High Power Hg Target Conceptual Design Review Equipment Installation at CERN V.B. Graves P.T. Spampinato T.A. Gabriel Oak Ridge National Laboratory February.

Slides:



Advertisements
Similar presentations
Regional Routing Model Review Frank Southworth Oak Ridge National Laboratory Oak Ridge, TN NETS Program Review December 12, 2005 Washington DC.
Advertisements

Mercury Intense Target (MERIT) Update Status of the Target System Design P.T. Spampinato V.B. Graves T.A. Gabriel Muon Collaboration Friday Meeting October.
Mercury Chamber Update V. Graves NF-IDS Meeting October 4, 2011.
A Free Jet Hg Target Operating in a High Magnetic Field Intersecting a High Power Proton Beam Van Graves, ORNL P. Spampinato,T. Gabriel, ORNL H. Kirk,
MERIT Hg System Design V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Review Meeting Brookhaven National Laboratory Dec 12, 2005.
NTOF11 Hg System Design Status Van Graves Tony Gabriel, Phil Spampinato Collaboration Meeting – Princeton University Apr 2005.
Titan-izing the Target Module V.B. Graves 16 Dec 2005.
Oak Ridge SNS Experimental Facilities X /arb 1 SNS MPS Review Target-MPS Review WBS Ron Battle Target Controls, Target Systems Experimental.
AB/ATB-EA ML, le 30/03/071 MERIT INSTALLATION. AB/ATB-EA ML, le 30/03/072 MERIT INSTALLATION Total supported weight Solenoid: 5500 kg (12000 lbs) Hg System.
Harold G. Kirk Brookhaven National Laboratory The CERN Target Experiment Schedule and Budget MERIT Review BNL December 12, 2005.
MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.
Target System Transportation and Decommissioning P.T. Spampinato V.B. Graves Hg System Safety Review CERN June 19-20, 2006.
Hg System Design V.B. Graves P.T. Spampinato MERIT Hg System Safety Review CERN June 19-20, 2006.
Managed by UT-Battelle for the Department of Energy Neutrino Factory Mercury Containment Concepts V.B. Graves 2 nd Oxford-Princeton High- Powered Target.
High Power Hg Target Conceptual Design Review Hg Jet Nozzle Analysis M. W. Wendel Oak Ridge National Laboratory February 7-8, 2005.
Neutron Scattering Experiment Automation with Python RT2010 Conference, Lisbon, Portugal (PCM-26) Piotr Żołnierczuk, Rick Riedel Neutron Scattering Science.
MERIT Collaboration Meeting ISSUES RELATING TO THE Hg-JET TARGET SYSTEM P.T. Spampinato V.B. Graves T.A. Gabriel Princeton University November 17, 2005.
MERIT Hg System Design Update V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting Princeton University Nov 17-18, 2005.
N UCLEAR S CIENCE AND T ECHNOLOGY D IVISION O AK R IDGE N ATIONAL L ABORATORY U.S. D EPARTMENT OF E NERGY Muon Collider-Neutrino Factory Collaboration.
High Power Hg Target Conceptual Design Review Hg Target System Cost Estimate V.B. Graves P.T. Spampinato T.A. Gabriel Oak Ridge National Laboratory February.
CERN Hg Jet System V.B. Graves P.T. Spampinato T.A. Gabriel MUON Collaboration Meeting Lawrence Berkeley National Laboratory February 16, 2005.
Harold G. Kirk Brookhaven National Laboratory MERIT Installation Issues CERN Meeting June 20, 2006.
Mercury Nozzle Status V.B. Graves Hg Jet Design Meeting Princeton University Nov 15, 2004.
High Power Hg Target Conceptual Design Review Hg Target System Controls V.B. Graves P.T. Spampinato T.A. Gabriel Oak Ridge National Laboratory February.
High Power Hg Target Conceptual Design Review Hg Target Design P.T. Spampinato V.B. Graves T.A. Gabriel Oak Ridge National Laboratory February 7-8, 2005.
N UCLEAR S CIENCE AND T ECHNOLOGY D IVISION O AK R IDGE N ATIONAL L ABORATORY U.S. D EPARTMENT OF E NERGY Muon Collider-Neutrino Factory Collaboration.
MERIT Hg System Final Design Review Hg Target System Design V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma Science & Fusion.
MERcury Intense Target (MERIT) Overview Van Graves, ORNL Syringe Procurement Kickoff Meeting Airline Hydraulics Bensalem, PA Oct 28, 2005.
Hg System Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting October 20, 2006.
Mercury Catcher Status V.B. Graves Hg Jet Design Meeting Princeton University Nov 15, 2004.
Baseplates and Hg System Handling V.B. Graves P.T. Spampinato MERIT Hg System Safety Review CERN June 19-20, 2006.
High Power Hg Target Conceptual Design Review Hg Target Interface with Solenoid V.B. Graves P.T. Spampinato T.A. Gabriel Oak Ridge National Laboratory.
Hg System Decommissioning V.B. Graves P.T. Spampinato CERN Feb 7-8, 2008.
High Power Hg Target Conceptual Design Review Design Requirements, Interfaces, and Schedule P.T. Spampinato V.B. Graves T.A. Gabriel Oak Ridge National.
Target System Operations and Hg Handling P.T. Spampinato V.B. Graves MERIT Hg System Safety Review CERN June 19-20, 2006.
Managed by UT-Battelle for the Department of Energy Follow-on MERIT Testing at ORNL Van Graves NFMCC Friday Meeting Feb 29, 2008.
Managed by UT-Battelle for the Department of Energy Review of NFMCC Studies 1 and 2: Target Support Facilities V.B. Graves Meeting on High Power Targets.
Mercury Chamber Considerations V. Graves IDS-NF Target Studies July 2011.
UCN Phase 2 Design Status September 10, Design Components Bulk Shielding Target Crypt Cryogenic Insert Target Insert UCN Port Beam Window Cooling.
Water Tests of Hg System V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting Dec 8, 2006.
Target Design Meeting Nozzle & Hg Collection Tests, Design Requirements, Instrumentation, Containment, Windows, Diagnostics, Controls, Base Support Structure,
Hg Delivery System Fabrication Status V.B. Graves P.T. Spampinato Muon Collaboration Friday Meeting May 5, 2006.
Rare Isotope Accelerator (RIA) Remote Maintenance Concepts Dave Conner Oak Ridge National Laboratory RIA R&D Participants: Argonne National Lab: J. Nolen.
HYSPEC Instrument: Status and Performance M. Hagen Neutron Facilities Development Division, SNS, Oak Ridge National Lab. W.J. Leonhardt and A. Ruga Condensed.
IDS-NF Mercury System Overview Van Graves IDS-NF 5 th Plenary Meeting April 9, 2010.
NTOF11 Collaboration Meeting Non-Design Issues for the Mercury Jet Target P.T. Spampinato V.B. Graves T.A. Gabriel Princeton University April 29-30, 2005.
MERIT Hg System Final Design Review Hg Target System Operations V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma Science.
Managed by UT-Battelle for the Department of Energy Hg System Decommissioning Activities V.B. Graves NFMCC Friday Meeting Feb 29, 2008.
Addendum to EDMS document “Instruction Manual for inserting the CMS ZDCs using the HXTC crane” In addition to the ZDC detectors in the TAN instrument.
Summary of Hg System Review at CERN Van Graves 13 Sep 2005.
CERN High Power Target Hg Jet Experiment - nTOF11 Facility & Safety Meeting V.B. Graves P.T. Spampinato T.A. Gabriel CERN March 15-17, 2005.
Can Thermal Reactor Recycle Eliminate the Need for Multiple Repositories? C. W. Forsberg, E. D. Collins, C. W. Alexander, and J. Renier Actinide and Fission.
16th March 2005, ENG target A.Fabich, CERN AB/ATB 1 Status of the TT2A target experiment Status of the TT2A target experiment A.Fabich CERN AB/ATB ENG/BENE.
MERIT Hg System Final Design Review Hg Target System Controls V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma Science &
Stepper Motor Control, PLC vs VME Herb Strong, Pam Gurd Spallation Neutron Source Oak Ridge National Laboratory October 17, 2007.
OPTICAL TOOLING Survey & Alignment. O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 2 Title_date OPTICAL INSTRUMENTATION AND TERMINOLOGY.
Baseplates and Hg System Handling V.B. Graves P.T. Spampinato MERIT Hg System Safety Review CERN June 19-20, 2006.
O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY The Spallation Neutron Source Project: Update T. E. Mason Oak Ridge National Laboratory.
O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 1 Transitioning to Version 8 The Setup Library Oak Ridge National Laboratory Weatherization.
T2K Remote Handling T. Sekiguchi (KEK) on behalf of Tada (KEK) 2012/11/10.
Introduction to the Accelerator layout February 2016 Nick Gazis Mechanical Integration Lead Engineer.
Experimental Hall in Mountain Regions
CLIC Handling Engineering Update
IT-4189 Supply and installation of a cryogenic distribution system
TAXS and TAXN ABSORBERS - OVERVIEW
Hg System Decommissioning Activities
Mercury Catcher Status
Cryomodule Assembly Plan
MRV system budget and scheduling Short overview installation
Presentation transcript:

