XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review1 Undulator for the LCLS project – from the prototype to the full scale.

Slides:



Advertisements
Similar presentations
ATLAS Pixel Detector February 2003 N. Hartman LBNL 1 Pixel Support Tube PRR: Assembly, Production, Schedule February 2003.
Advertisements

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 1 Undulator System Assembly, Installation, and Integration.
Magnets for the ESRF upgrade phase II
XFEL Undulator Efforts at DESY and Thoughts on LCLS-II H.-D. Nuhn June 30, 2010.
XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review1 Undulator for the LCLS project - design of the support and mover system.
XFD – XF Engineering Group October 20, 2005LCLS Undulator Alignment and Motion System1 Precision and repeatability of cam-shaft system in both directions.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Marion M. White Undulator System 07 April 2005 LCLSLCLSLCLSLCLS Undulator System Tests Marion M. White ANL-ASD-LCLS.
Apr. 16, 2007 Undulator Breakout Dean R. Walters 1 Vacuum System Undulator Vacuum System Dean R. Walters Soon-Hong Lee, James Bailey, James.
Geoff Pile LCLS Fixed support IDR 12 th January 2006 LCLS Fixed Support IDR Introduction and History Are special fixed supports needed?
Tagger and Vacuum Chamber Assembly Procedure. Preassembly of second bottom yokes and poleshoes. a) Install special support. b) Place the second bottom.
LCLS Undulators October 14, 2004 Heinz-Dieter Nuhn, SLAC / SSRL MMF Review Introduction to the LCLS Undulators Heinz-Dieter Nuhn,
David H. Dowell Injector RF Design November 3, LCLS Injector RF Gun: Design, Fabrication & Tuning Plans D. H. Dowell,
Isaac Vasserman Magnetic Measurements and Tuning 10/14/ I. Vasserman LCLS Magnetic Measurements and Tuning.
X-Ray Diagnostics for the LCLS Jan , 2004 UCLA.
Wire Position System LCLS Undulator Alignment and Motion Review, Oct. 22, Franz Peters Wire Position System The Undulator.
M. White – June 28, 2004 LCLS Requirements Meeting In a project, we live or die by the schedule. After we’re “baselined” it is our plan for what we will.
LCLS Prototype Undulator Design LCLS Prototype Undulator Design Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory.
Dean R Walters Undulator Vacuum October 12-13, 2004 Facility Advisory Committee Undulator Vacuum System/Mechanical By Dean R Walters.
Robert Ruland Installation Alignment -Magnetic Measurements – Fiducialization April 7-8, 2005 FAC Meeting 1 Installation Alignment,
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Robert Ruland MMF Introduction, Schedule, Budget October 14, 2004 MMF Review 1 MMF Introduction, Schedule, Budget Robert Ruland.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Rodd Pope, SLAC Undulator System April 20-21, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC In collaboration.
Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center LCLS Undulator Physics.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Marion M. White Undulator Prototype Status and 12 October 2004 LCLSLCLSLCLSLCLS Undulator Prototype Status and Measurement.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
J. Welch Talk MMF 10/14/04 LCLS Magnetic Measurement Facility Requirements Functional Temperature Vibration Earth's.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
LCLS-II Magnetic Structure Design Review - Conceptual Mechanical Design: Module Assembly Method Alan Black Steve Marks 7/6/11 1.
Zachary Wolf Undulator Oct 12, LCLS Undulator Tuning Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko,
TT Assembly Structure Reference-Reinforcement System: 1.Description of the system 2.Assembling Procedure 3.Production Project Board, march 2005 D.Orlandi.
DELTA Quadrant Tuning Y. Levashov, E. Reese. 2 Tolerances for prototype quadrant tuning Magnet center deviations from a nominal center line < ± 50  m.
ILC Rotating Target - Active Sliding Contact Cooling Wei Gai, Manoel Conde, Wanming Liu, Scott Doran, Vic Guarino, George Fenske (ES), Robert Erck (ES),
Magnetic Material Specification and Procurement Strategy Dawn Munson 1.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
Marion M. White Undulator System 27 October FAC LCLSLCLSLCLSLCLS Progress on the Undulator Module System Test Marion M.
LCLS Prototype Undulator Design LCLS Prototype Undulator Design Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory.
Dmitry Gudkov BE-RF-PM CLIC Module Working Group Engineering design of the adjustable supporting system for DBQ.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
X LCLS SCU NbTi Prototype Schedule Version: February 12, 2015 Update 23JUN2015 X X System complete and ready for test X System complete & tested w/Hall.
Procurement and Manufacture of LCLS Undulators FY 04 Activity: Complete design of Second Prototype Undulator This will include field control comb Procure.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
SCU 3-Lab Review Meeting, Dec. 16, 2014 SCU Presentations Today Intro. & Performance Motivations (P. Emma, SLAC, 20+5) Conceptual Cryostat Design: Option-A.
Update: Puck and Gun Magnet March 1, Magnetized Gun 2 K 2 CsSb Preparation Chamber HV Chamber.
Design and Measurement Results for the Permanent Magnet Undulators for the Linac Coherent Light Source Facility II D. Arbelaez BeMa2014, 01/02/2014.
1 Long QXF Mirror Fabrication (MQXFPM1) Rodger Bossert HiLumi-LARP Collaboration Meeting May 18-20, 2016 SLAC R. Bossert - HiLumi Collaboration Meeting.
Some Design Considerations and R &D of CEPCB Dipole Magnet
GLAST Large Area Telescope:
CHEN, Fusan KANG, Wen November 5, 2017
Pierre-Alexandre Thonet
SCU Next Phase Meeting July 8, 2014.
Undulator Assembly Procedure
Phase Adjustments: K vs
A Cold SCU Phase-Shifter
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
Undulator Tuning Status Heinz-Dieter Nuhn, SLAC / LCLS for Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko, Scott Jansson, Ralph Colon, Dave.
LCLS Undulator System Production Management
Heinz-Dieter Nuhn – LCLS Undulator Group Leader May 14, 2009
LCLS Undulator Tuning And Fiducialization
Undulator Long-Lead Procurement Preparation
Undulator Integration Test Status
CEPC Booster Ring Magnets
Alignment Diagnostic System Status
LCLS Undulator Magnetic Measurements
East Hall under construction
Presentation transcript:

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review1 Undulator for the LCLS project – from the prototype to the full scale manufacturing

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review2 OUTLINE Major Design features Latest Design Changes ( Internal ANL Review - June 18, 2004 ) Long Lead Items Manufacturing Approach Manufacturing Approach Major Design features Latest Design Changes ( Internal ANL Review - June 18, 2004 ) Long Lead Items Manufacturing Approach Manufacturing Approach

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review3 PARTIAL LIST of LCLS UNDULATOR REVIEW 2003 Lehman Review (May 21-23, 2003) - Rockville, MD LCLS Undulator Parameter Workshop - ANL - October 24, 2003 Review of the LCLC Undulator - ANL - November 14, 2003 LCLS Undulator Diagnostics and Commissioning Workshop - UCLA - January 19-20, 2004 LCLS Undulator System Review - ANL - March 3-4, 2004 Internal ANL Review - June 18, 2004 External Independent Review - SLAC - June 7-11, 2004 LCLS Undulator Physics and Engineering Meeting - ANL - June 28-29, 2004 LCLS Undulator Meeting - ANL - July 23, 2004 Lehman Review at SLAC - August 10-12, Lehman Review (May 21-23, 2003) - Rockville, MD LCLS Undulator Parameter Workshop - ANL - October 24, 2003 Review of the LCLC Undulator - ANL - November 14, 2003 LCLS Undulator Diagnostics and Commissioning Workshop - UCLA - January 19-20, 2004 LCLS Undulator System Review - ANL - March 3-4, 2004 Internal ANL Review - June 18, 2004 External Independent Review - SLAC - June 7-11, 2004 LCLS Undulator Physics and Engineering Meeting - ANL - June 28-29, 2004 LCLS Undulator Meeting - ANL - July 23, 2004 Lehman Review at SLAC - August 10-12, 2004

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review4 LCLS – general view

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review5 LCLS prototype undulator on the magnet measuring stand

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review6 LCLS Prototype Undulator (major design features ) 1.Titanium housing made of forged 12” bar. 2. Base of the magnet structure sections made of aluminum alloy to partially compensate the changes in the magnetization of the permanent magnets to partially compensate the changes in the magnetization of the permanent magnets with temperature. with temperature. 3. Only one clamp for each magnet is made of bronze. 4. Incremental shims or might be used for the undulator gap adjustment. 5. Out-bond area is completely open for the side shims to tune the field strength along the undulator. strength along the undulator. 6. Side shims have four bars made of low carbon steel. Each bar can be individually adjusted and locked in place. be individually adjusted and locked in place. 7. Five cam-shaft movers are used for alignment of the undulator as a whole.

