1 Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,

Slides:



Advertisements
Similar presentations
Southwest Rhode Island Transmission Supply Study Long Term Needs and Solutions.
Advertisements

Sistan & Balouchestan Electric Power Distribution Company
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
March 6, 2008 Technical Advisory Committee Luminant Energy & Oncor Tyler Grande Autotransformer Addition and 138 kV Line Upgrade Project Jay Teixeira Manager,
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Regional Planning Group Project
Entergy Transmission Planning Summit New Orleans, LA July 10, 2003
La Crosse 161 kV Capacitor Addition Northern MAPP Subregional Planning Group April 3, 2007 Daniel Kline.
Entergy Louisiana, LLC (North) 2010 to 2012 Draft Construction Plan
1 Entergy Louisiana, Inc. (North) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Eau Claire Area Study Northern MAPP Subregional Planning Group January 11, 2007 Daniel Kline.
Cleco Transmission Planning Summit 2011 Coughlin Transmission Operations Center April 15, :00 – 11:00am.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
1 1 Substation Asset Strategy Kevin Dasso, Senior Director Engineering and Operations IEEE/PES Annual Substations Committee Meeting April 7, 2008.
Entergy Transmission Planning Summit New Orleans, LA July 31, 2007
ICT 2011 Reliability Assessment and Construction Plan Evaluation Entergy Transmission Summit August 11, 2010 Sheraton New Orleans, Louisiana.
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
© 2000 PACIFICORP | PAGE 1 WYOMING WEST AREA STUDY DECEMBER 2013 Seongtae Kim/Jeremy Viula.
1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit.
Xcel Energy Smaller Scale Transmission Projects Northern MAPP Subregional Planning Group April 3, 2007 Srinivas Vemuri, Jason Standing, and Daniel Kline.
New Richmond Load Serving Study Northern MAPP Subregional Planning Group August 16, 2006 Daniel Kline.
Entergy Transmission Planning Summit New Orleans, LA July 8, 2004
George Bartlett Director, Transmission Operations Economic Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting December 16, 2009.
1 Update on the 2006 Transmission Study LPSC B&E Meeting Baton Rouge, LA November 29, 2006.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Transmission Planning Summit.
1 Entergy Texas, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
Lyndonville Electric Department Feasibility Analysis Review December 2,
1 Entergy Arkansas, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Aug 17, 2012 RPG Meeting KEC & MEC – Load Addition Project – ERCOT Independent Review Ehsan Ur Rehman Planning Engineer ERCOT.
ISTEP Phase II Final Report Summary LTTIWG Meeting – January 27, 2009 Douglas Bowman, PE Lead Engineer, ICT Planning
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
Local Area Study Local Area Study Mitigation Plan Update and Uncertainty Scenarios
1 Stability Issues in Entergy System Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
1 Entergy Gulf States Louisiana, L.L.C. Proposed Transmission Reliability Projects.
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
1 Entergy Louisiana, Inc. (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
1 Entergy Louisiana, Inc. (South) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
1 Entergy Gulf States, Inc. (Louisiana) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting November 19, 2008.
1 Entergy Louisiana, Inc. (North) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
1 New Orleans, LA July 31, 2007 Randy Helmick Vice President, Transmission Business Entergy Transmission Planning Summit.
Glades Electric Cooperative Infrastructure Miles of Line 2,213  Overhead Dist.2,180  UndergroundDist. 33  Transmission 87 16,402 meters Average 7.
Transmission Capital Project Updates. Transmission Expansion Plan Sigurd to Red Butte 345 kV line in-service May, 2015 Permitting activities continue.
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.
1 Entergy Transmission Planning Summit New Orleans, LA July 10, 2003 Generation and Transmission Development in the Southeastern United States.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
2006 Preliminary Reliability Study Results Bryan Guy September 7, 2006.
Presentation For PSAST May 14, Outline Most Limiting N-1-X Events Voltage Limitations For Loss of Three Terminal Monroe- Echo Lake 500kV and Chief.
1 Entergy Gulf States, Inc. (Texas) Approved & Proposed Transmission Reliability Projects Entergy/ETEC Subcommittee Meeting The Woodlands, TX November.
1 New Orleans, LA July 29, 2008 Randy Helmick Vice President, Transmission Entergy Services Inc. Entergy Transmission Planning Summit.
Barrilla Junction Area Transmission Improvements Project
Rocky Mountain Power Five Year Study Findings & Kick Off Meeting
Pacific Power Seismic Preparedness Update
Strategic Plan and Economic Upgrade Process
Presentation transcript:

1 Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008

2 ELL-South/ENOI Transmission Reliability Projects DSG: Phase III (Postponed) Improve ASI Capability: Phase II- Panama-Dutch Bayou Phase III- Coly-Vignes Conway-Bagatelle ELL-South Loblolly-Hammond: Build 230kV line SELA Phase #2 Peters Rd-Oakville : Build 230kV line & Station SELA Phase #3 Oakville-Alliance: Build 230kV line & Auto Houma: Install Cap Bank Paterson: Restore 4 breakers

