PALM-3000 HOWFS - 7/24/09 C. Baranec
PALM-3000 Current Status Summary 2 Telescope simulator assembled HOWFS assembled and tested Alignment plan (CIN 636) is halfway finished Alignment feedback GUI developed and tested
PALM-3000 Telescope Simulator 3 On-axis green laser Red laser fiber source On x-y-z translation stage F/# ~15.7 (needs to be confirmed)
PALM-3000 HOWFS Mechanical 4 Pieces needed for WFS fabricated and assembled. Alignment feedback GUI developed and tested.
PALM-3000 Alignment feedback GUI 5
PALM-3000 s16 6
PALM-3000 s32 7
PALM-3000 s64 8
PALM-3000 Demo… Switch to remote desktop 9
PALM-3000 Analysis/Discussion Pupil ellipticity at 2.0% (1.70% desired for AOI of 10.5) –There are degrees of freedom to change the ellipticity Pupil size at mm (9.600 target) We need to establish exact pupil sizes in the different modes before specifying collimator Different focus measurement in different modes –Many possible contributors, will require investigation CCD50 focus positions not yet established –Will require use of Pixelink camera 10
PALM-3000 Flexure analysis Flexure – ATS150 roll compliance is excellent. Still awaiting pitch compliance. Expect 0.1”/hour. Khanh’s description of flexure analysis however is confusing. What priority should we place on having him document this properly? 11
PALM-3000 Outstanding tasks - summary CCD50 readout modes – awaiting SciMeasure. Test the camera modes – RN/DC (JR, ? days) Finish alignment plan - (CB, 1 day) Further alignment investigation – (CB, 1 day) Amendments to alignment procedure – (CB, 1 day) Internal flexure testing – (CB, 1 day) Spec new optics – (CB, ½ day) Alignment with the testbed – (CB, 2 days) Plan for testing and incorporating new optics – (CB, 1 day) Mechanical… 12
PALM-3000 Mechanical Engineering Update 13 Task #PriorityDescriptionStatus 1CCD50 coverIn shop 2HOWFS coverConceptual, in solidworks 3Field stop with ACam mirrorFab. drawings 4ACam optics mountsConceptual, in solidworks 5ACam camera mountConceptual, in solidworks Khahn expects to be finished working on the HOWFS/Acam by end of next week.
PALM-3000 Schedule Mechanical finished – next few weeks SciMeasure modes - ? Integration with testbed (no DM) – 3-4 weeks Order testbed collimator/cylinder – after F/# established Integration with DM in testbed – 6-10 weeks Integration on PALM-AO bench – next year 14
PALM-3000 Management Summary Total labor: CB – ~8 days JR – CCD testing modes, integration ME – 1 week from Khanh Bui AB – integration Equipment costs: SciMeasure camera modes - ? New optics (col, cyl) ~ $