Hamid Shoaee LCLS FAC Review – October 2007 1 Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.

Slides:



Advertisements
Similar presentations
XTCAV X-Band Transverse Deflecting Cavity Project Overview Patrick Krejcik Yuantao Ding, Joe Frisch.
Advertisements

Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Joe Frisch LCLS FAC Oct. 30, Linac/BC2 Commissioning (Dec through Sep., 2008) J. Frisch, et al. LCLS FAC Meeting.
Ernest Williams FAC November 2008 Control Systems Software Section 1 Controls System Installation Status Ernest Williams for Controls Department.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
S. Smith LCLS Facility Advisory April 16, BPMs and Toroids Facility Advisory Committee April 16, 2007 System overview.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Hamid Shoaee Control System Installation 3/16/ Downtime Readiness Review Hamid Shoaee For LCLS Controls Group.
Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
Patrick Krejcik LCLS April 16-17, 2007 Breakout Session: Controls Controls Commissioning Experience.
P. Emma, SLACLCLS Commissioning – Sep. 22, 2004 Linac Commissioning P. Emma LCLS Commissioning Workshop, SLAC Sep , 2004 LCLS.
LTU & Electron Beam Dump Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center LCLS Technical Design.
Hamid Shoaee High Level Physics 20 April 2006 High Level Physics Applications Update on Plans, New Directions Fairley,
P. Emma, SLACLCLS FAC Meeting - April 29, 2004 Linac Physics, Diagnostics, and Commissioning Strategy P. Emma LCLS FAC Meeting April 29, 2004 LCLS.
Eric Bong LCLS FAC Injector-Linac October 27, 2005 Injector Design / Diagnostics / Gun & Linac RF Design E. Bong LCLS FAC.
Paul Emma LCLS Commissioning Status Nov. 11, 2008 SLAC National Accelerator Laboratory 1 LCLS Commissioning Status P. Emma for The.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
James Welch October 29, 2007 Injector Commissioning Injector Commissioning Results presentated to the Facilities Advisory Committee,
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
E. Bong, SLACLCLS FAC Meeting - April 29, 2004 Linac Overview E. Bong LCLS FAC Meeting April 29, 2004 LCLS.
Hamid Shoaee LCLS Facility Advisory Committee 20 April Plans for 2006 Installation April 20, 2006 Injector commissioning.
Oct. 30, 2007 LCLS FAC D. Fairley MATLAB Feedback Phase II Commissioning.
Henrik Loos High Level 17 June 2008 High Level Physics Applications for LCLS Commissioning Henrik Loos.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
Diane Fairley High Level October High Level Applications FAC Review October 12, 2006 High Level Applications.
Hamid Shoaee LCLS Control April 20, 2006 LCLS Control System Organization & Integration with the rest of the lab, Accelerator.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
Hamid Shoaee Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory Controls Department LCLS Maintenance.
Hamid Shoaee LCLS Control April 20, 2006 LCLS Control System Controls Organization Overview A Progress Report Hamid Shoaee.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
SPPS, Beam stability and pulse-to-pulse jitter Patrick Krejcik For the SPPS collaboration Zeuthen Workshop on Start-to-End Simulations of X-ray FEL’s August.
LCLS Accelerator SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m  rf   25° Linac-2 L  330 m  rf   41° Linac-3 L  550 m  rf  0°
Henrik Loos LCLS 6 February 2009 SLAC National Accelerator Laboratory High Level Physics Applications for LCLS Commissioning.
Diagnostics Overview for the LCLS Presented by Josef Frisch For the LCLS ANL / LBNL / LLNL / SLAC.
Hamid Shoaee Control LCLS ARR Oct 31, LCLS Accelerator Readiness Review Control System for Injector Commissioning.
LCLS Control Group FAC – 06 Installation October 27/28, Plans for 2006 Installation October 27, 2005 Installation.
Patrick’s Updates - 8/30/11 (one slide for each of the following) 1.XTCAV Project 2.ASTA Gun Test Facility Instrumentation & Controls 3.Fast wire scanner.
Henrik Loos LCLS ICW October 2006 Diagnostics in the LCLS LCLS Injector Commissioning Workshop October 9-11, 2006 Henrik.
Franz-Josef Decker 14-Dec-2011 CSR is a big deal limiting performance Tolerance studies beforehand helped a lot Tor’s List Software adaptability helped.
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
LCLS Commissioning & Operations High Level Software
LCLS Commissioning & Operations High Level Software
LCLS Linac Update Brief Overview L1 & BC1 Progress LTU & E-Dump Status Continuing Resolution Impact.
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LCLS Injector Diagnostics
Linac/BC1 Commissioning P
Electron Beam Systems ETC and Methodology
LCLS Linac Overview E. Bong Lehman Review August 10, 2004
LCLS Commissioning P. Emma, et al
High Level Physics Applications for LCLS Commissioning
Linac Physics, Diagnostics, and Commissioning Strategy P
Undulator Cavity BPM System Status
Diagnostics RF and Feedback
Linac Diagnostics Commissioning Experience
LCLS Injector Commissioning P
2007 Downtime Controls Installation
E-Beams Systems Manager
Control System Overview Hamid Shoaee LCLS Control System Manager
Diagnostics overview Beam profile monitors Cherenkov radiators Summary
Injector Diagnostics Status
Injector/Linac Design Status C. E
LCLS e- Beams System Overview
LCLS Control System Personnel Linac & BC2 Controls progress
LCLS e- Beams Systems Manager
Control System Overview Hamid Shoaee LCLS Control System Manager
Presentation transcript:

Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support Linac/BC2 Controls installation status Plans for the remainder of e- Controls Summary

Hamid Shoaee LCLS FAC Review – October Accomplishments in the past six months Providing ongoing support for the injector operation New Software, as well as upgrades & enhancements Commissioning of additional controls subsystems Field installation of large amount of cable plant, networking, racks & electronics for BC2/Linac Development of detailed plans for LTU, Undulator and E-Dump control system installation Coordination of undulator control with ANL Continuing the development of next generation applications software & feedback system

Hamid Shoaee LCLS FAC Review – October Continuing support for the Injector Controls Ernest Williams heading software engineering including EPICS system “Software Day” concept proved very productive Commissioning of new applications software such the bunch length measurement, MATLAB based feedback system Enhancement and troubleshooting of released software Commissioning of additional diagnostics

Hamid Shoaee LCLS FAC Review – October The Toroid charge monitoring system was successfully commissioned

Absolute charge measurement with Toroids Mean ratio of Toroid to BPM charge = 1.45

Hamid Shoaee LCLS FAC Review – October Laser Systems Image Acquisition and Steering Feedback PULNIX 8-bit 640x fps CameraLink Used for centroid feedback

Hamid Shoaee LCLS FAC Review – October Synchronous Acquisition to measure Resolution Simultaneous measurement of all BPMs Fitted beam position versus measured yields resolution 2 microns at 400 pC S. Smith et al.

Hamid Shoaee LCLS FAC Review – October SCP orbit display of Injector BPMS (EPICS) and SLC BPMS on the same pulse

Hamid Shoaee LCLS FAC Review – October BC1 Chicane OTR Screen commissioned 1  m thick Al foil

Hamid Shoaee LCLS FAC Review – October Wire Scanners Direction of motion Based on existing SLAC mechanical design (E. Bong) Updated EPICS controls interface Pulse-by-pulse compensation of bunch charge and trajectory jitter X U Y

Hamid Shoaee LCLS FAC Review – October Compressor chicane Coh. Diffraction Radiation + Coh. Synchrotron Radiation + Coh. Edge radiation Annular mirror collecting mirror vacuum mirror External optics Filters & Detectors Electronics and Data acquisition for Bunch Length Monitor System design by J. Frisch and H. Loos

Hamid Shoaee LCLS FAC Review – October Longitudinal Feedback System Commissioned

Hamid Shoaee LCLS FAC Review – October Save and Restore Application (phase 1)

Hamid Shoaee LCLS FAC Review – October Orbit data plot Model control Beam-line selector “Launcher” for Other programs Online Model Applications

Applications provided in MATLAB Image Management Bunch Length Measurement Emittance and Energy Application

