1 Brick manipulation report BMS machines status Black CS extraction status CNGS brick candidate extraction and BMS planning for 2009 D.Duchesneau LAPP,

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

20/01/09 OPERA general meeting Nagoya CNGS report.
Multidisciplinary Senior Design Rochester Institute of Technology Dresser-Rand Painted Post P10459 MSD II Update Presentation 4/9/10 Team: Phil Eaton (ME)
1 STILL open points: lead, ECC Packaging, CS laminated film, skates Construction Strategy Working groups BAM design and construction BAM LNGS site preparation.
Manchester 09/sept/2008A.Falou & P.Cornebise {LAL-Orsay}1 CALICE Meeting/ Manchester Sept 2008 SLAB Integration & Thermal Measurements.
HFT PXL Mechanical WBS 1.2 March 2010 Howard Wieman LBNL 1.
REDUNDANT ARRAY OF INEXPENSIVE DISCS RAID. What is RAID ? RAID is an acronym for Redundant Array of Independent Drives (or Disks), also known as Redundant.
SE429 Maintenance Planning and Control.
T. Le Flour LAPP OPERA Collaboration Meeting Gran-Sasso 1 TRACKING THE BRICK HANDLING From extraction to development.
Reliability of Disk Systems. Reliability So far, we looked at ways to improve the performance of disk systems. Next, we will look at ways to improve the.
Performance/Reliability of Disk Systems So far, we looked at ways to improve the performance of disk systems. Next, we will look at ways to improve the.
Data Structures Hash Tables
Emulsion scanning: present status and plans for the coming run Giovanni De Lellis.
Support to the event location in CS Scanning Station Fabio Pupilli LNGS Scanning Team OPERA Collaboration Meeting 20/01/2009 MIZUNAMI.
1 BMS activities and brick maniupulation Short summary of 2008 activities and results Extraction and filling activities foreseen in 2009 Black CS extraction.
Jan 16th 2009Spinetti1 Power plant Intervention done by Lngs All short term interventions Repair and deeper maintenance of UPS (Dec 08) Removal of diff.
CS LNGS Current status and perspectives.
Physical design. Stage 6 - Physical Design Retrieve the target physical environment Create physical data design Create function component implementation.
Brick Handling Meeting Nagoya T. Le Flour LAPP 1 BRICK HANDLING BMS/BMM Point of view D. Duchesneau T. Le Flour S. Lieunard.
H. Fagard, A. Orsoni (IGN) 1 Journées DORIS - Toulouse, 2 et 3 mai 2000 CURRENT STATUS AND EVOLUTION PROSPECTS OF THE DORIS NETWORK History Current status.
Support to the event location in CS Scanning Station Fabio Pupilli LNGS Scanning Team OPERA Collaboration Meeting 02/04/2009 ANKARA.
CS LNGS Current status and perspectives Luigi Esposito (European CS Scanning Team)
CS general status on behalf of JAPAN CS Analysis task force team T.Fukuda, S.Miyamoto, Y.Sakatani, Y.Taira 2nd April, OPERA Collaboration
Computer ArchitectureFall 2008 © November 3 rd, 2008 Nael Abu-Ghazaleh CS-447– Computer.
CSd scanning report from LNGS Nagoya OPERA workshop January 22 nd, 2008.
1 Status of the ‘Oscillation Physics’ WG Recall of the organisation and activities of the group –Main subjects and general approach –Starting steps and.
Preliminary studies for Muon shield modification to accommodate LCLS II Alev Ibrahimov December, 2010 BSY.
1 Recitation 8 Disk & File System. 2 Disk Scheduling Disks are at least four orders of magnitude slower than main memory –The performance of disk I/O.
Considerations about the BMS links to other OPERA systems Brick Manipulation Manager Links to other computing systems Needs to define the general framework.
Gran Sasso, 19/03/2003 OPERA Project Board meetingH. Pessard / 1 Brick Manipulator System (BMS) project uEvolutions and final design n Brick sliding and.
Reliability Andy Jensen Sandy Cabadas.  Understanding Reliability and its issues can help one solve them in relatable areas of computing Thesis.
Setting up the Ricoh C305 Press F5 to start the Presentation
Electronic Detector status and run organization Logistics and organization Updates on the electronic detector since last year run Conclusions.
Pixel Support Tube Requirements and Interfaces M.Olcese PST CDR: CERN Oct. 17th 2001.
Tuesday September Cambridge1 GDCC “next replacement of the LDA” Franck GASTALDI.
Status of the Brick Manipulation database development Introduction: goal and principles System analysis –The brick life –Manipulation procedures Proposed.
Malte HildebrandtDC Status Report, Dear MEG Committee,PSI, April 14 th 2009 this is the first report concerning the drift chamber status as.
LNGS Scanning Station Nicola D’Ambrosio (LNGS group) Maiori, 4-6 June 2007.
Notes After TIG 17/7/08 HF+ Move out of garage: Aug 15* Platform+table+collars+racks+BP support (jack up for platform) = 3 days Controls for motors = 1.
1 RUN 2008 OPERA events: Status Report M. Ieva on behalf of Bari Emulsion Lab OPERA Collaboration Meeting, April 1st - 5th, 2009.
Software Engineering Quality What is Quality? Quality software is software that satisfies a user’s requirements, whether that is explicit or implicit.
Gran Sasso, 20/05/2003 OPERA Main meetingH. Pessard / 1 Supervision of the Manipulator System (BMS) uWhat is Supervision for the Brick Manipulator System.
RADIATION SOURCE Design Review Dmitry Gudkov BE-BI-ML.
E8 / PPA Solar PV Design Implementation O&M Marshall Islands March 31-April 11, Preventive Maintenance.
Symbol Tables and Search Trees CSE 2320 – Algorithms and Data Structures Vassilis Athitsos University of Texas at Arlington 1.
Technical Support Activities in PH-ADO-PO
Emulsion Development Activity C.Sirignano Opera CM - Mizunami - 20/01/2009.
CERN Meeting 23/09/03 L.A.P.P OPERA T. Le Flour 1 B M M Brick Manipulation Manager FunctionalitiesAndArchitecture D. Duchesneau T. Le Flour S. Lieunard.
ATLAS TRT CO 2 cooling system project status Beaufort 12: “Hurricane” (>119 km/h) Saffir-Simpson 5: “catastrophic damage” (>250 km/h) (CO 2 distribution.
Integrated Monitoring Dashboard SEAP/BTIS/DB&I/Mar Integrated Monitoring Dashboard An Innovative Monitoring Approach Proposal by BTIS/DB&I.
March 23 & 28, Csci 2111: Data and File Structures Week 10, Lectures 1 & 2 Hashing.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
RWA, 4/11/2005 Review Movement & Motorization November 4 th, 2005 Program Introduction & Charge – R. Assmann Mechanical design & SPS results – O. Aberle.
Target tests 1 st – 2 nd Nov. Chris Booth Sheffield 7 th December 2006.
CSC 370 – Database Systems Introduction Instructor: Alex Thomo.
Greenlight Presentation Oracle 11g Upgrade February 16, 2012.
G.Barber Mice Tracker Integration Harbin Jan Mice Tracker Integration Installation requirements & Procedure.
Gates automation. Summary  Choosing the appropriate model  Faac Product Range (Sliding Gates)
A2-A5: The drawing has been revised (minor changes), the bid has been approved by INFN management and the invitation letter to the companies will be sent.
Software and Computing Status of Software development and MC production OpRoot-Fedra MC interface New CVS server Computing resources at CERN: present and.
SPHENIX MECHANICAL D. Lynch September 11, AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.
Hands-On Microsoft Windows Server 2008 Chapter 7 Configuring and Managing Data Storage.
Status on closing operations End cap calorimeter side A Forthcoming operations ATLAS – April 17th, 2009 Prepared by Michel RAYMOND.
TOF status and LS1 plansTOF status and LS1 plans 27/06/2012.
ICT in Product Manufacture ICT based Production Scheduling and Logistics.
MM Status Mostly unchanged (Feb. 3 rd 2016). Parts Mildly modified bridges, allowing to actually move 130nm pickup tools along r*phi –Turned out to be.
Reliability of Disk Systems. Reliability So far, we looked at ways to improve the performance of disk systems. Next, we will look at ways to improve the.
Pelletron status update Main Injector Departmental Meeting November 11 th, 2009 L. Prost.
Right-of-Way Cost Estimating Planning Tool Training Guide
World-Views of Simulation
Presentation transcript:

