CS-413 1 Integration Management (Part 6) Bilgisayar Mühendisliği Bölümü – Bilkent Üniversitesi – Fall 2009 Dr.Çağatay ÜNDEĞER Instructor Bilkent University,

Slides:



Advertisements
Similar presentations
Project Management Concepts
Advertisements

Software Quality Assurance Plan
1IT Project Management, Third Edition Chapter 4 Chapter 4: Project Integration Management.
Copyright 2009  Develop the project charter: working with stakeholders to create the document that formally authorizes a project—the charter  Develop.
Project Change Management
Dr. L. K. Gaafar The American University in Cairo
Project Integration Management Sections of this presentation were adapted from A Guide to the Project Management Body of Knowledge 4 th Edition, Project.
Modern Systems Analysis and Design Third Edition
Project Management Session 7
Course Technology Chapter 3: Project Integration Management.
Chapter 3: The Project Management Process Groups
10.5 Report Performance The process of collecting and distributing performance information, including status reports, progress measurements and forecasts.
Project Management based on the Project Management book of knowledge Risk Identify, analyse and respond to risks Resources Make most effective use of human.
Software Engineering Project Management (CS - 413)
Chapter 4: Project Integration Management
4 4 By: A. Shukr, M. Alnouri. Many new project managers have trouble looking at the “big picture” and want to focus on too many details. Project managers.
© 2008 Prentice Hall11-1 Introduction to Project Management Chapter 11 Managing Project Execution Information Systems Project Management: A Process and.
Project Execution.
PRESENTED BY TRUST THOMAS EROMOSELE STUDENT NO:
Copyright© 2004 Roger Beatty. All rights reserved.. Project Integration Management October 26, 2004 Roger D. Beatty, PhD, PMP PMBOK Guide is a registered.
Project Management Fundamentals Project Organization and Integration
Degree and Graduation Seminar Project Management Processes
Module 8: Risk Management, Monitoring and Project Control We would like to acknowledge the support of the Project Management Institute and the International.
Copyright Course Technology 1999
PMP® Exam Preparation Course
Software Project Management
1 Chapter 4: Project Integration Management. 2 Learning Objectives Describe an overall framework for project integration management as it relates to the.
PPMT CE-408T Engr. Faisal ur Rehman CED N-W.F.P UET P.
Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management.
1.  Describe an overall framework for project integration management ◦ RelatIion to the other project management knowledge areas and the project life.
Lecture 11 Managing Project Execution. Project Execution The phase of a project in which work towards direct achievement of the project’s objectives and.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
1IT Project Management, Third Edition Chapter 4 Chapter 4: Project Integration Management.
Apply Project Scope Management Techniques Project Scope Processes – Part 2 Certificate IV in Project Management Qualification Code BSB41507 Unit.
Project Management Components (Part 5)
Dr. Jana Jagodick Polytechnic of Namibia, 2012 Project Management Chapter 5 Project Integration Management.
Develop Project Charter
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 1 Diploma of Project Management.
M ONITOR & C ONTROL Focus is on Integrated Change Control 1.
Slide 1ICT 327 Management of IT ProjectsSemester 2, 2004 Topic 11 Executing & Controlling Projects.
Project Management Project Integration Management Minder Chen, Ph.D. CSU Channel Islands
Degree and Graduation Seminar Integration Management
The Project Plan Plan Your Work, then Work Your Plan
Project Management Processes for a Project
SCOPE DEFINITION,VERIFICATION AND CONTROL Ashima Wadhwa.
Report Performance Monitor & Control Risk Administer Procurement MONITORING & CONTROLLING PROCESS.
~ pertemuan 4 ~ Oleh: Ir. Abdul Hayat, MTI 20-Mar-2009 [Abdul Hayat, [4]Project Integration Management, Semester Genap 2008/2009] 1 PROJECT INTEGRATION.
Apply Project Scope Management Techniques Project Scope Processes – Part 2 Week 4 Certificate IV in Project Management Qualification Code BSB41507.
BSBPMG501A Manage Project Integrative Processes Manage Project Integrative Processes Project Integration Processes – Part 2 Diploma of Project Management.
V. 2. © Copyright and all rights reserved 4. Project Integration Management PMP Prep Course Based on the PMBOK ® Guide 3 rd Edition.
Project Integration Management
The Project Management Process Groups
B U D I L U H U R U N I V E R S I T Y POST GRADUATE PROGRAM MAGISTER ILMU KOMPUTER (M.Kom) IS PROJECT MANAGEMENT.
Slide 1ICT 327 Management of IT ProjectsSemester 1, 2005 Topic 3 Executing & Controlling & Closing Projects.
1IT Project Management, Third Edition Chapter 4 Chapter 4: Project Integration Management.
V. 2. © Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 4. Project Integration Management PMP Prep Course Based on the PMBOK ® Guide 3 rd.
Project Management PTM721S
Process and customizations
Project Management PTM721S
Project Integration Management
Project Integration Management
TechStambha PMP Certification Training
CIS12-3 IT Project Management
Project Management Process Groups
Mumtaz Ali Rajput +92 – SOFTWARE PROJECTMANAGMENT– WEEK 4 Mumtaz Ali Rajput +92 – 301-
Project Integration Management
Project Integration Management
Chapter 3: Project Integration Management
Managing Project Work, Scope, Schedules, and Cost
Presentation transcript:

CS Integration Management (Part 6) Bilgisayar Mühendisliği Bölümü – Bilkent Üniversitesi – Fall 2009 Dr.Çağatay ÜNDEĞER Instructor Bilkent University, Computer Engineering Middle East Technical University, Game Technologies & General Manager SimBT Inc.

CS Integration Management Project Management Components (knowledge areas) –Project Integration Management –Project Scope Management –Project Time Management –Project Cost Management –Project Human Resource Management –Project Communication Management –Project Quality Management –Project Risk Management –Project Procurement Management

CS Integration Management Introduction Project Plan Development Project Plan Execution Integrated Change Control

CS Integration Management (Introduction) Includes the process required to ensure that –Elements of project are properly coordinated. Involves making tradeoffs among competing objectives and alternatives –To meet stakeholder needs and expectations.

CS Integration Management (Introduction) All project management components are integrative to some extend, But integration management is primarily integrative. Although process will be presented as discrete elements with well-defined interfaces, –In practice, they may usually overlap and interact.

CS Integration Management (Major Phases) Project Plan Development: –Integrating and coordinating all project plans to create a consistent, coherent document. Project Plan Execution: –Carrying out project plan by performing activities included in the plan. Integrated Change Control: –Coordinating changes across entire project.

CS Integration Management (Major Phases)

CS Integration Management Introduction Project Plan Development Project Plan Execution Integrated Change Control

CS Project Plan Development (Introduction) Uses outputs of other planning processes. It is an iterative process; –Initial draft may include a coarse plan; –Subsequent versions includes details.

CS Project Plan Development (Introduction) Scope of the project plan is usually determined; –Using a work breakdown structure, and –Iteratively decomposing tasks. All of the tasks must be; –Planned, –Estimated, –Scheduled, and –Authorized.

CS Project Plan Development (Objective) Project plan is used to: –Guide project execution, –Document project planning assumptions, –Document project planning decisions, –Faciliate communication among stakeholders, –Define key management reviews, –Provide a baseline for progress measurement and project control.

CS Inputs, Tools & Techniques, and Outputs

CS Project Plan Development (Inputs) Other planning outputs Historical information Organizational policies Constraints Assumptions

CS Project Plan Development (Inputs) Other planning outputs: –Work breakdown structures, –Gantt Charts, network diagrams, etc. –Outputs of planning processes in other knowledge areas: e.g. time, cost, quality management Historical information: –Estimation (e.g. cost, time) database –Performance database

CS Project Plan Development (Inputs) Organizational Policies: –All the organizations involved in the project may have their own formal and informal policies. –Effects of policies must be considered.