Hamid Shoaee LCLS FAC Review – October LLRF Work Completed since last review All remaining stations in the injector and L1 were built, programmed and installed: Transverse cavity in L0 Phase cavity in L0 (alternative input source for laser phase feedback) Phase cavity in L1 (diagnostic, no feedback) Klystron phase & amplitude detectors (PAD) at 20-5, 20-6, 20-7, 20-8, 21-1 S-band and 21-2 X- band Laser phase feedback enhancements

Hamid Shoaee LCLS FAC Review – October SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m Linac-2 L  330 m Linac-3 L  550 m BC1 L  6 m BC2 L  22 m DL2 L =275 m ‘Wall region’ undulator L =130 m 6 MeV 135 MeV 250 MeV4.30 GeV13.6 GeV Linac-X L =0.6 m 21-1 b,c,d...existing linac L0-a,b rf gun 21-3b 24-6d X 25-1a 30-8c Operational 2007 down, Sept-Nov BC2, Linac Controls System Installation 2008 INJECTORLINAC/BC2 LTU/DUMPUNDULATOR

Hamid Shoaee LCLS FAC Review – October LCLS Installation and Commissioning Time-Line S S O O N N D D J J F F M M A A M M J J J J A A S S O O N N D D J J F F M M A A M M J J J J Linac/BC2 Controls Install Linac/BC2 Commissioning LTU/Und/Dump Controls Install LTU/Und Commissioning A A S S O O N N D D PPS X-ray tunnel/FEH Install CD-4 (7/30/10) PPS FEE/NEH Commissioning Tunnel/FEH Commissioning J J F F M M A A M M FEE/NEH Install

Hamid Shoaee LCLS FAC Review – October Linac & BC2 Controls Installation Detailed plans were in place Feb-March 2007 The scope includes pulsed horizontal dipole magnet Adding new magnets including pulsed horizontal dipole magnet Adding BPM, x-collimator, OTR screen Extending the new timing system Safety systems (MPS, BCS) BC2 installation, similar scope to BC1 Very little engineering development The biggest challenge has been meeting the schedule

Hamid Shoaee LCLS FAC Review – October Linac & BC2 Controls Installation proceeding close to original schedule Controls Check out to start 11/7/07

Hamid Shoaee LCLS FAC Review – October Cable plant installations are nearing completion

Hamid Shoaee LCLS FAC Review – October Electronics Racks have been installed in the field

Hamid Shoaee LCLS FAC Review – October BC2, Linac Controls checkout to start next week All vacuum control equipment bench tested and loaded. All network Switches, terminal servers, patch panels in place..

Hamid Shoaee LCLS FAC Review – October Undulator Control Close collaboration between SLAC and ANL Separate weekly video conferences on Controls, BPM, BLM (Beam Loss Monitor) Participation by SLAC personnel in planning, coordination and testing at ANL Cavity BPM tests successful, meet sped Undulator motion control FDR in 2 weeks Have a design for BLM with schedule for development

Hamid Shoaee LCLS FAC Review – October First beam tests of Undulator Cavity BPM at ANL (R. Lill) undulator Cavity BPM

Hamid Shoaee LCLS FAC Review – October m vertical bends horizontal bends emittance diagnostic and collimation undulator dumpline BSY Controls for LTU, Undulator, E-dump

Hamid Shoaee LCLS FAC Review – October Controls for LTU, Undulator, E-dump Identification of cable plant is nearing completion and documented in CAPTAR We have developed electronics rack profiles for nearly all systems We have an installation plan which is being integrated with the over all 2008 schedule The challenge is coordination with other installations

Hamid Shoaee LCLS FAC Review – October Developing detailed schedule for 2008 Controls installation

Hamid Shoaee LCLS FAC Review – October Plans for the Next Six Months Complete the BC2 installation and support the commissioning effort Develop detailed plans for LTU, Undulator installation Make major progress on the next generation high level applications software

Hamid Shoaee LCLS FAC Review – October Conclusions We have been providing ongoing support for the injector controls The commissioning experience and the collaboration with physicists have been very effective in refining the systems BC2/Linac Controls installation is proceeding well and close to the original schedule We are developing detailed controls installation plans for the remainder of the e- regions With the exception of a few systems, we are over the engineering curve, and the remaining challenge is maintaining the schedule