Using Cost Accounting Documents in Construction Claims and Litigation By William Schwartzkopf Sage Consulting Group.

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension.
Fixed price contract: A contract that provides a price for each procurement item obtained under the contract.
CONTRACT A binding agreement between two or more parties for performing, or refraining from performing, some specified act(s) in exchange for lawful consideration.
Time Is Money - Delay Claims in Construction June 18, 2012
John Boon ZUT November Procurement Systems The organisation of the interaction between the purchaser of a new building and the suppliers of goods.
Contract Law 2014 NCHCA Education Series- January 23, 2014 Presented by Geoffrey Cantello, City of Ottawa and Ron Price, Rasmussen Starr Ruddy LLP.
Chap 16 Proving costs and damages How do you calculate damages?? Inability to prove with certainty may prevent full recovery Need to determine true cost.
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
OCR Payment Process Training 01/17/2012. Article 9 – Compensation and Payment General Conditions – Article 9 – 9.1 Preconstruction Stage Compensation.
Time for a new standard - AS General Conditions of Contract
PREPARED BY: Mohammed Tanbora SUPERVISED BY: Dr. Kamalain K. Shaat CHAPTER8: Application Of Controls.
Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
Slide 10.1 Invoice 4E1 Project Management Specification & Costing - 1.
Introduction -Discussed preparation of the overall plan for the project - as well as its implementation. -The control system quantitatively measures actual.
Unique Pricing And Estimating Challenges Faced In Change Orders, Requests For Equitable Adjustments, And Claims Breakout Session # 408 Greg Bingham Date:
APPLICATION OF CONTROLS CHAPTER 8 Presenting by : Mustafa Al tayeb Date 21/11/2005.
Delay Claims from the Owner and Contractor’s Perspectives
Construction Engineering 221 Cost Estimating and Bidding.
EM15 – Contractors COST MANAGEMENT
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Change Orders. Build the project that was bid and awarded.
Termination and Damage Termination of contract is rare- requires a material breach (not partial breach) Partial breach is insignificant failure to perform.
Discussion Topics Construction Contract Administration Lessons Learned Other Construction Issues Questions? / Comments (Anytime)
March 2005 UMORS 1 UMORS Vander Kooi and Associates, Inc Ultimate Multiple Overhead Recovery System.
Construction Scheduling and Estimating.  Someone gets an IDEA  The IDEA inspires a PLAN to be created  The PLAN is used to build the SCHEDULE  The.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 3 Requirements of a realistic CPM schedule.
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
Intermediate Accounting
Chapter 8 Pricing Generally. Objectives Upon completion of this chapter, you will be able to: –Describe the general process of pricing a construction.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 5 Advanced Techniques of CPM Deception and Mystery.
Kenneth D. Fenton P.S. Clark County Engineer’s Office.
Cost and Time Control. Project completed on time and on budget –Want to get done early –Lower costs –More profit.
CVE 4070 Construction Engineering Test-2 & Review Prof. Ralph V. Locurcio, PE.
Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed.
King Fahd University of Petroleum & Minerals
LECTURE 4 FORMULATION & PRESENTATION OF MONETARY CLAIMS  Recovery of Loss / Expenses / Damages  Notice of intention to claim  Particular and further.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Construction Contracts
Marketing & Tendering. Budget Forecasting Profit is the key to Business Success – Profit is amount of money after all expenses Materials Labour Insurances.
CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-Anazi CEM 520 February 27,1999.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
PREPAREDBY: PREPARED BY: Ahmed Al Tayeb Saed Al Qeshawe Tareq Amen Abdalla Syiam SUPERVISED BY: Dr. Kamalain K. Shaat CHAPTER8: Application Of Controls.
Financial Management Glencoe Entrepreneurship: Building a Business Analyzing Your Finances Managing Your Finances 21.1 Section 21.2 Section 21.
LECTURE 5 FORMULATION & PRESENTATION OF OTHER CLAIMS
 Section Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days.
Measurement and Payment
University of Calgary Continuing Education Construction Contract Law and Documents Week 12 Changes Delays Claims Contract Documentation.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Lost Productivity Claims and the importance of project documentation and experts ABA FORUM ON CONSTRUCTION INDUSTRY DIVISION 9 February 17,
Final Accounts. Accounts Submissions Last Bill for Contracted Works ( excluding Retention) Presented at Practical Completion Practical Definition dependant.
Fundamentals of Project Control Chapter 11 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project.
CVE 4070 Construction Engineering HW #6 review Test-2 & Review Prof. Ralph V. Locurcio, PE.
Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.
1 Breakout Session # E12 DISRUPTION – THE HIDDEN COST OF CHANGE Date: July 31, 2012 Time: 2:30 P.M. to 3:45 P.M.
Helen S. Henningsen Department of Veterans Affairs Office of General Counsel.
HORTICULTURE II - LANDSCAPE Unit B Landscape Design.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Termination and Damage
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Estimating Project Costs
Costs and Economics of Construction
(Additional materials)
Department of Navy Money Part 2 (FAR Part 22) 9/20/2018.
Certificates JCT 11 SBC allows for 10 different kinds of certificates.
ARCH 435 PROJECT MANAGEMENT
Department of Navy Money Part 2 (FAR Part 22) 4/13/2019.
Construction Contracts
Directed Change Constructive Change
TOTAL COST CONTROL ON CONSTRUCTION PROJECTS
Presentation transcript:

Using Cost Accounting Documents in Construction Claims and Litigation By William Schwartzkopf Sage Consulting Group

Goal of Most Construction Disputes: Receive Additional Compensation OR Avoid Paying Additional Amounts 2

Reason For Dispute One or More Parties Incurred Cost Overrun 3

How Does A Party Know It Has Been Damaged? Cost Report Shows Overrun Expended More Funds 4

What is the Purpose of A Damage Award? “To place the nonbreaching party in the same position it would have been absent the breach by the other party.” 5

Preliminary Damage Analysis Cost Accounting Records Original Estimate Where Are the Overruns? When Did the Overruns Occur? Linking Causation to Overruns 6

Causation What Caused the Overrun? Who is Responsible for the Cause? How is the Cause Linked to the Overrun? Merely Having Overruns (i.e. Actual Damages) Is Not Enough to Allow Recovery 7

Damage Calculation Goal: To Arrive At the Most Accurate Determination of Actual Damages Suffered as a Direct Result of the Other Party’s Breach 8

Methods of Damage Calculation Actual Cost Method Estimated Cost Method Total Cost Method Modified Total Cost Method Quantum Meruit 9

Actual Cost Method Formula: Actual Extra Equipment Costs Caused by Breach + Actual Extra Material Costs Caused by Breach + Actual Extra Labor Costs Caused by Breach + Overhead and Profit Total Actual Damages Preferred Method Analysis of Overruns and Underruns Determine Linkages Application to Some, but Not All, Elements of a Claim Law or Contract May Require Use of Actual Cost Method 10

Estimated Cost Method Formula: Estimated Extra Equipment Cost Caused by Breach + Estimated Extra Material Cost Caused by Breach + Estimated Extra Labor Cost Caused by Breach + Overhead and Profit Total Costs Recoverable Variety of Supporting Data Examination of Underlying Assumption Analysis of Other Projects Performed by the Contractor 11

Total Cost Method Formula: Total Actual Costs + Overhead and Profit - Contract Amount Total Costs Recoverable Generally Disfavored Method – Courts vs. Board of Contract Appeals Four-Part Test: – Impossible or highly impractical to determine the losses with a reasonable degree of accuracy – Contractor’s bid or estimate was realistic – Contractor’s actual costs were reasonable – Contractor was not responsible for the cost overrun 12

Modified Total Cost Method Formula: Total Actual Costs - Bid Errors - Costs caused by Contractor - Costs caused by other Non-Owner parties +Overhead and Profit - Contract Amount Total Costs Recoverable Adjust Cost for Contractor Problems – Estimate Errors – Construction Errors – Weather and other Natural Causes – Subcontractor and Supplier Problems Must Meet Same Four-Part Test as Total Cost 13

