UPGRADES FOR ENERGY EFFICIENCY Vali Sorell, PE Vice President National CF Chief HVAC Engineer Syska Hennessy Group AFCOM NC Chapter, November 12, 2014.

Slides:



Advertisements
Similar presentations
Challenges in optimizing data center utilization
Advertisements

Sustainable School Design Creating Healthy, High Performance School Facilities Presented by Stephen M. Koontz, Energy Services Leader, Tampa Bay Trane.
XEnergy Technologies Energy Efficiency Through Creativity.
Air Conditioning System
Clair Christofersen Mentor – Aaron Andersen August 2, 2012
ENERGY SAVING Product Offering COMPRESSOR MARKETING OPPORTUNITIES.
Components of HVAC System
Innovative Air Distribution for Healthcare Facilities.
University of Iowa Indoor Practice Facility Outside-the-box HVAC Lincoln Pearce, PE – KJWW Engineering David Hahn – University of Iowa Chilled Water Plant.
The Value of DOD Installation Energy Management Control Systems (EMCS) and Command Centers for Improved Operations and Increased Energy Efficiency Moderator:
Smart Devices. Smart Buildings. Smart Business The Potential for DCx Technology Enabled HVAC Operation Scot Duncan, P.E.
Variable Frequency Drives VFD Basics
Using Benchmarking to Identify Energy Efficiency Opportunity in Cleanrooms; The Labs 21 Approach William Tschudi and Peter Rumsey June 29, 2004
An Economical Analysis on Data Servers; Green vs. Regular Teddy Hsieh, Chris Davis, Christopher Perrenoud, Matt Nickeson, Shabnam Jahromi ETM 535-Winter.
Worcester Polytechnic Institute Gordon Library and Fuller Laboratory B.N. Tripathi Senior Vice President CES/Way.
Cooling Product Positioning
PG&E and Altera Data Center Energy Efficiency Project.
ENERGY EFFICIENCY FOR END-USERS.  CSU Chancellors office coordinates the efforts to accomplish the goals established by Assembly Bill 32 for green house.
44 th Annual Conference & Technical Exhibition By Thomas Hartman, P.E. The Hartman Company Georgetown, Texas Sustainable Chilled Water.
UTSW Thermal Energy Plants, Power Generation and Electrical System What do we do to meet the Emission Reduction, Energy usage Reduction and Electrical.
 Site  Requirements  Local Resources  Initial layout ideas  Brief material selection  Supply options.
Presentation Outline Introduction CHP Analysis Electrical Analysis Acoustical Analysis Thermal Storage Analysis System Optimization Analysis Conclusion.
Solar Energy Technology for Commercial Facilities John Archibald American Solar, Inc. Association of Energy Engineers Baltimore Chapter.
Refrigeration and Heat Pump Systems Refrigeration systems: To cool a refrigerated space or to maintain the temperature of a space below that of the surroundings.
CoolAir Temperature- and Variation-Aware Management for Free-Cooled Datacenters Íñigo Goiri, Thu D. Nguyen, and Ricardo Bianchini 1.
September 18, 2009 Critical Facilities Round Table 1 Introducing the Heat Wheel to the Data Center Robert (Dr. Bob) Sullivan, Ph.D. Data Center Infrastructure.
Upstate Energy Expo 2010 NYSERDA Program Overview March 30, 2010 Cheryl Glanton, Project Manager.
Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency.
1Taylor Engineering, LLC HVAC System Design Mark Hydeman, P.E., FASHRAE Taylor Engineering, LLC
Chilled Water Systems Total Cost of Ownership
CenterPoint Energy Healthcare Energy Efficiency Program (HEEP) CenterPoint Energy Healthcare Energy Efficiency Program (HEEP) November 2013.
Auraria Higher Education Center Case Study John Ismert & Frank Ellis Auraria Higher Education Center Facilities Management.
Best Practices in HVAC Design/Retrofit
Overview of Liquid Cooling Systems Peter Rumsey, Rumsey Engineers.
Important variables Water: Air: Conversion:
Data Centers - They’re Back… E SOURCE Forum September, 2007 William Tschudi
Air Conditioning and Computer Centre Power Efficiency The Reality Christophe Martel Tony Cass.
Mission Energy: Energy Efficient Cooling How Data Centre energy consumption and operating costs can be significantly reduced through readily available.
Data centre air management Case studies Sophia Flucker.
NOVO ETS IMPROVING YOUR ORGANIZATIONS’ ENVIRONMENTAL, HEALTH AND SAFETY PERFORMANCE ENERGY MANAGEMENT IN THE CONTEXT OF GREEN PRODUCTIVITY.
Name of Building(s) or Project Speaker(s) Organization(s)
November 2004 Low Hanging Fruit Low Cost Energy Efficiency Opportunities in Cleanrooms.
Overview of Data Center Energy Use Bill Tschudi, LBNL
VIMS Seawater Research Laboratory Dan DiCriscio AE Senior Thesis Mechanical Option 2007.
The Data Center Challenge
Introduction to HVAC Optimization
We can…. 2 GLOBAL REFERENCES Rev: 00 References :
1 CTO Challenge William Tschudi February 27, 2008.
Authors: William Tschudi, Lawrence Berkeley National Lab Stephen Fok, Pacific Gas and Electric Company Stephen Fok, Pacific Gas and Electric Company Presented.
#watitis2015 TOWARD A GREENER HORIZON: PROPOSED ENERGY SAVING CHANGES TO MFCF DATA CENTERS Naji Alamrony
1 Data Centers for the 21st Century Working with Industry to Improve Energy Efficiency in Data Centers Dale Sartor, P.E. LBNL Applications Team June 7,
Energy Savings in CERN’s Main Data Centre
Green Server Room Construction Primary concerns when building a server room is size and cooling. Size can be diminished with the use of virtual servers.
Data Center Energy Use, Metrics and Rating Systems Steve Greenberg Energy Management Engineer Environmental Energy Technologies Division Lawrence Berkeley.
All content in this presentation is protected – © 2008 American Power Conversion Corporation Row Cooling.
War Stories: Implementing ASHRAE’s 2011 Allowable Ranges in Data Centers Mark Monroe, Vice President & CTO of DLB Associates Consulting Engineers Session.
Copyright © 2015 Optimum Energy LLC. All Rights Reserved. Proprietary & Confidential Incorporating Energy Conservation Strategies into University Research.
1 ITM 1.2 How IT Decisions Impact Data Center Facilities: The Importance of Collaboration Lars Strong P.E. Upsite Technologies, Inc.
1 PCE 2.1: The Co-Relationship of Containment and CFDs Gordon Johnson Senior CFD Manager at Subzero Engineering CDCDP (Certified Data Center Design Professional)
Data Center Energy Efficiency SC07 Birds of a Feather November, 2007 William Tschudi
1 Copyright © 2016, The Green Grid The webcast will begin shortly Today’s live session will be recorded.
Unit 2: Chapter 2 Cooling.
The Data Center Challenge
Lecture Objectives: Discuss Final Project
Thermal Energy Storage
ANSI/ASHRAE 90.4 Energy Standard for Data Centers
Energy Efficiency in District Coiling System
The Benefit of Including Energy Recovery System Analysis
ENERGY SAVING Product Offering
Liebert DSE High efficiency thermal management
Presentation transcript:

