Cryo Capture Cavity II Progress Mike McGee April 6, 2005.

Slides:



Advertisements
Similar presentations
ILCTA-MDB RF Power Status 9/21/06 Reid 1 ILCTA-MDB Status 1.3 GHz RF Power Meson Detector Building 3.9 GHz RF Power A0 Building September 21, 2006 [John.
Advertisements

MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
ATD Assembly. ATD Assembly #1 Dewar Assembly #1 Status: Dewar has been completely assembled and vacuum tested. No vacuum leaks were detected on the outer.
Superconducting Spoke Resonator Cavities and Cryomodules
Progress and Plan for Superconducting RF Cavity RF Group.
SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
RF Measurement Plan Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory January 20, 2011 MICE Video Conference Meeting.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Cryo Capture Cavity II Progress Mike McGee April 13, 2005.
LCLS-II Cryomodules Production Plans at Fermilab
SPL cryo-module conceptual design review Cavity, helium vessel and tuner assembly N. Valverde, G. Arnau, S. Atieh, I. Aviles, O. Capatina, M. Esposito,
An SRF Single Cavity Horizontal Test Facility Tom Peterson, Fermilab May 10, 2005.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
Internal Cryomodule Instrumentation ERL Main Linac Cryomodule 10/10/2015 Peter Quigley, MLC Design Review.
MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013.
S1 Global Module Cavity String Assembly Workflow Tug Arkan January 15, 2010.
FNAL Cavities for S1 Global Jim Kerby ALCPG 09. FNAL Deliverables Discussed in meetings 15/16 July and 10/11 Sept, and Webex and s 9/30/20092FNAL.
Type IV Cryomodule Proposal (T4CM) Don Mitchell, 16 JAN 2006.
E. KAKO (KEK) 2010' Feb. 05 STF Meeting for S1-G Global Design Effort 1 Preparation Status at KEK for S1-Global Eiji Kako (KEK, Japan)
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Americas Cavity Specification C.M. Ginsburg (Fermilab) On behalf of the Fermilab cavity crew October 20, 2010.
Date 2007/Oct./23 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Interface Definition (FNAL-GDE-Meeting) N. Ohuchi.
October, 2009 Cost of SRF Components Gary McIntyre October, 2009 Internal Review.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory Oxford, UK July 7, 2011 July 7, 2011.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
S1-Global status report KEK Norihito Ohuchi 2008/11/171ILC08-GDE-Meeting-Chicago.
CM2 Repair Status 8/13/2012 Tug Arkan 1. Latest Status After the warm end couplers were disassembled, it was decided to disassemble all the lower aluminum.
FNAL Cryomodule Assembly and Installation Plans Tug Arkan LCLS-II Production Cryomodule Final Design Review May 12-14, 2015.
Cryomodule Assembly Facility (CAF) at Fermilab Tug Arkan (FNAL) FNAL-LBNL joint meeting on SRF Cavities and Cryomodules March 15, 2012.
CM2 Helium Circuit Vacuum Leak & Repair Tug Arkan, 6/18/
Visiting DESY for S1-G module Norihito Ohuchi 2009/8/251 19th Biweekly Webex meeting (S1-G, Cryomodule, Cryogenics)
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Status of MICE RF for Step V’ (at LBNL) Derun Li Lawrence Berkeley National Laboratory December 6, 2014.
Page 1 CRYOMODULE 650 (TESLA Style) Stand Alone Tom Peterson and Yuriy Orlov Collaboration Meeting 25 Jan 2011.
RF Module Update MICE Collaboration Meeting 44 Andrew Lambert Lawrence Berkeley National Laboratory March 30 th, 2016.
Cryomodule Assembly Facility Fermilab Cleanroom: Assembly/Disassembly Tools Tug Arkan 1.
FNAL Cryomodule Assembly and Installation Plans Tug Arkan May 22, 2015.
HTS-2 – FY17 Budget Request Joe Ozelis, Sr. Eng. Physicist PIP-II Budget Retreat 26 April, 2016.
Overview of elliptical cryomodules vacuum system Vacuum Equipment Standardization meeting February 2014 P. Bosland – C. Darve – N. Elias.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
LEReC System 1. Project Schedule 2015 shutdown COMPETE! Move beam line equipment from IP 01:00 Install cooling section beam line 2016 shutdown Install.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
Fabrication of Remaining Components Allan DeMello Lawrence Berkeley National Laboratory MICE RF Workshop Fermilab June 2, 2014.
Status Report of the Review of Vacuum Systems and Procedures Tug Arkan, Allan Rowe 3/7/
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
LCLS-II 3 rd Harmonic Dressed Cavity Design Review Chuck Grimm November 20, 2015.
October 7, 2010 HINS Test Cryostat 2 K Conversion Status October 7, 2010.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
Teleconf ACS – FREIA 28th March 2017
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
FRIB Cryogenic Support
1.3-GHz Cavity Vacuum Furnace at IB4
DESY Experiences on Use of Gas overlay during Assemblies
S1-G cryomodule assembly status
Definition of work flow for string DESY Example on critical operation
S1-G Webex meeting Global Design Effort
Teleconference ACS – FREIA 20th February 2018
IHEP Cryomodule Status
Cryomodule Assembly Plan
Prototype cryomodule development
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
SNS PPU Cryomodule Instrumentation
SC1R Cold Box PDR Assembly Sequence
SNS PPU Cryomodule Design Overview
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

Cryo Capture Cavity II Progress Mike McGee April 6, 2005

DESY will Provide Input coupler assembly 2 VAT valves Magnet shielding (short) Helium vessel 1.3 GHz cavity

Status at Fermilab Designing VAT valve supports, shipping/installation fixture (to be made of 316 L) 316 LN material and tube ready to order 316 L bellows specified and ordered (to arrive 4/24) Finalizing US AND DS warm-to-cold transition and VAT valve to cavity spool design

US warm-to-cold transition

DS warm-to-cold transition

Fermilab will Provide To be send to DESY Cleaned US and DS warm-to-cold transitions (w/isolation flanges on ends and slight positive Ar pressure) Drawing and procedure for assembly with fixture to be shipped Shipping/installation fixture Cleaned VAT valve supports Cleaned helium vessel support clamps Cleaned spool between cavity and VAT valve (also capped on ends)

Fermilab will Provide Currently at Fermilab Vacuum vessel and instrumentation 80 K shielding 5 K manifold Tuner 2 Spare VAT valves

Process Send to DESY (May 2005) Cleaned US and DS warm-to-cold transitions and spool Under argon positive pressure valve w/filter blank flange

Process cont… 2 helium vessel support clamps

Process cont… VAT valve supports

Process cont… Shipping/installation fixture with temporary supports for bellows with crate

Process cont… Work at DESY (May-June 2005) Warm-to-cold transition Magnet shielding VAT valves with supports Cavity and helium vessel Assemble Clean US and DS warm-to-cold transitions Spool between VAT valve and cavity

Process cont… Send to Fermilab (July 2005) Assembled cavity with VAT valves, shielding, spool and transitions

Process cont… Work at Fermilab (July-August 2005) Modify helium return Install cavity assembly into vacuum vessel Pressure test helium vessel Make up cryogenic connections Test fit feedcan and leak check circuits

Process cont… Install cavity assembly into vacuum vessel

Layout

Process cont… Make up cryogenic connections Test fit feedcan and leak check circuits Commission Cryo Capture Cavity II

Questions and Requests Need DESY cleaning procedure Need to confirm critical measurements

Schedule