1 FEE Installation & Commissioning TPC Meeting, 21 April 2006 L. Musa.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

TPC-RO DCS set-up PVSS main(s) Iseg OPC server HV Iseg crates (3)LV Wiener crates (22) CAN bus Interface to FEE -temp.mon -I &V mon. Wiener OPC server.
TPC DETECTOR SEGMENTATION OF THE READOUT PLANE LATERAL VIEW OF THE TPC
Peter Chochula CERN-ALICE ALICE DCS Workshop, CERN September 16, 2002 DCS – Frontend Monitoring and Control.
Forward Detector Meeting, 11 Mar 2003Børge Svane Nielsen, NBI1 Si-FMD status Forward Detector meeting, CERN, 11 March 2003 Børge Svane Nielsen Niels Bohr.
1 Luciano Musa CERN participation to EUDET for TPC electronics CERN, 31 August 2006 Outline Part I – Development of the readout electronics for the LPTPC.
Star Week 6-10 Frb 2002SSD Status Report 1# SSD Status Report Main components Production status Last news: first ladder Schedule SSD pages:
HEP2005, Lisboa July 05 Roberto Campagnolo - CERN 1 HEP2005 International Europhysics Conference on High Energy Physics ( Lisboa-Portugal,
11/12 December 20061Borge S. Nielsen, NBI FMD contribution Second Installation and Commissioning Workshop DAQ and ECS FMD contribution Børge S. Nielsen,
Status at P2 C. Lippmann Jan. 22, 2007 TRD DCS workshop at PI, Heidelberg.
Update on DAQ Klaus Schossmaier CERN PH-AID ALICE TPC Meeting 21 April 2006.
HLT Collaboration (23-Jun-15) 1 High Level Trigger HLT PRR Planning Volker Lindenstruth Kirchhoff Institute for Physics Chair of Computer Science University.
CMS Tracker Week – Module Test Meeting – April 2003 – Patrick Gartung 1 Status of US long term module testing Patrick Gartung University of California,
Jochen Thäder – Kirchhoff Institute of Physics - University of Heidelberg 1 HLT for TPC commissioning - Setup - - Status - - Experience -
S.Sergeev, JINR, Dubna. This is just an example of what could be done Could be extended to needs of any NA62 sub- detector requiring a lot of analog measurements.
3 June 2003U. Frankenfeld1 TPC Detector Control System Status.
Normal text - click to edit RCU – DCS system in ALICE RCU design, prototyping and test results (TPC & PHOS) Johan Alme.
1 HBD Commissioning (II) Itzhak Tserruya HBD group meeting November 28, 2006 Progress from October 3 to November 28, 2006.
1 ALICE Control System ready for LHC operation ICALEPCS 16 Oct 2007 L.Jirdén On behalf of the ALICE Controls Team CERN Geneva.
Status of TRD Chamber and Readout Electronics Integration Ken Oyama and Christian Lippmann for the TRD Collaboration Sep. 26, 2005 TRD status meeting in.
February 12 th, 2004 Heidelberg TPC Meeting J.B. TPC SECTOR TEST at T10 May 3 rd – June 2 nd MOTIVATION REQUIREMENTS STATUS OF SYSTEM TIME SCHEDULE CONCLUSIONS.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
SALTRO TPC readout system Presented by Ulf Mjörnmark Lund University 1.
DCS T0 DCS Answers to DCS Commissioning and Installation related questions ALICE week T.Karavicheva and the T0 team T0 DCS Answers to.
DAQ & ECS for TPC commissioning A few statements about what has been done and what is still in front of us F.Carena.
FEE + ROC cooling S. Popescu CERN, U. Frankenfeld, H.R. Schmidt GSI.
1 Responsibilities & Planning DCS WS L.Jirdén.
Leo Greiner TC_Int1 Sensor and Readout Status of the PIXEL Detector.
TB Peter Glässel, Heidelberg1 TPC Progress.
S.Vereschagin, Yu.Zanevsky, F.Levchanovskiy S.Chernenko, G.Cheremukhina, S.Zaporozhets, A.Averyanov R&D FOR TPC MPD/NICA READOUT ELECTRONICS Varna, 2013.
108 Mar 2007L. Musa TPC Commissioning ALICE Technical Forum, CERN, 8 th March 2007 L. Musa Outline Pre-commissioning above ground (2006) Preparing for.
ALICE TPC Status, Meeting with LHCC referees ALICE TPC – Status Report Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader:
Bernardo Mota (CERN PH/ED) 17/05/04ALICE TPC Meeting Progress on the RCU Prototyping Bernardo Mota CERN PH/ED Overview Architecture Trigger and Clock Distribution.
