HOOSIER HEARTLAND HIGHWAY Public Information Meeting – August 27, 2009 STATE ROAD 25, SEGMENT 2 From 0.42 mile east of Tippecanoe/Carroll County line to.

Slides:



Advertisements
Similar presentations
Fairfax County Board of Supervisors Transportation Sub-Committee Briefing Federal Highway Administration Eastern Federal Lands Highway Division Robert.
Advertisements

Resource Team/TEER Meeting October 19, CBRT Meeting October 19, 2006 Agenda 10:00 AM 10:05 AM 10:30 AM 11:30 AM Noon Introductions and Housekeeping.
District Agreement Process Temi Latinwo Federal Aid Agreement Technician.
Mid-Bay Bridge Connector Phase II and III December 2011 Project Update.
Titusville to Edgewater Bike Loop PD&E Study
State Road 46 Pavement Replacement Owen Valley High School Wednesday, September 3, 2014.
I 65 Added Travel Lanes Project Clark County Ivy Tech Community College Thursday, March 12, 2015.
U.S. 33 Northern Connector Alternative
Narcoossee Roadway Corridor Analysis Osceola County Board of County Commissioners Meeting December 4, 2006
S.R. 256 Road Reconstruction Project From City of Austin to S.R. 203 Thursday, February 6, 2014 Austin Elementary School 6:00 p.m.
State of Florida Department of Transportation SR 7 (US 441) Value Engineering Study September 24-28, 2001 Segment III - From North of Hollywood Blvd to.
Chubaka Producciones Presenta :.
U.S. 31 at CR 400 South Roundabout Information Meeting December 18, 2013 Clifty Creek Elementary Columbus, Indiana.
2012 JANUARY Sun Mon Tue Wed Thu Fri Sat
NE 203 rd Street & NE 215 th Street Intersection Improvements between US 1 & West Dixie Highway Florida Department of TRANSPORTATION Upcoming Project Development.
Highway 169 Phase 2 (Part 2) – Cross Range Expressway April 30, 2014 Public Information Meeting Taconite Community Center.
US 1 COLLEGE PARK – SEGMENT 1 FROM COLLEGE AVE/REGENTS DRIVE TO MD 193 (UNIVERSITY BLVD) Presentation to College Park City Council August 5,
U.S. 150 / S.R. 56 Roadway Rehabilitation Project Thursday, August 22, :00 p.m. Presentation Orange County Community Center Paoli, Indiana.
Gaviota Beach Road – Transportation Division County Project Summer Crossing – Pre 1997 Located west of Highway 101 Access to Gaviota Beach and Hollister.
U.S. 24 over Tippecanoe River Bridge Replacement
PWC Quarterly Transportation Report DATA Roundtable June 17, 2015 Rick Canizales – Chief Department of Transportation.
West Northern Lights Boulevard – Sound Barrier Improvements August 16, 2006 Meeting Purpose: A Forum to Share and Gather Information The Municipality of.
Ottawa’s Light Rail Transit Project OLRT Tunnel Geotechnical Update Technical Briefing December 21, 2010 John Jensen Director Rail Implementation Office.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
Utility & Rail Coordination in Project Development Jennifer McCleve Utilities & Rail Branch Manager.
INDOT Access Management Study _________________________ Long Range Transportation Planning Section Division of Environment, Planning and Engineering INDIANA.
SR 1 BLUFFTON Public Hearing September 25, INDOT Mission: INDOT will plan, build, maintain and operate a superior transportation system enhancing.
FEDERAL PROGRAM Charles F. Riddle, P.E. Program and Office Engineer Bureau of Local Roads and Streets
U.S. 33 Northern Connector Alternative Goshen High School Auditorium, Goshen, IN Thursday, March 20, 2014.
WELCOME! July 31, 2012 ODOT District July 31, 2012 PURPOSE OF TONIGHT’S MEETING Introduce the project –Reconstruct I-75.
S.R. 930 and Green Street Intersection Improvement Project Tuesday, May 22, :00 p.m. Presentation Park Hill Learning Center Auditorium New Haven,
Sunrise JTA Project Jobs and Transportation Act. Project Vicinity I-205 Downtown Portland Oregon City.
U.S. 150 / S.R. 56 Road Reconstruction Project in Paoli, Orange County Thursday, August 25, :00pm Presentation Orange County Community Center 1075.
Texas Department of Transportation Corpus Christi District Harbor Bridge Project U.S. 181 (Harbor Bridge)/SH 286 (Crosstown Expressway) Citizens Advisory.
Titusville to Edgewater Bike Loop PD&E Study FDOT Project Number: Volusia County, Florida FDOT Project Number: Brevard County,
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
Needs What is it? Needs What is it?. Minnesota Statute Apportionment of money to counties. Subd. 2. Money needs defined. For the purpose of this.
HOOSIER HEARTLAND HIGHWAY SR25 Segment Four Cass County Public Information Meeting December 10, 2009 Design Consultant – United Consulting Engineers.
August 19, 2015 Port Bienville Rail EIS Scoping Meeting Presented by: Rhea Vincent Mike McGuire.
U.S. 20 Intersection Improvement Project at Waverly Road Porter Town Hall Thursday, August 13, 2015.
1 MD 5 (Point Lookout Road) Leonardtown (Phase 1) Intersection Reconstruction At Abell and Moakley Streets Informational Meeting January 19, 2016.
MED SR 18 Corridor Project MED PID October 13, 2015.
I-465 at I-65 Interchange Modification Public Meeting 6:00pm Monday, October 1, 2012 South Grove Intermediate School Beech Grove, Indiana.
Asphalt Pavement Association of Indiana Annual Winter Conference Michael B. Cline Commissioner, INDOT December 14, 2010.
Fitzgerald Marine Reserve CA Coastal Trail California Coastal Commission May 12, 2011.
California’s Experience with HFST 1.  Overview  Challenging Locations  Collision Reduction (State and Local Roads)  Typical Placement and current.
July 2007 SundayMondayTuesdayWednesdayThursdayFridaySaturday
Tonight’s Schedule Introduction Presentation Question and Answer Session Open House Staff at displays to answer questions Complete comment cards and/or.
BROOKS BRIDGE REPLACEMENT STUDY February 18, 2016 Project Briefing for Presenters: April Williams, P.E. (FDOT Project Manager) Steve Schnell, AICP (HDR.
Indian Hill Grade Separation City Council Meeting February 23, 2016.
Introductions U.S. Army Corps of Engineers Metro Parks Mayor’s Office Metro Council District Representatives HDR, Inc.
S.R. 30A / U.S. 98 / Panama City Beach Parkway Project Development & Environment (PD&E) Study F ROM M ANDY L ANE TO T HOMAS D RIVE I NTERSECTION B AY C.
Welcome!. OVERVIEW Limited access reconstruction/relocation of US 31 from US 30 to US 20. The project area includes the communities of LaPaz and Lakeville,
Brookeville Bypass Final Design Presentation Initech May 6, 2004.
Project Status & Right-of-Way Acquisition
FY 2012 Status Report on the North Mainland (Ormond Crossings CRA)
I-66 Outside the Beltway Design Public Hearing Meetings November 13, 14 & Susan Shaw, P.E., Megaprojects Director Virginia Department of.
SR 25 – Hoosier Heartland Highway Lafayette to Logansport
Measure A Financial Oversight Committee August 7, 2013
McDonald’s Kalender 2009.
McDonald’s Kalender 2009.
SR422 Section 29M, Berks Co. West Shore Bypass Reconstruction
McDonald’s Kalender 2009.
McDonald’s calendar 2007.
Teacher name August phone: Enter text here.
Louis E. Feagans, P.E. Statewide Technical Services Director, INDOT
McDonald’s calendar 2007.
STATE ROAD 61/369 CRAWFORDVILLE HIGHWAY
2015 January February March April May June July August September
Presentation transcript:

HOOSIER HEARTLAND HIGHWAY Public Information Meeting – August 27, 2009 STATE ROAD 25, SEGMENT 2 From 0.42 mile east of Tippecanoe/Carroll County line to 0.20 mile east of CR400W Length of 8.46 miles with 9 Bridges INDOT DESIGN CONSULTANT: Bernardin Lochmueller & Associates, Inc. Jeff Whitaker, P.E.

Section 2: Central Segment Current Design Status Road & Bridge Design - 50% Complete R/W Engineering – 50% Complete

Section 2: Central Segment Work Schedule Hydraulic Review & Grade Review (Completed 2007) Context Sensitive Solution Design (Completed August 28, 2008) Preliminary Field Check of Road & Bridge (February 23, 2009) Public Information Meeting (August 27, 2009) Design Approval (September 2009)

Section 2: Central Segment Right-of-Way Schedule R/W Engineering & Acquisition ( ) 90 Parcels of Property 26 Relocation R/W Appraising (Oct/Nov 2009-April 2010) Property Information

Construction Schedule Phase 2A - (November ) Phase 2B – (March ) Phase 2C – (December ) Phase 2D – (October ) Section 2: Central Segment

Alignment Issues: Alignment was shifted on SR 25 and Connector Roads to avoid Environmental Sensitive Areas Alignment shifted on SR 218 because of an at-grade Railroad Crossing Alignment shifted on Connector Road between the New SR 218 and Existing SR 218 Robinson Branch Bridge Added: Because of Environmental Stream Impacts & Wetland Seeps Upstream Bridge Creek Bridge Added: Because of hydraulics & cost savings Section 2: Central Segment

Main Street Access Local Officials Requested – Main Street Access Revised Improve Entrance into Delphi Signature Bridge for the Monon Trail Section 2: Central Segment

Context Sensitive Solutions - Deer Creek Valley Rural Historic District Committee Stakeholders Total of 4 Meetings, Last Meeting August 28, 2008 Context Sensitive Design Solutions Texturing & Coloring of the Retaining Walls & Bridge Piers Shape of Bridge Piers Type of Bridge Railing Type of Landscaping Type of Lighting at Main Street Section 2: Central Segment

HOOSIER HEARTLAND HIGHWAY Thank You For Coming Questions Contact: Aimee Kindred, Public Involvement Director Office: (317) Mobile: (317) Fax: (317)