UPGRADES FOR ENERGY EFFICIENCY Vali Sorell, PE Vice President National CF Chief HVAC Engineer Syska Hennessy Group AFCOM NC Chapter, November 12, 2014

Agenda – Non-Capital Upgrades Improvements in Air Flow Improvements in Setpoints Improvements in IT Operations – Capital Upgrades CRAH Unit Upgrades Economizers New Build Improvements – Reduction of Impact to Utilities Importance of Reducing kW Demand 2Syska Hennessy Group / Upgrades for Energy Efficiency

Agenda – Non-Capital Upgrades Improvements in Air Flow Improvements in Setpoints Improvements in IT Operations – Capital Upgrades CRAH Unit Upgrades Economizers New Build Improvements – Reduction of Impact to Utilities Importance of Reducing kW Demand 3Syska Hennessy Group / Upgrades for Energy Efficiency

Improvements in Air Flow – Biggest mistake owners make is not managing air flow This leads to orphaned capacity Which leads to wasted energy – To manage air flow, must MIND THE GAP! Minimize “recirculation” and “bypass” (or use containment) Monitor load per cold aisle Adjust air flow per cold aisle for the load in that cold aisle 4Syska Hennessy Group / Upgrades for Energy Efficiency

Improvements in Air Flow 5Syska Hennessy Group / Upgrades for Energy Efficiency Not so good… Much better!