The Readout Electronics for TPC with GEM readout chamber (and for almost any other readout chamber) Anders Oskarsson Lund Univ. Electronics: Bruxelles,
1 VeLo L1 Read Out Guido Haefeli VeLo Comprehensive Review 27/28 January 2003.
The AFTER electronics from a user’s point of view D. Attié, P. Colas Mamma meeting,CERN Feb T2K electronics.
Status report on the development of a readout system based on the SALTRO-16 chip Leif Jönsson Lund University LCTPC Collaboration Meeting
Status of the Remote HV System 10 June 2015 TileCal week, upgrade session Roméo Bonnefoy, Romain Madar and François Vazeille ● Summary of performances.
CERN, O.Pinazza: ALICE TOF DCS1 ALICE TOF DCS Answers to DCS Commissioning and Installation related questions ALICE week at CERN O. Pinazza and.
17th March 2005Bernardo Mota / CERN - PH TPC FEE Status and Planning CERN, 7th March 2005 Content  Introduction  Status and Milestones  PASA, ALTRO.
Alice DCS workshop S.Popescu 1 1. News from TPC DCS cooling prototype Project overview: Aim of the prototype: investigating and developing standard.
17/1/07 F. Formenti PH-ED1 Competence domain (PH-ED) What field of expertise ED can provide?  System electronics design  1.Front-end detector electronics.
07-Jan-2010 Jornadas LIP 2010, Braga JC. Da SILVA Electronics systems for the ClearPEM-Sonic scanner José C. DA SILVA, LIP-Lisbon Tagus LIP Group * *J.C.Silva,
Director’s Review of RunIIb Dzero Upgrade Installation Linda Bagby L0 Electronics Installation  System Electronics Overview u Low Voltage u High.
S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES.
TB Peter Glässel, Heidelberg1 TPC Status Report Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel, Heidelberg.
PS VFE & PS/SPD FE Electronics Status and Plans 16 January 2008 LPC Clermont.
1 Calorimeters LED control LHCb CALO meeting Anatoli Konoplyannikov /ITEP/ Status of the calorimeters LV power supply and ECS control Status of.
LC Power Distribution & Pulsing Workshop, May 2011 Super-ALTRO Demonstrator Test Results LC Power Distribution & Pulsing Workshop, May nd November.
Technical FORUM, Peter Glässel, Heidelberg1 TPC Progress Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel,
D. Attié, P. Baron, D. Calvet, P. Colas, C. Coquelet, E. Delagnes, R. Joannes, A. Le Coguie, S. Lhenoret, I. Mandjavidze, M. Riallot, E. Zonca TPC Electronics:
HBD Report Craig Woody BNL DC Meeting January 7, 2009.
1 HBD Commissioning Itzhak Tserruya DC meeting, BNL December 13, 2006 Progress from October 3 to November 28, 2006.
1 19 th January 2009 M. Mager - L. Musa Charge Readout Chip Development & System Level Considerations.
Status of Integration of Busy Box and D-RORC Csaba Soós ALICE week 3 July 2007.
IPHC-LBL-BNL video conference 19 Jan 2007 HFT development MimoStar2 based telescope.
14 February 2007 G. Bohner, R. Bonnefoy, M. Crouau, P. Jacquet, C. Lacan, J. Lecoq, S. Monteil, P. Perret, G. Reinmuth, K. Suchorski LPC Clermont PS Very-Front-End.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
T0 DCS Status DCS Workshop March 2006 T.Karavicheva on behalf of T0 team.
André Augustinus 17 June 2002 Detector URD summaries or, what we understand from your URD.
J. Valls, CMS L2-L3 Meeting, Sept ROD Production at CERN  ROD Flow During Production  ROD Flow at CERN  ROD Testing Areas  Infrastructure  Equipment.
The ALICE TPC Readout Control Unit 10th Workshop on Electronics for LHC and future Experiments 13 – 17 September 2004, BOSTON, USA Carmen González Gutierrez.
TPC Commissioning: DAQ, ECS aspects
Mini-drawers, FE-ASIC , Integrator
SPD – ALICE DAQ/ECS/Trigger Integration Status Report
Large CMS GEM with APV & SRS electronics
TPC Status Outline Completion of installation 14 September 2006
TileCal ROD Commissioning Counting Room Installation
TPC Detector Control System
SALTRO16 activities in Lund
Presentation transcript:

1 FEE Installation & Commissioning TPC Meeting, 21 April 2006 L. Musa

2  Installation of FECs and Backplanes Jan ’05 - Mar ’06  electrical and functional test of each FEC  test of the connection between FECs and pad plane  test of the connection between FECs and readout backplane PHASE I  Installation of RCUsMay – Aug ’06  Comprehensive test of all (216) readout partitions: FEE, DAQ, DCS, TRIGGER, HLT, ECS (power bars and cooling required) PHASE III  Characterization of the whole system with RCUsMar – May ’06  Characterization of 1 readout partition at a time: noise, gain, width, baseline, time offset, temperature, voltages and currents PHASE II Electronics Installation and Commissioning Schedule

3 FE Cards Installation 1/2  Organization and schedule 2 installation crews (3 people / crew) Installation started on the 30 th January Installation rate: ~ 1 sector / day  Status Installation of FECs completed (on March 15), with exception of 1 sector on C side Installation of Readout &Control backplanes completed by end of March, with exception of 1 sector on C side The electronics of 1 sector (A09), equipped with the LV bus rods and cooling, was characterized (pedestals, noise, gain) The electronics of sector A08 is under test

4  Measurement of VCC A, VCC D, I A, I D and T  Measurement of the FEC Identifier FE Cards Installation 2/2 During the installation, the FECs are tested individually (stand-alone) by means of a dedicated “mounting test tool”, U2F (USB to FEC interface) U2F Card  Readout of trigger related data (pulser) Connection to the pad plane

5 FE Cards Installation highlights

6 TPC A Side (17 th February ’06)

7 Characterization of Sector A09 Sector A09 equipped with backplanes cooling circuit LV power rods LV PS + cables (4 x 40m) Sector A09 equipped with backplanes cooling circuit LV power rods LV PS + cables (4 x 40m)

8 sum of charges sum of charges, pad row 46 baseline noise rms (ADC counts) Characterization of Sector A09 - IROC

9 sum of samples baseline rms Characterization of Sector A09 - IROC baseline  (PASA noise 2 + ADC noise 2 ) = 0.70 ADC counts

10 sum of chargessum of charges, pad row 11 Characterization of Sector A09 - OROC baseline noise rms (ADC counts)

11 sum of samples Characterization of Sector A09 - OROC baseline rms sum of samples

12 Power Regulators RCU status and plans … Readout Control Unit 1/2 DCS CARD SIU CARD

13 Readout Control Unit 2/2  Mass Production (240 units including 10% spares)  completed November ‘05  Mass Test  completed December ’05  Delivery of tested DCS cards Mar ‘06  Delivery of tested SIU cards (DAQ project):  1 st lot (108 units)Mar ’06  2 nd lot (108 units)May ‘06  Assembly and final test of RCU + SIU + DCS: Apr – Jun ‘06  Installation and commissioning of RCUs: May – Aug ‘06 Production, test, installation and commissioning

14 Preparing for Commissioning Phase III  RCU Lab - setup I  Final assembly and test of RCU + SIU + DCS  25 FECs (readout partition) + Backplane + RCU  1 DAQ PC (PCALD23) + single-channel RORC  1 DCS PC (local network DHCP server, DIM Server) + Ethernet Switch  Local Trigger Crate (SBC, LTU, TTvi, TTCex) + TTCoc  RCU Lab - setup II  TPC FEE + DAQ + HLT Integration  2 x Readout Partitions  1 DAQ PC (EPAITBEAM02) + dual-channel RORC  1 HLT PC + 1 HRORC  P2 SXL2 – Test of the electronics, 1 Sector at a time  1 x Readout Partition  1 DAQ PC (ALDAQPC021) + dual-channel RORC

15 Conclusions  Installation of FECs almost complete (97% done)  The complete electronic chain of one TPC sector has been characterized  gain, baseline and noise distributions well within specifications  Installation of backplanes was completed by Mar ’06  Installation and commissioning of RCUs in May - Aug ‘06