1 Brick manipulation report BMS machines status Black CS extraction status CNGS brick candidate extraction and BMS planning for 2009 D.Duchesneau LAPP, Annecy OPERA General Meeting Ankara, April 1 st, 2009

2 Some numbers for ‘fun’: BMS Machines: 2007: bricks have been inserted in the target in 11 months => 1700 /week 2008:  bricks have been inserted in the target in 6 months => 2900 /week  bricks have been extracted and reinserted in the target in 6 months time => 800 /week 2009: bricks are extracted and reinserted in the target in 3 months => 1170 /week Since 2008: BMS machines have moved 894 tons of bricks in the target with great care: 28 motors and 100 sensors are active all the time and mechanics and actuators are working very hardly with challenging reliability. BMS VV have travelled about the distance Roma- L’Aquila: 50 km in 2008 and already 70 km in 2009 (diameter of wheels: 40mm)

3 BMS Machines: hardware status  The BMS maintenance + repairs are programmed from Monday April 27 th to May 8 th  a LAPP team will work to address the following items: Preventive maintenance after black CS replacement total revision of the BMS bridge on the Rock Side Replacement of some profibus cables on the Rock side (Y and Z chains) Try to correct the geometry of the Rock side platform due to the deformation Replace and readjust the guiding of the portico along the large Z movement Z Navig driving belt tension system analysis on corridor side Revision of the drums and the rotating parts of the cage Recalibration of the whole BMS setups The work should be carefully organised such that the other activities are not interfering We need at least 3 days (from May 6 th to May 8 th to run without interference in order to reoptimise the BMS for the new Run