Improvements in Air Flow – Don’t forget to look in the less obvious places! – These blatant gaps can rob 25% - 50% of actual cooling capacity! 6Syska Hennessy Group / Upgrades for Energy Efficiency

Improvements in Air Flow 7Syska Hennessy Group / Upgrades for Energy Efficiency Both of these lead to orphaned capacity

Improvements in Air Flow – Do not install tiles where they are not needed – When CRACs/ CRAHs can modulate, they should adjust based on the amount of tiles installed 8Syska Hennessy Group / Upgrades for Energy Efficiency

Agenda – Non-Capital Upgrades Improvements in Air Flow Improvements in Setpoints Improvements in IT Operations – Capital Upgrades CRAH Unit Upgrades Economizers New Build Improvements – Reduction of Impact to Utilities Importance of Reducing kW Demand 9Syska Hennessy Group / Upgrades for Energy Efficiency

Improvements in Setpoints 10Syska Hennessy Group / Upgrades for Energy Efficiency

Improvements in Setpoints – Use the thermal envelope – Use the highest temperature possible – THIS SINGLE DESIGN DECISION MAKES THE BIGGEST IMPACT ON ENERGY 11Syska Hennessy Group / Upgrades for Energy Efficiency

Improvements in Setpoints – The reason users use 65 deg F in the cold aisle rather than 80 deg F: Fear that high points in the cabinets will overheat – Follow the best practices and this stratification will not occur – How much difference is there between these two setpoints? 12Syska Hennessy Group / Upgrades for Energy Efficiency

Improvements in Setpoints – When staying within “Recommended Range” 13Syska Hennessy Group / Upgrades for Energy Efficiency At 65 deg F SAT (Charlotte) At 80 deg F SAT (Charlotte)

Improvements in Setpoints – With excursions into “Allowable Range” 14Syska Hennessy Group / Upgrades for Energy Efficiency At 65 deg F SAT (Charlotte) At 80 deg F SAT (Charlotte) Up to 90 deg F SAT (Charlotte)

Agenda – Non-Capital Upgrades Improvements in Air Flow Improvements in Setpoints Improvements in IT Operations – Capital Upgrades CRAH Unit Upgrades Economizers New Build Improvements – Reduction of Impact to Utilities Importance of Reducing kW Demand 15Syska Hennessy Group / Upgrades for Energy Efficiency

Improvements in IT Operations – Too often, design decisions are made to minimize PUE – only to be overridden when the owner sees how much the facility will cost. – PUE is a BAD metric to use for design decision making. PUE = annual energy into facility / annual energy consumed by IT equipment PUE does not address IT energy It is not a good decision-making tool in selecting the most suitable design It does not include use of other resources, such as – KW demand (yes, this is a resource separate from energy) – gallons of water – Therms of gas 16Syska Hennessy Group / Upgrades for Energy Efficiency

Improvements in IT Operations 17Syska Hennessy Group / Upgrades for Energy Efficiency 131 million kWH/year 105 million kWH/year 110 million kWH/year

Improvements in IT Operations – It is important to consider: More efficient servers Refresh when new technologies are available Virtualize Consider use of Cloud Computing Remove unused (comatose) servers New technologies – Liquid immersion cooling – Air-Liquid hybrid cooling – Scope of potential IT energy savings is greater than the entire infrastructure energy 18Syska Hennessy Group / Upgrades for Energy Efficiency

Agenda – Non-Capital Upgrades Improvements in Air Flow Improvements in Setpoints Improvements in IT Operations – Capital Upgrades CRAH Unit Upgrades Economizers New Build Improvements – Reduction of Impact to Utilities Importance of Reducing kW Demand 19Syska Hennessy Group / Upgrades for Energy Efficiency

