Columbia River Lock Users Meeting Portland District Corps of Engineers August 14, 2007 US Army Corps of Engineers Portland District Portland District.

Slides:



Advertisements
Similar presentations
ISO Adult PIT Interrogation System Installations BPA Project Number July
Advertisements

Evaluate Spawning of Fall Chinook and Chum Salmon Just Below the Four Lowermost Columbia River Mainstem Dams Project PNNL.
1 Permanent International Association of Navigation Congresses - PIANC July 15, 2008 RIS - RIVERS INFORMATION SYSTEM Our Invisible Transportation Network.
US Army Corps of Engineers Budgeting Process
BUILDING STRONG ® AVIAN ABUNDANCE AND DETERRENT MEASURES AT NWW & NWP DAMS US Army Corps of Engineers BUILDING STRONG ® FPOM – Subgroup: Inland Avian WG.
SAME “Meet the Chiefs” Don Erickson, P.E., PMP
US Army Corps of Engineers BUILDING STRONG ® PNWA Conference Update COLONEL Jose Aguilar District Commander Portland District 2 October, 2014.
US Army Corps of Engineers Portland District Fiscal Year 2007 NWP Dredging Plan Including: The Columbia River Channel Improvement Project (CRCI)
BUILDING STRONG ® US Army Corps of Engineers BUILDING STRONG ® Portland & Walla Walla Districts Columbia-Snake River System Extended Navigation Lock Outage.
1 Ports and Harbors – Transitions and Challenges Ms. Doris J. Bautch Commissioner, U.S. Section of PIANC U.S. Maritime Administration Presented at the.
US Army Corps of Engineers 1 NAD-SAD FY07 Navigation Metrics PDT December 14, December 2004 North Atlantic Division – South Atlantic Division FY2007.
Washington Port Issues Washington State Freight Advisory Committee Seattle, WA December 9, 2013.
C. A. Peery, M. L. Keefer, and S. R. Lee Idaho Cooperative Fish and Wildlife Research Unit U.S. Geological Survey and Northwest Fisheries Science Center.
Channel Portfolio Tool (CPT)
Developing Navigation Performance Measures Barry Holliday Navigation Program Manager US Army Corps of Engineers Headquarters Washington, DC 14 December.
Winter Leader Conference February 4, 2009 “ Building Strong “1 The FY 2011 CW Program Mr. Pete Luisa 1 March 2010 PNWA.
US Army Corps of Engineers BUILDING STRONG ® Eastern Shore Navigation Partnership Meeting “ A Unified Voice for Navigation, Project Prioritization, and.
One Corps Serving the Armed Forces and the Nation Navigation Lock and Dam Inspection and Emergency Repairs Workshop April 2006 Mel Price – Auxiliary.
Belleville Locks & Dam Barge Accident on 6 Jan 05 John Clarkson
NAD/SAD REGIONAL DREDGING MEETING/WEDA WILMINGTON DISTRICT
Columbia Snake River System. Chart: Columbia River Channel Coalition Oregon Columbia Snake River System 110 mile 40-foot deep draft channel 30 million.
Pacific Northwest Waterways Association 2008 MID-YEAR MEETING Inland Project Report: Little Goose, Lower Monumental, the PSMP and the Five Year Funding.
US Army Corps of Engineers BUILDING STRONG ® Seattle SAME “Meet the Chiefs” COL Steve Miles, P.E., PMP 21 June, 2011.
US Army Corps of Engineers BUILDING STRONG ® Walla Walla District Small and Large Business Federal Opportunities Meet the Chiefs Workshop June 3, 2015.
SAME “Meet the Chiefs” LTC Shawn Patrick Deputy Commander
Matt Schueler Civil Project Management & Programs
Data Requirements for Asset Management Corps of Engineers Asset Risk and Reliability Workshop C Krahenbuhl and S Foltz August 2006 Alexandria, VA.
Mouth of the Columbia River Jetties Major Rehabilitation.
US Army Corps of Engineers BUILDING STRONG ® Mouth of the Columbia River (MCR) Jetties Laura Hicks Chief, Planning and Project Management Branch Pacific.
US Army Corps of Engineers BUILDING STRONG ® Portland District - Navigation Update COL Steve Miles Commander Portland District PNWA Annual Meeting 13 October.
WRRDA and WRDA: How are they different, and does it make any difference? Inland Rivers, Ports and Terminals, Inc. Tuesday, April 29, 2014 James A. Kearns.
Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency.
US ARMY CORPS OF ENGINEERS NORTHWESTEN DIVISION PORTLAND, OREGON WELCOME BY COL. FASTABEND Division Commander.
BUILDING STRONG ® PORTLAND DISTRICT 1. BUILDING STRONG ® PORTLAND DISTRICT 2 BiOp Performance Standards for Dam Passage Survival RPA RM&E Actions - Strategy.
