temperature (LM35) sensors in hand for installation.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting June 7, 2010.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 4, 2011.
MICO 8 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - Problems and Issues.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 19, 2010.
Applied Science Division MICE Prototype Control System T W Bradshaw April 2004 MICE Proto Control System Organisation.ppt.
MICO 15 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
Detector Systems Update MICO March 10, MICE Detector Systems  CKOV u No update  TOF0/1 u Tests with laser injection system progressing. u Tests.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO March 30, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting May 24, 2010.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 7 September, 2009.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
MICE - UK Project Progress Roy Preece 30 th April 2013.
Control and Monitoring System / EPICS Pete Owens Daresbury Laboratory.
Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
1 Re-gas compressors to 2.20 Mpa - Me New oil mist adsorbers in compressors at 20k hrs – Me Comp1 11K hrs, Comp2 11K, Comp3 20K, Comp4 18K Service cold.
MOM Report Victoria Blackmore VC /06/11 1/7.
Click to add Text L. CONEY1 MICE Shifter Training June 2015.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICE Video Conference May 7, 2009.
MOM Report Paul Hodgson Paul Soler Victoria Blackmore VC-139: 14/04/111/8.
Alain Blondel MICE VC 12 March 2009 Brief MICE news 1. Decay solenoid: operations will restart in early July. Criteria for acceptance have been specified.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
MICE VC MOM Report, 25 th February 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - Machine Physics and User Runs - Suggestions.
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Running plan Step I.1 Basic radiation levels. I.1.1 ISIS running with beam elements on, target off, beam stop shut. Establish permanent MICE monitoring.
VC117 February 2009Jean-Sébastien GraulichSlide 1 MOM Report o Yagmur Torun ( June 15 - July 14) o J.S. Graulich ( July 13 - August 7) Jean-Sebastien Graulich,
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
MICE MICO Alain Blondel 23 December MICE Commissioning needs 22 December 08.
1 Re-gas compressors to 2.20 Mpa - Me New oil mist adsorbers in compressors at 20k hrs - Me Service cold heads - Sumitomo Replace broken insulating vac.
MICE CM30 Goals of the Meeting Alain Blondel 1 MICE CM30 – Goals and Status.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.
Beamline Update Adam Dobbs, MICE CM38 Feb Contents Recent and Upcoming Activities Target Conventional magnets Decay Solenoid Proton Absorber Summary.
MICE Online Group Linda R. Coney UCR MICE CM31 UMiss October 2011.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Linda Coney MICO June 6, 2011 MICE Online Report.
MICE Hall Summer Workplan
Project Manager’s Report + DC/MoM Report
Presentation transcript:

MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO April 6, 2009

Commissioning Needs-Coney2 Commissioning Needs Working Decay Solenoid – Stands..Huge Progress Made —Many thanks to Mike Courthold, Matt Hills, Willie Spensley and Co. —MLI installation done —Pumped down over the weekend —Cooldown commencing today —Watch over Easter – cold by week from Wednesday? —Worth bringing in PSI expert for Quench Protector o Who is coming? When will they be here? Working target – Stands.. —one in R78 for demo —one in ISIS for data

April 6, 2009Commissioning Needs-Coney3 Issues Detectors – —luminosity monitor o Brunel & Paul Soler working on this o Case for it will be made by Alain Blondel at video conference —Tracker cryostats o Cryostat 1 He leak gone – see discussion by Malcolm Ellis o Install emergency shutoff valves on cryostats – this week o Install exhaust filter – this week —CKOV o New temp and humidity monitoring device installed o Need network connection and power in the DSA – have temporary o HV power supply crate died – replaced w/new one – testing now Get Decay Solenoid magnet-on lights working —reposition light on top of turret; check light in ISIS vault – will be done this week

April 6, 2009Commissioning Needs-Coney4 Issues Documentation inventory/overhaul - ongoing —Instructions for shifters – things are in flux, old documentation needs updating —Safety – need all relevant documents in one obvious place Computing —Need network connections to progress in Hall —Still cannot print on OKI printer in R76 —Need Windows PC in MLCR – done next week —Need connection to GRID from MLCR – in progress Need beamline magnet on to test alarm handler —Pressure regulators installed on Q7-9, water pipe connections made in trench —Water restored to magnets – end of this week