CRAH Unit Upgrades – For DCs with old CRAC units: Upgrade to CRAH units, if feasible Energy supporting CRAC units is ~2X energy for CRAH (chilled water) units If conversion to chiller water is not feasible, consider pumped refrigerant units – For DCs with old CRAH units: Upgrade to VFD – Modify controls sequences to reduce speed to just meet the load – System performance is improved and operation is more stable – Can be added to existing CRAHs Upgrade to ECM (electronically commutated motors) – Similar in concept to VFD control, but slightly more efficient – Requires more upgrades – Can easily be rolled into economizer upgrade 20Syska Hennessy Group / Upgrades for Energy Efficiency

Agenda – Non-Capital Upgrades Improvements in Air Flow Improvements in Setpoints Improvements in IT Operations – Capital Upgrades CRAH Unit Upgrades Economizers New Build Improvements – Reduction of Impact to Utilities Importance of Reducing kW Demand 21Syska Hennessy Group / Upgrades for Energy Efficiency

Economizers – Airside Uses outside air to cool the data hall Usually implements direct evaporative coolers to cool when hot and dry / humidify when cold Very efficient Requires significant space and cost If high SAT is selected, and/or if no cooling is required, this option is very attractive – Waterside Uses cooling tower water to provide cooling when outdoor wet bulb temperature is low Not as efficient as Airside, but extremely cost effective when coupled with existing CRAH units No extra humidification and filtration required This option usually has the best TCO due to low capital expense – Indirect Evaporative Coolers Outside air is cooled by evaporating water into it; this outside air then to cools the air for the data hall air through a heat exchanger Very efficient Requires significant space and cost No extra humidification and filtration required This options usually has the highest TCO unless the design outdoor is dry. Under those conditions, the plant size can be reduced, making the TCO more favorable 22Syska Hennessy Group / Upgrades for Energy Efficiency

Economizers – All buildings are required to incorporate an economizer (ASHRAE 90.1) – The selection of the type of economizer is not a straightforward decision; TCO, convenience, and risk become major considerations – Very dependent on cost of energy and hours of available free cooling – Hours of available free cooling is very dependent on the selection of supply air temperature 23Syska Hennessy Group / Upgrades for Energy Efficiency

Economizers – But is there risk to the critical load when using an economizer? – Risk can be mitigated by: Proper controls and sequencing of valves, motors, and other equipment Commissioning Increasing the hours of available free cooling! – Consider this: The fewer the hours required of the mechanical plant (the least reliable portion of the infrastructure), the more reliable becomes the operation of the infrastructure 24Syska Hennessy Group / Upgrades for Energy Efficiency

Agenda – Non-Capital Upgrades Improvements in Air Flow Improvements in Setpoints Improvements in IT Operations – Capital Upgrades CRAH Unit Upgrades Economizers New Build Improvements – Reduction of Impact to Utilities Importance of Reducing kW Demand 25Syska Hennessy Group / Upgrades for Energy Efficiency

New Build Improvements – A facility starting from scratch will look very different from one that is upgraded over its life – Accommodations can be made to incorporate a more energy efficient design right from the start. This may include: Extra yard space – E.g. dry coolers may be required if liquid cooling is used Extra fan gallery or air handling unit gallery space – E.g. indirect evaporative coolers may require twice the space compared to conventional air handlers Roof penetrations for rooftop equipment – E.g. indirect evaporative coolers are well suited for rooftop installation Wall penetrations for outside air and exhaust air – E.g. airside economizers require wall space or roof space for intake/exhaust 26Syska Hennessy Group / Upgrades for Energy Efficiency

New Build Improvements – New technologies can be incorporated at the design phase Liquid immersion cooling (which may change the look and feel of the data hall) – Can eliminate mechanical cooling – High temperature cooling (this is not an oxymoron!) opens the possibility of heat reclaim Elimination of cooling – Today’s servers are designed for higher inlet temperatures (>90 deg F) and lower air flow (i.e. higher delta T) – Simply ventilating the data hall should be sufficient – If a data hall is ventilated only (no cooling, no humidification) the ideal infrastructure efficiency would be achieved. Only fan energy would be utilized. 27Syska Hennessy Group / Upgrades for Energy Efficiency

