MICE Collaboration meeting RAL 21 – 24 Oct 2005 Summary of Design & Safety review progress By Wing Lau – Oxford University.

Slides:



Advertisements
Similar presentations
TURANDOT – Puccini Luciano Pavarotti Sincro No one sleeps, no one sleeps... Nessun dorma, nessun dorma.
Advertisements

1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
Action Who Progress made status Implement central repository for drawings -- need detector information to add to official drawing WL Progress on-going.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module work group report Wing Lau – Oxford.
Cooling Channel Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICE Collaboration.
March 2003 Paul Drumm MICE Collaboration Meeting, CERN 1 Beam Line & Installation Plans Paul Drumm CLRC Rutherford Appleton Laboratory.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
paul drumm; 3rd December 2004; AFC MM 1 Cost & Schedule Review I Terms of reference: –To review the Cost and schedule of the MICE Muon beam –To review.
Report from meeting Hydrogen system operation from cryocooler and level control Cryocoolers for MICE Tom Bradshaw Elwyn Baynham Yury Ivanyushenkov Rutherford.
MICE Project Report Paul Drumm ~ Sunday August 1 st 2004.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 MICE Project Report, paul drumm, 9 march 2005 CM Highlights & Tasks… –Tracker base line – scintillating fibres – performance validated –TOF performance.
1 MICE Project Board Schedule and milestones Reconstructing the schedule Present status Monitoring and feedback Key schedule drivers and concerns Andy.
Paul drumm; 3rd December 2004; AFC MM 1 Why? Goal: Ultimate (CCLRC defined) Safety & Design Review –How do we get there? We need a Process –What is needed?
A reminder of the outstanding action list:- Implement central repository for drawings – need detector information to add to official drawing Instrumentation.
MICE AFC Group phone conference on 27 January 2005 AFC module progress By Wing Lau, Oxford.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
MICE Collaboration Meeting Harbin, China 13 – 17 January 2009 Integration Issues By Wing Lau, Oxford University.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
Main progress on Design & Safety Review: EmCAL -- Received the revised TRD write up from Ludovico Design & Safety Audit sheets need to be revised to correspond.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Project manager report paul drumm CM16 October 2006.
MICE Collaboration Meeting Frascati 26 – 29 June 2005 Work Group report On Design & Safety Review.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
1 Preparation of the hydrogen test system Yury Ivanyushenkov for Elwyn Baynham, Tom Bradshaw, Mike Courthold, Matthew Hills and Tony Jones CCLRC Technology.
Goals & Status MICE CM 33 Thanks go out to the organizers: Paul Soler, Ryan Bayes and Valerie Flood.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
MICE Collaboration meeting (CM20) At RAL 10 – 13 Feb 2008 AFC Magnet – Status and Progress W. Lau, Oxford University.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Hydrogen Delivery System Schedule MICE Schedule Review 23 rd -25 th May 2011 M Hills STFC.
1 MICE Collaboration meeting at Berkeley 9 – 12 February 2005 Integrated Design & Safety Review Presented by Wing Lau & Paul Drumm.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
Design & Safety Review Work Group meeting 10 March 2005 Progress update Wing Lau, Oxford.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
MICE CMPB Alain Blondel 1 Highlights on MICE.
1 MICE PID Group Meeting 11 May 2005 Update on Design & Safety Review Presented by Wing Lau.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
MICE – Video conference Alain Blondel, 17 December   MICE selected NEWS: Future meetings Safety review Study of controls Gateway I & Toward Gateway.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Status of infrastructure MICE Collaboration Meeting, Frascati, June 26-29, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation.
Progress on Hydrogen R&D System Yury Ivanyushenkov on behalf of Elwyn Baynham, Tom Bradshaw, Mike Courthold Matthew Hills, Tony Jones MICE Collaboration.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 MICE UK meeting at RAL 05 May 2005 Integrated Design & Safety Review Presented by.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE absorbers work package MPB – 27/10/15 Mike Courthold Mark Tucker Phil Warburton Steve Watson.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
1 paul drumm; Date; Title …project report …more comments paul drumm february 2005.
Status of the MICE Construction Project
MICE CM31 Schedule summary
Spectrometer Solenoid Fabrication Status and Schedule
Presentation transcript:

MICE Collaboration meeting RAL 21 – 24 Oct 2005 Summary of Design & Safety review progress By Wing Lau – Oxford University

