Herschel / HIFI 1.Status mirrors FM/FS 2.Status COA QM 3.Status COA FM 4.Financial situation COA FM 5.Status MSA FM/FS
Status mirrors FM/FS Request for a quote sent out to TNO/LFM Quotation available at ETH Purchase order sent out to TNO Circulation of purchase order in Holland Expected delivery of 1 st batch (42 mirrors) Expected delivery of 2 nd batch (22 mirrors) Expected delivery of 3 rd batch (22 mirrors) Further requests, quotations, purchase orders is an ongoing process between SRON, LFM, TPD/TNO and ETH
Status COA QM Release for riveting Delivery rivet samples to SRON Stork FDO Conclusions from rivet samples by SRON Updated riveting procedures HTS/RUAG Delivery of single parts for riveting Start riveting process at RUAG aerospace Riveting completed ~ Delivery review foreseen ~
Status COA FM Kick off COA FM phase C/D Full set of drawings available at HTS Starting date at HTS Wallisellen Review MAIP Manufacturing release Latest documents delivered to HTS Manufacturing assembly review Delivery review COA + Container
Financial situation COA FM 1 st estimation from experience in phase B495,0 KEuro New estimation during man. in phase B445,0 KEuro Quotation explicitly given by HTS430,5 KEuro Agreed Firm Fix price by ESA350,0 KEuro Available budget from PRODEX325,0 KEuro Missing amount of money to pay for 25,0 KEuro
Status MSA FM/FS Negotiation meeting at HTS Starting date Review MAIP Manufacturing AR Delivery review Permanent delivery of MSA parts to SRON foreseen according to priority list
Financial situation MSA FM Quotation given by HTS542,2 KEuro Agreed Firm Fix price by ESA542,2 KEuro Available budget from PRODEX666,0 KEuro Left over to cover FM COA (25 KEuro), ECR (~30 KEuro) + unforeseen expenses123,8 KEuro