Quantum Meruit A Theory of Recovery, not a Method of Calculation Allows Recovery of Actual Value of Goods or Services; Not their Contract Price. Actual value Not Necessarily cost Recovery of Costs Incurred in Completing Work that Is outside the Scope of the Original Contract Changes Can Be a basis for Quantum Meruit Recovery Recovery of Damages Resulting from Owner’s Breach of a Contract Terminated Before Job Completion Contractor Cannot Be in Breach and Must Have Substantially Performed 14

Causal Link: Connecting Responsibility to Damages Damages presented with best approximation using as much actual cost data as possible with each separate item of cost examined by the judge/arbitrator to arrive at a fair result. The total cost method and its variations are disfavored and generally permitted only when contractor clearly proves injury and no other method is more reliable in estimating the losses. Sufficient evidence must be presented to make a fair and reasonable approximation of damages. 15

Types of Claims Added Work Changed Work Disrupted Work Extended Duration 16

Added Work Additional Units Force Account Estimated Cost 17

Changed Work Causes – Directed Changes – Defective Specifications – Differing Site Conditions Results in: – Added Work – Deleted Work – Change in Quantity Types of Damages – Direct Costs – Indirect Costs – e.g., Overhead – Lost Productivity – Additional Profit 18

Disrupted Work Causes – Excessive Changes – Late Changes – Sequencing – Weather – Access – Stop Work Orders Results in – Lost Productivity – More Manhours Types of Damages – Added Labor – Added Equipment Costs – Added Small Tools and Supplies – Profit and Overhead 19

Extended Duration Types of Extended Duration Project Is Longer Working Days vs Calendar Days Fixed Completion Date Causes – Access – Added Work – Changes – Weather Damages – Time-Related Clauses – Escalations 20

Types of Damage Labor Cost Overrun Equipment Cost Overrun Material Cost Overrun Subcontractor Cost Overrun General Conditions Costs Home Office Overhead 21

Types of Labor Cost Damage Direct Labor Overrun – More hours to perform more work – Discretely accounted for through time tickets Wage Escalation (higher rate per hour) Premium Time Costs Loss of Productivity – More hours to perform same amount of work 22

Factors Affecting Labor Productivity Overtime Disruptions Weather Lack of Capable Laborers Change in Sequence Trade Stacking Restricted Site Access Shift Work Shop Drawing Review Learning and Experience Curves Effect of Changes on Labor Productivity 23

Calculation of Loss of Productivity Measured Mile Calculations Comparison with Similar Projects Industry Standards Experts and Consultants Total Cost Method Modified Total Cost Calculations Productivity Analysis 24

Cost Accounting Data is KEY Good Cost Accounting Helps Determine the Amount of Overrun and Pinpoint the Causes 25

Cost Report Entry Cost CodeDescription Est. Cost Cost to Date 3300 PCC Paving $70,000$50,000 26

Cost Report With Independent Variable Cost CodeDescriptionCostUnits 3300PCC PavingEst.$70,00035,000 To Date$50,00020,000 27

Cost Report With Unit Cost Cost CodeDescriptionCostUnitsUnit Cost 3300PCC PavingEst.$70,00035,000$2.00 To Date$50,00020,000$

Cost Report With Unit Cost Cost CodeDescriptionCostUnitsUnit Cost 3301PCC PavingEst.$70,00035,000$2.00 To Date$90,00055,000$

Cost Report Modified for Change Orders Cost CodeDescriptionCostUnitsUnit Cost 3302PCC PavingOriginal$70,00035,000$2.00 Current$110,00070,000$1.57 To Date$90,00055,000$

Cost Report Incorporating Manhours Cost Code DescriptionCostManhoursUnitsManhours / Unit Unit Costs 3303PCC PavingEst.$70,0004,00035, $2.00 Current$110,0008,00070, $1.57 To Date$90,0005,50055, $