High Power Hg Target Conceptual Design Review Equipment Installation at CERN V.B. Graves P.T. Spampinato T.A. Gabriel Oak Ridge National Laboratory February 7-8, 2005

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 2 Conceptual Design Review 7-8 Feb 05 Outline  Facility layout & constraints  Modularity  Assembly sequence  Post-experiment operations

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 3 Conceptual Design Review 7-8 Feb 05 CERN Tunnel Plan View A. Fabich, CERN Access from ground level Experiment Setup

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 4 Conceptual Design Review 7-8 Feb 05 TT2A Photos Photos from A. Fabich, CERN Tunnel Width 400cm (158") Width 1.3m (51")

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 5 Conceptual Design Review 7-8 Feb 05 Facility Constraints  No overhead lifting capability within tunnel  Mobile crane used to lower equipment from ground level to tunnel floor  All components must have lifting points  Components moved manually  Modularity required  Component footprint size limitation is 1.3m x 3m

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 6 Conceptual Design Review 7-8 Feb 05 System Modules  Solenoid  Target module (inside solenoid)  Hg delivery system  Hydraulic pump & controls

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 7 Conceptual Design Review 7-8 Feb 05 Assembly Sequence  Align solenoid to beam, set elevation and tilt  Fiducials assumed to be on solenoid  Manually insert target module into bore of solenoid  Beam windows on primary & secondary containment can be used as fiducials to insure proper insertion depth  Position Hg delivery system  Align Hg delivery system as required, set elevation and tilt  Alignment precision dictated by size of downbeam window on secondary containment  Connect flexible hoses  Leak check primary containment  Load Hg if not already in sump tank  Position hydraulic reservoir  Connect hydraulics & instruments

O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY 8 Conceptual Design Review 7-8 Feb 05 Post-Experiment Operations  Minimize operator time near equipment  Prefer to leave target module and delivery system intact for this operation  Lower Hg system and solenoid together  Retract Hg system, adding support for target module as it exits solenoid  Must have adequate clearance in front of beam stop  Move solenoid and Hg system out of beam line  May need to operate Hg system one last time to move majority of Hg into sump tank (depends on type of sump drain valve used)  System isolated for radiation decay