Research and Development Inland Navigation Research Inland Waterways Conference March 7, 2007 Cincinnati, OH Program Manager: James Clausner HQ Navigation.
U.S. Army Corps of Engineers USACE Navigation Data/Information Workshop July 7, 2005 Arlene L Dietz, Director, Navigation Data Center.
USACE Northwestern Division Leadership
HQ Perspective on Asset Management – Thoughts for Coastal Structures Jim Clausner’s interpretation of Jim Walker Vision as Influenced by Sandra Knight’s.
Fiscal Year 2004 April 10, FY 2002FY 2003FY 2004 EnactedBudgetBudget COLUMBIA RIVER BASIN: Army Corps of Engineers Bureau of Land.
BUILDING STRONG SM Partnering and Coordination to Accomplish the Navigation Mission.
Glenn Vanselow Executive Director Kristin Meira Government Relations Director Heather Kenneson Communications Manager PNWA Staff Update.
National Levee Safety Act, Title IX, WRDA 2007 Update for Levee Summit Eric Halpin, P.E. Special Assistant for Dam and Levee Safety Headquarters, US Army.
U.S. Army Corps of Engineers Why Asset Management? “Short list” 1000 Coastal Structures 600 Dams 2500 Recreational Areas 250 Locks 75 Hydropower
McAlpine Lock Closure and Emergency Repairs 9-19 August 2004 Peter W. Frick, PE Lock & Dam Emergency Repairs Workshop Vicksburg, MS 19 April 2006.
One Team: Relevant, Ready, Responsive, Reliable 1 Hannibal L/D Ohio River - Quoin Block Failure 110-ft x 1200-ft Main Lock Sep & Nov 2005 Pittsburgh District.
Research and Development Inland Waterways Conference 7 March 2007 Improved Hydrodynamic Design/Detection and Evaluation of Scour at Dams John E. Hite,
One Corps Serving the Armed Forces and the Nation Mel Price Locks & Dam Miter Gate Inspections Navigation Lock and Dam Inspection and Emergency Repairs.
US Army Corps of Engineers Great Lakes & Ohio River Division US Army Corps of Engineers Great Lakes & Ohio River Division Achieving Navigation Systems.
Harbor Maintenance and Dredging: A Legislative Update CAPT Bill Diehl, USCG (Ret.), P.E. President Greater Houston Port Bureau.
Risk Analysis for Major Rehabilitation. Major Rehabilitation Background  Prior to FY 1992  Funded under Operation and Maintenance, General, Appropriation.
The Lower Mon Project William A. Karaffa, P.E. Project Manager Briefing to Waterways Association of Pittsburgh April 14, 2004.
1 An Approach to Levee Assessment and Contingency Planning Presentation to the National Waterways Conference 7 September 2006 Portland, Oregon By Rob Vining.
Mark R. Pointon Operations/Navigation COP U.S. Army Corps of Engineers Mark R. Pointon Operations/Navigation COP U.S. Army Corps of Engineers Presentation.
1 Smart Rivers Conference September 15, 2011 New Orleans, Louisiana “Status of Inland Waterways Infrastructure Funding”
US Army Corps of Engineers BUILDING STRONG ® Walla Walla District Update LTC Timothy Vail Oct 15, 2014.
Inland Navigation - A National Perspective Jim Walker USACE, Headquarters November 8, 2007.
Research and Development Corps Navigation Mission Provide safe, reliable, efficient, effective and environmentally sustainable waterborne transportation.
Lower Allegheny River Stakeholders Meeting June 15, 2006.
“If you think we’ve got problems now... and …what can we do about it” Transportation Day-Pittsburgh May 17, 2007 James R. McCarville Port of Pittsburgh.
Port of Pittsburgh Commission James R. McCarville Met Coke Conference – Pittsburgh November 2, 2010 Welcome to the Port of Pittsburgh.
US Army Corps of Engineers BUILDING STRONG ® Inner Harbor Navigation Canal Lock 2016 Dewatering Marine Industry Day USACE - New Orleans District 20 May.
US Army Corps of Engineers BUILDING STRONG ® 1 Inland Marine Transportation System Capital Investment Strategy Jeanine Hoey, PE, PMP Program Manager 15.
DTU A VISION OF SUPPORTING NEUTRON CHOPPER ESS PT 1 - BUNKER SYSTEMS Discussion Document.
Infrastructure, Innovation and Standardization
PIANC Work Group SMART Rivers 2017
Ouachita/Black Rivers Lock Operations
AVIAN ABUNDANCE AND DETERRENT MEASURES AT NWD DAMS
Illinois Waterway 2020 Consolidated Closure
PRESENTATION OVERVIEW
Project focus areas FY20+ Potential contract opportunities
Presentation transcript:

Columbia River Lock Users Meeting Portland District Corps of Engineers August 14, 2007 US Army Corps of Engineers Portland District Portland District

Critical Infrastructure Ranking Model For the Columbia – Snake River Waterways Transportation System Laura Hicks, Chief Planning Branch August 14, 2007

Three Major Rehab Studies Underway Columbia/Snake System MCR Jetties 1,800 feet lost on North Jetty and 5,000 feet lost on South Jetty Lower Monumental Downstream lift gate John Day Horizontal cracking on monolith bases

Our Navigation System  Uniqueness of the system and national metrics  OMBill Metric of $/tons  Multipurpose projects  Number 1 national export system for grain  System reliability is critical to users  Transportation of juvenile salmon

Budgeting Concerns  MVD ranking system’s main performance measures are commercial tonnage and outage time –metrics not very applicable to Columbia-Snake River System

Logic Diagram Columbia/Snake System

 Four broad ranking categories relate roughly to 4 FY08 funding increments and similar to other river system approach  Decision points evolved from discussions with the Operating Projects as well as internal team discussions  Safety and Reliability were determined to be the most critical when evaluating a budget item  Some adverse results not immediate (i.e., eventual dredging shutdowns to due loss of disposal site because of environmental non-compliance)  Found need to add ‘Essential Information Requirement’ to address items considered critical but ranked lower than critical in original diagram – MCR jetty monitoring, Dam Safety monitoring, hydrographic condition surveys all moved to ‘Urgent & Compelling’ based on results of applying updated logic diagram Logic Diagram Process Columbia/Snake System

Columbia/Snake System Results  FY08 rankings compared to FY09 logic diagram results  Mostly consistent  Rehab reports ranked higher  Some (mostly smaller $) maintenance items ranked lower  Urgent and Compelling  Fairly Consistent with EC guidance for level 1 funding

NAVIGATION Columbia/Snake

Urgent and Compelling  Channel River Channel Improvements Project FY08, and FY09  Lower Monumental Downstream Gate - interim repairs FY08, and FY09  Lower Monumental Major Rehab FY08, FY09, and FY10

Critical  MCR Major Rehab 08, 09, 10, 11, 12  Bonneville Dam  Swing Bridge Bearing Replacement 08, 09, 10, 11, 12  Tainter Valve Repair 08, 09, 10, 11, 12  Remove Upstream Debris 08, 09, 10, 11, 12  Navlock Chamber #1 Decommissioning 08, 09, 10, 11, 12  The Dalles Dam  North Downstream Gates Pintel Bearing Replacement 08  Upstream Gate Cables 08  Miter Gate Gear Boxes 09, 10  Tainter Valve Repairs 09, 10, 11  Valve Repair 09, 10, 11, 12

Critical  John Day Dam  E&D for Monolith Structural Repair 08, 09, 10, 11, 12  John DayMajor Rehab 08, 09, 10, 11, 12  Interim Tainter Valve Repairs 09, 10  Tainter Valve Repair 10, 11, 12  McNary Dam  HHS Inspections 08, 09, 10, 11, 12  Ice Harbor Dam  PSMP 08, 09, 10, 11, 12  HHS Inspections 08, 09, 10, 11, 12