CS Project Plan Development (Inputs) Organizational Policies: –Policies that are typically considered: Quality management: –Standard documentation procedures, –Process improvement goals, Personnel administration: –Hiring and firing guidelines, –Employee performance reviews, Financial controls: –Required expenditure and disbursement, –Standard contract provisions.

CS Project Plan Development (Inputs) Constraints: –Restrictions that will limit project team’s options: Predefined schedule / deadlines, Predefined budget, Predefined hardware or OS, Predefined programming language, Contractual provisions.

CS Project Plan Development (Inputs) Assumptions: –Factors that are considered to be true for the planned system. –For instance: A plan can be made assuming that; –A key person will be available after a specific date. A plan can be made assuming that; –Atmospheric conditions are ineffective to the system. –Generally involve a degree of risk.

CS Project Plan Development (Tools & Techniques) Project planning methodology Stakeholder skills and knowledge Project management information system (PMIS)

CS Project Plan Development (Tools & Techniques) Project planning methodology –Any structured approach used to guide project team during plan development. As simple as forms and templates As complex as a series of required simulations.

CS Project Plan Development (Tools & Techniques) Stakeholder skills and knowledge –Every stakeholder has some skills and knowledge that may be useful for plan development. –Create an environment to let stakeholders contribute to the planning.

CS Project Plan Development (Tools & Techniques) Project management information system (PMIS) –Consist of tools and techniques used to; Gather, integrate and disseminate outputs of the project management process.

CS Project Plan Development (Outputs) Project plan Supporting details

CS Project Plan Development (Outputs) Project plan: –A formal, approved document used to manage the project execution. Activity dates are scheduled; Meeting milestones are identified. –Distributed to all the stakeholders as defined in communications management plan.

CS Project Plan Development (Outputs) Project plan: –Expected to evolve over time as more information comes in. –Performance measurement baseline will change only in response to an approved scope change.

CS Project Plan Development (Outputs) Project plan includes: –Project charter –Project management approach (a summary of plans from other knowledge areas) –Scope statement (objectives, deliverables) –Work breakdown structure (a baseline scope document) –Cost estimates, schedules, responsibility assignments –Performance measurement baselines for: Scope, schedule and cost –Major milestones and their target dates –Key or required staff and their expected costs –Key risks and their planned responses if happened –Subsidiary management plans: Scope, schedule, cost, quality, staffing, communications, risk, procurement management plans –Open issues and pending decisions –Other project planning outputs.

CS Project Plan Development (Outputs) Supporting details: –Outputs from other planning processes –Additional information generated during the process –Technical documentation such as: Requirements, Specifications, Conceptual designs –Documentation of relevant standards.

CS Integration Management Introduction Project Plan Development Project Plan Execution Integrated Change Control

CS Project Plan Execution Primary process for; –Applying the plan to create the product. Majority of the budget will be expended here. Project manager & project management team must coordinate and direct technical and organizational processes. Performance against the baseline plan must be continuously monitored, –Corrective actions may be required.

CS Inputs, Tools & Techniques, and Outputs

CS Project Plan Execution (Inputs) Project plan Supporting details Organizational policies Preventive actions

CS Project Plan Execution (Inputs) Project plan: –Project plan and subsidiary management plans. Supporting details: –Outputs from other planning processes –Additional information generated during planning –Technical documentations –Documentation of relevant standards

CS Project Plan Execution (Inputs) Organizational policies: –Any policy effective on plan execution: Quality management Personnel administration Financial controls Preventive actions: –Any action done that reduces the risks. Corrective actions: –Any action done that brings project performance in line with the baseline plan.

CS Project Plan Execution (Tools & Techniques) General management skills Product skills and knowledge Work authorization system Status review meetings Project management information system (PMIS) Organizational procedures

CS Project Plan Execution (Tools & Techniques) General management skills: –Leadership, communicating, negotiation skills are essential. Product skills and knowledge: –Project team must have skills and knowledge about the project domain. –If required, new staff can be acquired.