4 Black CS treatment status

5 Black CS extraction reminder: 2 groups have to be extracted:  The first bricks produced by the BAM for which there was no hole in the CS envelop: they are considered as the first bricks loaded in the detector (Brick Id < 14400)= group A  There are additional 4000 bricks for which there was a hole but stored during long time under vacuum. Those brick positions are not so sharply defined as in the first category. But looking at the CS fog data we isolated the group B: 34000< Id < (about 3500 bricks) A B FOGFOG CS Identifier Total=16500 bricks but 1000 are spread randomly in the detector in rows with < 13 black CS

6 Black CS row localisation in the detector (Side views of the target) SM1 RS SM1 CS Group A: Id < rows Group B: < Id < rows as of March 9th 2009: remains 289 rows (blue squares) = 7500 bricks to extract as of March 30th 2009: remains 157 rows (blue squares) = 4082 bricks to extract

7 To be careful: some rows contain good bricks or bricks which should not be treated: (0.3% candidate bricks and 0.6% not high fog bricks) : both types will be reinserted in the detector  However the priority are given according to the rows where there is a maximum of CS to replace. We use a BMM tool interface to the DB to do the bookkeeping of the extracted bricks Black CS extraction strategy: A dedicated activity has been installed beginning of this year and made operational in Hall C since Feb 2 nd 2009

8 Global setting-up (in hall C) Storage pallets point 8 Work stations point Security corridor always free Loading unloading drums point Slide from David Biare

9 Work stations point Bricks NOT done Bricks done Linear stream There are 2 work stations Slide from David Biare

10 Work station control point BMM recording CS & Skates replacement Dimensions control Activities on the working tables in Hall C:

11 Black CS replacement operation in Hall C (from David) Constant and very demanding human effort: we are following a good slope but keep motivation!

12 ‘theoretical’ upper limit achievable for the BMS if there is no major hardware failure during 2 shifts/day: BMS Insertion max. rate: 900 bricks/day  4 drums/day BMS Extraction max. rate: 2/3 of insert rate = 600 bricks/day ‘Average’ rate achieved for the BMS during 2 shifts/day including all sort of hardware and Gran Sasso related failures since Feb 2 nd : BMS Insertion average rate: 3 drums/day (max=3.72) (eff = 75%) BMS Extraction average rate: = 586 bricks/day (eff = 98%) However several unrelated show stoppers occurred: Tunnel closure (-15 hours), Snow storms (-5 hours), OPERA DB Oracle access problem (-8 hours), etc… BMS performances

13 Summary for the last 2 months (Feb 2 nd -March 30 th ): Black CS extraction Expected: 10800achieved: Brick reinsertion: Expected: 7650achieved: 6084 CNGS extraction:Expected: 260achieved: 231 BMS performances and schedule Goals for the period (Feb 2 nd -April 24 th ): Black CS extraction Expected: 13700originally: Brick reinsertion: Expected: 14900originally: CNGS extraction:Expected: 460originally: 260 Activities foreseen from May 11 th – May 23 rd Brick reinsertion: Expected: 2200 (includes last BAM production) CNGS extraction:Expected: 100 (4days) BMS maintenance and repair April 27 th – May 8 th Start CNGS 2009 run extraction from May 25 th

14 CNGS candidate extraction status

15 CNGS extraction efficiency is then: ± 0.10 % 4 rows with candidate bricks inside are blocked. and are not yet recovered and no hope to easily recover them Those achievements were not done without pain:  BMS Extraction suffers from bad skates + glue + lost/destroyed CS cover  Unexpected and damaging LNGS power cuts on BMS systems and hardware + loss of BMM DB…  Hardware failures: motors, servo-control, vehicle, crashes due to external factors 1906 bricks extracted up to March 27 th 2009 (for 1690 events!). CNGS Brick candidate extractions: However during the black CS extraction in the worst rows with the bad skates only we have 16 rows with blocked bricks! It is why the maximum exchange of black CS would have been the best option for the 5 coming years

16 CNGS Brick candidate extractions:  At the Exec meeting of Feb. 13 th Dario summarised the need for additional extractions Bricks still to be extracted: (first) (2nd estimated with (second, first extracted) % ineff on 1st) (second, first not extracted) 90 Total 680  It was asked to modify the planning during the black CS extraction period to include more CNGS extraction which we did and went from 5 to 10.5 days of extraction. It was corresponding to double the rate and should end up with 460 extracted bricks up to April 24 th 2009 among the 680 possible requests However the drawback was the reduction of the number of black CS to be treated of about 2000 => instead of treatable At the beginning of 2009 run: a maximum of 100 bricks may still to be extracted if we base on the above numbers

We see clearly the CNGS extraction activity we included during the black CS treatment

18 Shielded area Storage capacity: 1000 bricks up to March. 28th # places on shelves We extract more but this gap increases!

19 Brick Handling and new BMM development: Brick to Brick connection management actions have been implemented this week in the BMM software. The knowledge of the B2B characteristic is known at the time of the brick extraction request retrieved from the central database. For those bricks the flow will be: CS-ray is done CS is developped when the brick arrives in the shielded area, its state will go directly to waiting for X-ray if put on a shelf

20 The END