Agenda – Non-Capital Upgrades Improvements in Air Flow Improvements in Setpoints Improvements in IT Operations – Capital Upgrades CRAH Unit Upgrades Economizers New Build Improvements – Reduction of Impact to Utilities Importance of Reducing kW Demand 28Syska Hennessy Group / Upgrades for Energy Efficiency

The Importance of Reducing kW Demand – Most data center metrics focus on energy PUE is an energy term TCO analyses look at $’s in the life of the facility, which is proportional to the energy use (it also includes capital costs and other owning costs) USGBC’s LEED energy modeling requirement looks at operating cost/year, which is a surrogate for energy use 29Syska Hennessy Group / Upgrades for Energy Efficiency

The Importance of Reducing kW Demand – How does kW Demand fit in? End users have expectation of availability of full capacity from the grid, even if it’s a transient need for a few hours in the year When that capacity cannot be met, rolling brownouts and blackouts begin This is bad for business and troublesome for the end user with a need for continuous uptime Deficiencies are usually met by running generating capacity, and risk is increased proportionately 30Syska Hennessy Group / Upgrades for Energy Efficiency

The Importance of Reducing kW Demand – There is a general misconception about the need to save energy: It’s not just about energy; saving on demand may have a bigger role! – The EPA/DOE/US-State-Local Governments have an interest in conserving energy – The end user has an interest in conserving energy (actually, the end user wants to save $$) – The utility that sells the energy to the end user has an interest in NOT building new generating capacity or NOT running peaking plants » Building new capacity is extremely expensive, complex, and time consuming » Running peaking plants to meet the occasional demand is not cost effective to the utilities 31Syska Hennessy Group / Upgrades for Energy Efficiency

The Importance of Reducing kW Demand – The end user has several options: Load curtailment/demand response – i.e. reduce load during high demand peaks – In exchange, utility gives reduced rates to the end users – This may require running generators – this may be risky and may violate state and local ordinances for air quality Load shedding – i.e. design a cooling system with extended thermal storage (beyond what a typical data center would need) – The capital expenses for this type of system usually exceed other options – The controls for load shedding are complicated – Increased risk of failure – e.g. one event when load shedding doesn’t work may negate cost savings for month or year – Will use more energy – Not recommended for critical facilities 32Syska Hennessy Group / Upgrades for Energy Efficiency

The Importance of Reducing kW Demand – For cooling technologies, some options that reduce the peak demand: DX CRAC units/remote condensers Chilled water CRAH units with air-cooled chillers Chilled water CRAH units with water-cooled chillers Built-up air handling units with water-cooled chillers Indirect evaporative coolers with DX coils/remote condensers (but only if a credit for reduced cooling capacity is taken) Immersion liquid-cooling Ventilated-only spaces 33Syska Hennessy Group / Upgrades for Energy Efficiency BETTER WORSE

The Importance of Reducing kW Demand – Economizers DO NOT affect the peak demand But utilities will incentivize for better economizers to save energy – The utilities will also incentivize to reduce the annual peak demand through innovative technologies This usually provides the bigger bang for the buck, for the reasons already stated The incentive programs are often published and socialized to the many end users that would need them, but there are cases where this program can be negotiated 34Syska Hennessy Group / Upgrades for Energy Efficiency

Parting thoughts… – Reduction of ITE kW demand is the biggest piece of the energy AND demand pie – End users must consider how to reduce IT energy/demand, and how to quantify this reduction (through virtualization, improved IT equipment selection/design, equipment refresh, etc.) so that its value, in terms of incentives and rebates, can be calculated. 35Syska Hennessy Group / Upgrades for Energy Efficiency

Questions, comments, thoughts, complaints ??? 36Syska Hennessy Group / Upgrades for Energy Efficiency Vali Sorell, PE Syska Hennessy Group 201 S. Tryon St., Suite 1400 Charlotte, NC