CS Project Plan Execution (Tools & Techniques) Work authorization system: –A formal procedure for authorizing project work –To ensure that work done at the right time and in the proper sequence. –Usually written authorization to begin work is used.

CS Project Plan Execution (Tools & Techniques) Status review meetings: –Regular scheduled meetings to exchange information about project situation. –May be held on different levels and frequencies. Project management team (weekly) Customer (monthly)

CS Project Plan Execution (Tools & Techniques) Project management information system (PMIS) –Consist of tools and techniques used to; Gather, integrate and disseminate outputs of the project management process. Organizational procedures: –All organizations involved in project may have formal and informal procedures that are useful.

CS Project Plan Execution (Outputs) Work results Change requests

CS Project Plan Execution (Outputs) Work results: –Outcomes of activities performed to accomplish the project: Results of activities (completed, failed, cancelled etc.) Documents produced (requirements, design, test report, etc.)

CS Project Plan Execution (Outputs) Change requests: –Sometimes, change requests about scope, cost and schedule occur during the plan execution. –The approved ones are reflected to the project plan.

CS Integration Management Introduction Project Plan Development Project Plan Execution Integrated Change Control

CS Integrated Change Control Concerned with: –Influencing factors, which create changes, To ensure that changes are agreed upon; –Determining that a change has occured; –Managing actual changes when and as they occur.

CS Integrated Change Control Project scope and performance baseline must be maintained by continuously managing changes: –Rejecting new changes, or –Approving changes and integrating them into a revised baseline.

CS Integrated Change Control Requires: –Maintaining integrity of performance measurement baselines; –Ensuring that product scope changes are reflected to planned scope. –Coordinating changes across knowledge areas; e.g. a schedule change will effect costs, risks, staffing, and quality.

CS Inputs, Tools & Techniques, and Outputs

CS Integrated Change Control (Inputs) Project plan Performance results Change requests

CS Integrated Change Control (Inputs) Project plan: –Provides baseline against which changes will be controlled. Performance results: –Provide information on project performance.

CS Integrated Change Control (Inputs) Change requests: –Occur in many forms: Oral or written Direct or indirect Externally or internally initiated Legally mandated or optional.

CS Integrated Change Control (Tools & Techniques) Change control system Configuration management Performance measurement Additional planning Project management information system (PMIS)

CS Integrated Change Control (Tools & Techniques) Change control system: –A collection of formal, documented procedures defining how performance will be monitored and evaluated. –Defines steps by which official project documents may be changed.

CS Integrated Change Control (Tools & Techniques) Change control system: –Includes: Paperwork, Tracking systems, Processes, Approval levels for authorization. –Must also include procedures to handle changes that are approved without prior review (e.g. for emergencies). –Baseline should be kept up to date.

CS Integrated Change Control (Tools & Techniques) Configuration management: –Usually a subset of change control system. –A formal documented or automated procedure to apply technical and administrative directions to: Identify and document functional and physical characteristics of an item or system. Control any changes to these characteristics. Record and report change and its implementation status. Track versions of items and system. Audit items and system to verify conformance to requirements.

CS Integrated Change Control (Tools & Techniques) Performance measurement: –Enable to assess whether variances from baseline require corrective actions. Additional planning: –Projects seldom run as planned. –Therefore changes may require revised; Cost estimates, modified activity sequences, schedules, resource requirements, contingency plans for risks,...

CS Integrated Change Control (Tools & Techniques) Project management information system (PMIS): –Consist of tools and techniques used to; Gather, integrate and disseminate outputs of the project management process.

CS Integrated Change Control (Outputs) Project plan updates Corrective actions Lessons learned

CS Integrated Change Control (Outputs) Project plan updates: –Any modification to the contents of project plan or the supporting details. –Related stakeholders should be notified. Corrective actions: –Any action done that brings project performance in line with the baseline plan.

CS Integrated Change Control (Outputs) Lessons learned: –Causes of variances from baseline, –Reasoning behind corrective actions, and –Other types of lessons learned should be documented. –Become a part of historical information for future recomendations.