Critical  Little Goose Dam  PSMP 08, 09, 10, 11, 12  HHS Inspections 08, 09, 10, 11, 12  Lower Monumental Dam  PSMP 08, 09, 10, 11, 12  HHS Inspections 08, 09, 10, 11, 12  Lower Granite Dam  PSMP 08, 09, 10, 11, 12

The Dalles Navigation Lock Miter Gate Pintle Repair US Army Corps of Engineers Portland District Portland District Lance A. Helwig, P.E. Project Manager Pintle

What’s the problem?  March 07 lock outage (14 d)  Cracks in both miter gates near pintle, north gate worse  Lower 30’ not mitering  Undesirable load path  Performed temporary weld repairs  May 07 – current  Vibrations & shock loading  Monitoring situation (visual)  Did cracks reopen? Propagated?  Did bolts shear off again (2005)?  Lower Granite (NWW)

What needs to be done now?  Visual inspection of pintle area (diving/submersible won’t work)  Install instruments, strain gages & accelerometers  Lock outage  25 Oct (12 hr), sweep sills  29 Oct – 5 Nov (7d)  Objectives  Possible minor repairs  Collect data for interim repair in Mar 08  Ensure gate safe for continued use  Develop contingency plans (as appropriate)

What’s the overall plan? Phase/ActivityDateComments Temporary RepairsMar 07Done Install instruments + monitoring 29 Oct – 5 Nov 077d lock outage Interim RepairsMar 08Target repairs for scheduled 14d lock outage Visual inspectionSummer/Fall 087d lock outage, if necessary Design permanent repairs & new pintle assembly 2009Developing scope Final repairsFeb/Mar 2010Extended outage likely (30d) ($3M - $5M)

On-going Challenges  Currently blind (underwater), need instruments  Funding: new problem, not part of 08 budget  Unscheduled outages  impacts to river users  Commo Plan, need to work w/ industry & stakeholders (periodic updates)  Upstream lock gate  Vibrating  Investigating problem

The Dalles Navigation Lock Miter Gate Pintle Repair US Army Corps of Engineers Portland District Portland District

US Army Corps of Engineers Portland District Portland District The Dalles Dam Spillwall Extension Update Bay 8/9 Wall Bay 6/7 Wall

TDA Spillwall Extension Update  Mar 07: invited river users to ERDC  Reps from Shaver, Tidewater and Foss  Bay 6/7 wall – no navigation impacts  Jul 07: wall moved to Bay 8/9  reduced gas  Sep/Oct 07: model 8/9 wall  ERDC (H. Parks) run model tug  Expects no impacts to navigation  Corps will send out model results to river users  Determine if river user trip is necessary  Spillwall schedule:  Complete P&S:May 08  Award contract:Jul 08  Complete construction:Apr 09

John Day Major Rehabilitation Mark Dasso, Project Manager Doug Clarke, Chief, Progams and Project Management

Movement During Lockage 0.7” 0.5” Monolith Cracks

Leaking lift lines M27M29 North Wall Monolith Cracking

2003 Emergency Upstream Gate Repair, $4M

2004 Emergency Lock Repair, $16M

2007 Downstream Gate Wire Rope Replacement, $1 M

Future Tainter Valve Replacement

SPRA Recommendations John Day Lock and Dam  Perform a Major Rehab Study asap  3-5 Years, $6M Study  Design / P&S, 1-3 Years  Implement Repairs, 3-5 Years  Funding from the Dam Safety “Wedge”  Scoping to begin in 4 th qtr FY07  $1M Funding in $FY08

 Commercial Waterborne traffic (tonnage & system ton-miles) Coos Bay, Columbia – Snake System  Risk & Reliability of System  Avg. O&M $ per Ton  Other Considerations: Refuge & Safety, Subsistence, National security, Commercial Fishing. All the rest  Remaining Items – R&D, waterborne performance data  Remarks, Purpose, Consequences FY 07 & 08 Federal Budget Justifications Key Factors in Navigation O&M Budget Ranking