3 Paterson: Restore 4 Breakers Scenario: Paterson substation was flooded during Hurricane Katrina resulting in all major transmission equipment being damaged. Prior to Katrina, Paterson 115kV bus terminated four 115kv transmission lines and operated as a hub for the transmission system in the New Orleans area. Presently, the Paterson 115kV bus has been temporarily restored to operate in a split, east / west bus configuration. The east bus is in series with the Chalmette 115kV and the Sherwood Forest 115kV substations. The west bus is in series with the Claiborne 115kV and the Pontchartrain Park 115kV substations. Various single contingencies in the New Orleans area now could result in overloads on portions of this west bus circuit. Recommended Solution: Re-build the Paterson 115kV substation to terminate four 115kV transmission lines from Pontchartrain Park, Sherwood Forest, Chalmette and Claiborne. The bus configuration should be configured in a double bus with shared breaker configuration (breaker and a 1/2). This arrangement will allow for station expansion, including power transformer additions and potentially the addition of a 230/115kV auto transformer as system conditions dictate. Proposed In-Service Date: 2008 Estimated Cost: $3 MM ENOI

4 Paterson: Restore 4 Circuit Breakers Restore Breakers

5 Houma: Install Capacitor Bank Scenario: This project was identified as required as part of a transmission service request Recommended Solution: Install a 40MVAr capacitor bank at Houma 115kV substation. Proposed In-Service Date: 2008 Estimated Cost: $850 k ELL-South

6 Houma: Install Capacitor Bank Install Cap Bank

7 Loblolly-Hammond: Construct 230 kV Substation and Line Scenario: Entergy’s transmission system north of Lake Pontchartrain is primarily supported from the ELL 230kV system between Willow Glen and Waterford. –Loss of the Franklin-McKnight 500kV line, or certain other transmission contingencies, result in overloads to occur on the underlying transmission system, primarily on the Gypsy-Madisonville 230kV line. –Adding another 230kV source from a location north of Willow Glen reduces loading on the existing system and improves load serving capability north of Lake Pontchartrain and into south Mississippi. Recommended Solution: Construct 230 kV line from Loblolly to Hammond using existing Coly–Hammond 69 kV line (constructed for 230kV). Proposed In-Service Date: 2012 Estimated Cost: $75 MM ELL-South

8 McKnight To Franklin To SOCO’s Plant Daniel To Coly To Fancy Point Loblolly Loblolly-Hammond: Build 230 kV Line Construct new 230kV line ELL-South / EGSI-LA Coly

9 Scenario: When generation in the Amite South area is low, loss of the Waterford–Willow Glen 500 kV line is the most severe contingency that establishes the Amite South Import (ASI) capability. The ASI capability improved to approximately 2,450 MW upon completion of Phase 1 of the ASI Improvement Plan (Conway-Panama) in Phase 2 (Panama-Dutch Bayou) and Phase 3 (Coly-Vignes, Conway-Bagatelle) were expected to provide economic benefits and were to be completed by 2007 prior to Hurricane Katrina. Post Hurricane Katrina and the subsequent loss of load within southeast LA, Phases 2 and 3 were determined to be needed for reliability by 2015 or by 2010 for economics. Based on the 2006 Transmission Study, Entergy determined that accelerating Phases 2 & 3 could yield economic benefits sufficient enough to advance the in-service dates to earlier than Recommended Solution: Construction of Phases 2 & 3. Proposed In-Service Date: 2009 (Phases 2 & 3) Estimated Project Costs: Phase 2: $38 MM Phase 3: $20 MM ASI Improvement Plan - Phases 2 & 3 ELL-South / EGSI-LA

10 Panama ELL-South ASI Improvement Plan - Phase 2 Build 230kV line

11 Coly Vignes Panama ELL-South / EGSI-LA ASI Improvement Plan - Phase 3 Upgrade 230kV line

12 Scenario: The primary transmission sources to lower Lafourche, Lower Jefferson, and Plaquemines Parishes are the Ninemile and Valentine substations. Although lower Plaquemines Parish experienced heavy damage during Hurricane Katrina, it is expected that oil refining and pumping facilities in the area will be restored. Additionally, upper Plaquemines Parish, including Belle Chasse and the Naval Air Support facility, is experiencing growth. For the contingency loss of the Ninemile-Barataria 115kV or the Valentine-Clovelly 115kV lines, potential low voltages and line overloads exists. Recommended Solution: Peters Road-Oakville 230kV –Build a new 230kV substation at Oakville and a new radial 230kV line from Peters Road to Oakville Substation. –Proposed In-Service Date: 2010 –Estimated Cost: $21.3 MM Oakville-Alliance 230 kV –Construct a new 230kV transmission line from Oakville substation to Alliance substation. Add a 150MVA 230/115kV auto at Alliance substation. This project also provides support for the Fourchon area. –Proposed In-Service Date: 2010 –Estimated Cost: $35 MM Southeast Louisiana Coastal Improvement Plan: Construct New Peters Road-Oakville-Alliance 230 kV Line ELL-South

13 ELL-South Peters Road-Oakville 230kV: Build new line and substation Oakville-Alliance 230 kV: Build new line Build 230kV Line & Auto Peters Rd. Oakville Build 230kV Line & Auto Build 230kV Line & Sub

14 ELL-South and ENOI Identified Target Areas Beyond 2011 Paterson: Install 230/115kV auto Belle Point – Little Gypsy: Reconductor 230kV Line DSG: Phase III Napoleonville – Add capacitor bank