Progress on the following items: Phase 1 LH2 system R&D LH2 Absorber R&D Fibre Tracker Beamline Target Magnetic Shielding Diffuser Tracker solenoid Hall Infrastructure Cherenkov 1 & 2 TOF MuCAL Phase 2 RFCC AFC Radiation Shield Others

The Hydrogen delivery system R & D We have made excellent progress. This has already been reported in depth in the previous plenary session. The order for the Hydride Bed, though not placed, is in advanced stage of contract negotiation. The dry run revealed the need for a few minor revisions, but we do not expect any show-stopper there. TRD is being revised and will be available before mid-November The external review will take place on the 21 st and 22 nd of November. I believe Tom & Yury’s team is well prepared for that. Provided it passes the external review and the Hydride Bed supplier honours the contract, the R&D work will commence in mid-2006

Absorber R&D Shigeru has continued to make good progress in bringing the hardware together. Although the absorber R&D is not subject to further Safety review (preliminary review already done), we need to review the suitability of the instrumentations which will be applied to the AFC Absorber system Thermal performance; cool down procedures and heat leak data will be used in the final benchmarking of our Absorber design For this reason a Design review is appropriate. Action: Shigeru to submit TRD when R&D results become available (?)

Tracker Solenoid Conductors: Specification is written. Reviewed by the TB. Provided no further changes to the specification, it can go out for tender / price quotation. The rest of the solenoid: Draft TRD is written & submitted – need to revise to reflect small change in coil thickness; Audit spread sheets to be done – this is now urgent This must be completed by mid November for the review to be done before procurement starts Action: Mike Green and Steve Virostek to confirm TRD status as well as completing the Audit Spread sheets

Fibre Tracker TRD and Audit Spread sheets done some time ago. Ghislain is leading the independent review It was reported that significant design changes have been made since the TRD was written. Consequently the Audit Spread sheets are now out of date and need to be revised. The request for document update has been made to Ken Long. The team is waiting for a revised set of documents before continuing with the review Action: Ken Long to respond ASAP

Target TRD preparation is underway Plan to install target prototype in ISIS by end of this year; ISIS is likely to be involved in the review of the design before granting permission to fit target on the Beam Pipe We urgently need to have the TRD written by mid- November Action: Chris Booth to prepare documents urgently

Beamline; Iron Shield; Cherenkov2; TOF & MuCAL; PID support TRD and Audit Spread Sheets have been written awaiting for review assignment The issue: Beamline – likely to be moved by 2m? Is it worth doing the review now? Cherenkov 2 – funding is still unknown. Should review go ahead anyway? PID support final design awaits decision on Cherenkov 2 Action: Wing Lau, Paul Drumm and PID group to tie up the loose ends

Hall Infrastructure TRD is not finalised – uncertainty on the final positions of a number of components; Audit Spread sheet not submitted Action: Yury to advise realistic dates for document submission based on Hall construction schedule

Diffuser; Cherenkov 1 TRD not yet written Reason: Diffuser interchange requirements still to be specified. This may affect the final design; Cherenkov 1 design is not ready. Action: Advice from Alain on Diffuser interchange requirements; Mississippi to submit TRD and Audit Spread sheets once design is finalised

Summary Considerable effort was spent in making sure that the preparation for the Hydrogen System R&D design & safety is ready for the November review. We are almost there, and we would like to thank Elwyn, Tom, Yury and the team for their effort; Progress has been delayed by the continuing update of a number of designs, consequently invalidating the TRD and Audit spread sheets already submitted to this work group. Unfortunately the search for better physics makes design changes inevitable. For some components, imposing a design freeze may not be an option. We need to review our working method to overcome this issue.

Nessun dorma!... Nessun dorma!... Tu pure, o Principessa, nella tua fredda stanza guardi le stelle che tremano d'amore e di speranza! Ma il mio mistero è chiuso in me, il nome mio nessun saprà! No, no, sulla tua bocca lo dirò, quando la luce splenderà! Ed il mio bacio scoglierà il silenzio che ti fa mia! Coro donne: Il nome suo nessun saprà... E noi dovrem ahimè, morir, morir!... Il Principe: Dilegua, o notte! tramontate, stelle! Tramontate, stelle! All'alba vincerò! Vincerò! Vincerò! From Puccini’s opera -- Turandot No one shall sleep Let no one sleep May no one sleep Action: until the job is done……