Cross Checks on Labor Cost Quantity Overruns Material Cost Overruns Change in Equipment/Labor Ratio Change in Subcontracts 32

Cross Check on Labor Cost–Case Study Building Inc alleged labor productivity losses resulting from excessive owner changes. The cost reports showed: Labor Budget as Adjusted for Changes ActualOverrun Concrete$125,000$393,000$268,000 Finish Carpentry$ 23,795$303,348$279,553 TOTAL$148,795$696,348$547,553 Material Budget as Adjusted for Changes ActualOverrun Concrete$217,527$359,876$142,349 Finish Carpentry$137,894$407,863$269,969 TOTAL$355,421$767,739$412,318 33

Measured Mile –Exhibit 1 122,452 manhours were spent by a contractor paving two similar stretches of roadway, Road A and Road B. The owner’s changes were limited to Road B, and required a more labor- intensive method of construction. The contractor used the same labor force and equipment, and encountered the same weather conditions on both roads. Measured Mile = Road A Impacted Area = Road B Manhours 55,000 Manhours 67,452 SY Produced 170,000 SY Produced 154,322 Hours/SY Hours/SY Increase in Unit Labor Rate = – = Quantity Affected by Changes 154,322 Manhours Increase Due to Changes = x 154,322 = 17,524 Labor Cost Per Manhours $23.40 Total Additional Labor Cost 17,524 x $23.40 = $410,

35 Measured Mile –Exhibit 2 In this hypothetical, the contractor segregated the equipment costs expended on each of the two roadways that were being paved, Road A and Road B. The owner’s changes were limited to Road B, and required a more equipment method of construction. The contractor used the same labor force and types of equipment, and encountered the same weather conditions on both roads. Measured Mile = Road A Impacted Area = Road B Manhours 55,000 Manhours 67,452 SY Produced 170,000 SY Produced 154,322 Hours/SY Hours/SY Increase in Unit Labor Rate = – = Quantity Affected by Changes 154,322 Manhours Increase Due to Changes = x 154,322 = 17,524 Labor Cost Per Manhours $23.40 Total Additional Labor Cost 17,524 x $23.40 = $410,068.48

Additional Equipment Cost Using Total Time on Project Equipment Monthly Ownership Rate Months On ProjectTotal Ownership Cost CAT 2258, ,000 CAT 63318, ,200 CAT 95012, ,600 Dump truck5, ,600 Total Ownership CostWorkdays On ProjectTotal Per Workday (Total ¸ Days) 88, , , , Cost Per WorkdayDelay Days Extended Equipment Ownership Costs (Cost × Days) $ , $ , $ , $ , TOTAL$40,

Additional Equipment Cost Using Daily Equipment Rates Equipment Idle/Unproductive Hours Hourly Standby Ownership Rate Extended Equipment Ownership Cost (Hour × Rate) CAT 22585$43.00$ 3,655 CAT $88.00$12,408 CAT $60.00$11,760 Dump truck208$27.00$ 5,616 TOTAL$33,439 37

Additional Equipment Costs Using Differential Costs (Method 1) EquipmentMonths On ProjectUnits Of Work Equipment Costs Per Unit Ownership Costs Recovered (Months × Units × Cost/Unit) CAT ,0002.5$ 75,000 CAT 63384,5003.5$126,000 CAT ,0001.5$126,000 Dump truck127, $ 63,000 Total Ownership CostOwnership Costs RecoveredExtended Equipment Cost $ 88,000$ 75,000$13,000 $147,200$126,000$21,200 $147,600$126,000$21,600 $ 63,600$ 63,000$ 600 TOTAL$56,400 38

Additional Equipment Costs Using Differential Costs (Method 2) Equipment Hourly Ownership Rate Productive Hours Ownership Costs Recovered CAT ,651$ 82,550 CAT ,243$130,515 CAT ,884$131,880 Dump truck301,872$ 56,160 EquipmentActual Costs Incurred Ownership Costs Recovered Ownership Costs Not Recovered CAT 225$ 88,000$ 82,550$ 5,450 CAT 633$147,200$130,515$16,685 CAT 950$147,600$131,880$15,720 Dump truck$ 63,600$ 56,160$ 7,440 TOTAL$45,295 39