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review7 LCLS Undulator Latest Design Changes 1. Canted undulator design (wedged shims) – proposed by Joachim Pflueger 2. Housing has provision for “magnetic needles” and alignment targets. 2. Simple pole design with two clamping screws from the bottom. 3. Outside fixture for the pole installation. 4. New side shim design to decrease fringed field. 5. New cam-shaft mover deisgn. 6. Magnet structure base made as a single block (three parts before)

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review8 LCLS undulator with wedged shims (canted)

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review9 LCLS prototype undulator magnetic structure with two pole clamps

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review10 LCLS magnetic structure (old and new) Implementation of the new design can save about $20K - $25K per undulator

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review11 LCLS magnetic structure base – new design Implementation of this new design can save about $4K - $5K per undulator

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review12 LCLS magnetic structure with a single unit base

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review13 LCLS undulator pole assembly fixture

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review14 Fixture for the Magnet Structure Assembly

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review15 LCLS Prototype Undulator Titanium Housing

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review16 LCLS Prototype Undulator magnetic needle test set-up

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review17 LCLS Undulator Housing Design Changes Manufacturing simplification 1. Counterbore clamping holes instead of counterbore groves. 2. No provisions for phase shifters. 3. Central grove for vacuum chamber location is removed. 4. More simple provisions for the support pads. Improvements for more precise alignment 1. Housing has provision for “magnetic needles” on both ends. 2. Housing has provisions for four sets of alignment targets.

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review18 LCLS Undulator Pole Material: VACOFLUX 50 (vanadium permendure) Quantity: PER UNDULATOR TOTAL TOTAL WEIGHT: ~ 5300 lbs

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review19 LCLS Undulator Magnet Material: N39UH (Nd-Fe-B type magnet ) Quantity: PER UNDULATOR TOTAL TOTAL WEIGHT: ~ lbs

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review20 Design of the undulator itself is ready for manufacturing,Design of the undulator itself is ready for manufacturing, Design of the undulator support cradle and all associated motions is 2005 year task. Nevertheless we can’t see its impact on housing design. Some minor changes in the support area location can be easily corrected during the manufacturing – we have time;Design of the undulator support cradle and all associated motions is 2005 year task. Nevertheless we can’t see its impact on housing design. Some minor changes in the support area location can be easily corrected during the manufacturing – we have time; It is not necessary to work with only companies, who have undulator experience, our choice of vendors is quite wide;It is not necessary to work with only companies, who have undulator experience, our choice of vendors is quite wide; We are going to teach and train selected vendor (vendors) how to assemble magnetic structure of LCLS undulator and how to put it inside housing. Detailed procedure is written and necessary fixtures are designed.We are going to teach and train selected vendor (vendors) how to assemble magnetic structure of LCLS undulator and how to put it inside housing. Detailed procedure is written and necessary fixtures are designed. Manufacturing approach

XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review21 Conclusion Prototype of the LCLS undulator was successfully designed,Prototype of the LCLS undulator was successfully designed, manufactured, tuned, and tested; manufactured, tuned, and tested; Multiple changes in the design of the prototype were Multiple changes in the design of the prototype were implemented, tested in the preparation for the full scale implemented, tested in the preparation for the full scale production, and approved by internal design review ; production, and approved by internal design review ; Forty undulators will be manufactured in the next three years; Forty undulators will be manufactured in the next three years; Procurement package for the long lead items (strong back, Procurement package for the long lead items (strong back, magnets and poles) is 98% ready; magnets and poles) is 98% ready; We would like to have one LCLS undulator each two weeks. We would like to have one LCLS undulator each two weeks.