Home Office Overhead Extended Overhead vs. Unabsorbed Overhead Fixed Costs vs. Variable Costs The Eichleay Formula 40

The Eichleay Formula 41

Variations in Quantity Unit price contracts often allow for adjustment in the unit price if the quantity of work is increased or decreased to a certain degree: – “Substantial inequity” – Increase or decrease of more than 25% Adjustments allowed only if the increased or decreased costs were caused by the quantity difference itself. 42

Example of a Contract or Claim 43

Summary of Amounts Due Contractor 44

Exhibit 1 Calculation of Remaining Contract Balance Due 45

Exhibit 2 Increase in Labor Burden Due to Extended Project Duration Because of increases in state and federal UCF, FICA, and workers’ compensation, on labor expended after November 30, 2010, the labor burden was 27.94%, an increase of 10.26%. This is calculated as follows % Total 11/30/2010 Labor Net of Burden Total Labor – Total 11/30/2010 Labor Total Burden Cost – Burden as of 11/30/2010

Exhibit 3 Labor Escalation – Part 1 Using the original distribution, the actual manhours of 122,452 are distributed using the estimated percentage distribution. This compared with the actual distribution. This project was delayed as shown on the Schedule Analysis. As a result, much of the labor was expended during higher wage rate periods. The original labor distribution was taken from the estimate, as shown below ,367 73,471 30,

Exhibit 3 Labor Escalation – Part 2 The labor escalation for this project is calculated as follows: Anticipated hours based on original schedule 18,36773,47130,6140 Labor hours actually expended 010,36068,7360 Hours escalated from prior period 8,00715,09566,00033,350 Total hours to be escalated to next period rate 10,36068,73633,350 Period differential Escalated wages 5,18051,52233,350 Total Escalated Wages $ 90,052 Labor Burden (at Original Rate) 17.68% $ 15,926 Total Wage Escalation Claim $ 105,978

Exhibit 4 Acceleration Costs – Premium Time Summary of Costs: Premium Portion$66, Burden at 17.68%$11, Total Premium Time Cost Claim$78,

Exhibit 5 Productivity Loss - Measured Mile – Part 1 Total Actual Manhours122,452 Change Order Hours Added to Contractor Work Change Order No Change Order No. 21,451 Change Order No. 36,790 Change Order No. 49,417 Change Order No. 56,157 Change Order No. 66,941 Subtotal 31,206 Additional Manhours Pending Change3,455 Additional Manhour Unit Price Adjustment 479 Total Change Order Hours (35,140) Actual Hours for Base Contract Work 87,312 Estimated Hours Base Contract Work(63,200) Unproductive Hours 24,112 Hourly Billing Rate – Original Contract $23.40 Lost Productivity Cost Claim$564, Predicted Productivity Loss-Measured Mile 25% Actual Productivity Loss27.6% 50

Exhibit 5 Productivity Loss - Measured Mile – Part 2 Measured Mile Determination Unit Productivity - Unit Productivity x Number of Units = Impact (Impacted Period) (Unimpacted period) (During Impacted Period) Productivity = cost in $ or manhours ÷ units produced Productivity of concrete work in Impacted Area A was $2.50/unit Productivity of concrete work in Unimpacted Area B was $2.00/unit Measured mile predicts 25% loss 51

Small Tools Costs Small Tools Costs are a function of labor. Therefore, if a contractor is entitled to compensation for extra labor, it is also entitled to compensation for extra small tools: 52

Small Tools Costs Small tools rate: Actual Small Tools Cost Actual Productive Labor = $99,106 $1,484,825 =6.67% Additional labor due to lost productivity totaled $591,205 Impact to small tools: $591,205 x = $39,433 53

Exhibit 6 Calculation of Extended Overhead Costs Using Eichleay Method

Exhibit 6 Calculation of Extended Overhead Costs Using Eichleay Method 55