Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.

Slides:



Advertisements
Similar presentations
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Advertisements

Focus Coil Update Roy Preece / Tom Bradshaw / Mike Courthold STFC – RAL VC 17 th Jan 2013.
Magnet Cooldown Scheme 17 th February 2012 Roy Preece (STFC RAL)
Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MICE Collaboration meeting May 31 st – June 3 rd 2009 RAL Tim Hayler, Andy Lintern DRAFT SEQUENCE OF EVENTS STEPS
Spectrometer Solenoids MICO 146 Steve Virostek LBNL June 6, 2011.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 114 September 18, 2008.
128 April 2008 Spectrometer Solenoid Fabrication Update MICO Meeting 19 May 2008 S. Virostek, M. Zisman LBNL.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009.
Spectrometer Solenoid Report and Coupling Coil Update Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #129 February 25, 2010.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
Spectrometer Solenoid Testing Update S. Virostek and M. Zisman Lawrence Berkeley National Laboratory MICO Meeting—RAL May 17, 2010.
MICE Video Meeting, 10 Jan 081 Spectrometer Magnet Progress Michael A. Green Lawrence Berkeley Laboratory.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update S. Virostek and M. Green are visiting vendor today for progress update Vendor expects to complete.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #145 December 15, 2011.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update Vendor still expecting to complete first magnet by the end of November, before X-mas more.
Spectrometer Solenoid Testing Update S. Virostek and M. Zisman Lawrence Berkeley National Laboratory MICO Meeting—RAL June 7, 2010.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #26 University of California.
Spectrometer Solenoid Update Steve Gourlay Steve Virostek Lawrence Berkeley National Lab Steve Gourlay Steve Virostek Lawrence Berkeley National Lab MICE.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
MICE - UK Project Progress Roy Preece 30 th April 2013.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
Magnet quench during a training run Successfully trained to peak currents and operationally tested Thermal performance requirements met 3D magnetic bore.
MICE Coupling Coil Update Steve Virostek for Allan DeMello Lawrence Berkeley National Laboratory MICO January 23, 2013 January 23, 2013.
Spectrometer Solenoid Test Plan Workshop: Spectrometer Solenoid Overview Steve Virostek - LBNL February 17, 2012.
Instrumentation and Controls Test Plan Review 17 th February 2012 Roy Preece (STFC RAL)
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
MICE CC Test Status Ruben Carcagno 11/06/13 1. Cooldown Coil Temperature (calculated average in each of 8 coil segments) SC Transition (voltages across.
Spectrometer Solenoids MICO 214 Steve Virostek LBNL February 6, 2013.
MICE VC Alain Blondel 1 MICE NEWS MICE VC Spectrometer solenoid 2. Magnetic shielding 3. Next Collaboration meeting.
Spectrometer Solenoids MICO 197 Steve Virostek LBNL August 15, 2012.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Spectrometer Solenoid Overview Roy Preece 31 st January 2011.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #28 Sofia, Bulgaria.
Spectrometer Solenoid – Quench Analysis The LBNL version of the quench model has been further refined - Heng Pan is finishing various quench scenarios.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
SBS Magnet and Support Status Robin Wines June 2013.
SPOKESMAN’S UPDATE K. Long Imperial College London/STFC.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 120 May 7, 2009.
Spectrometer Solenoid Design and Test Results Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
MICE Spectrometer Solenoid Recovery Review - December 3-4, Steve Virostek MICE Spectrometer Solenoid Design and Assembly.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Status of the MICE Construction Project
Spectrometer Solenoid Update
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Spectrometer Solenoid Fabrication Status and Schedule
MICE Coupling Coil Update
Presentation transcript:

Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation method being written for the Wang tech to remove old resistor system and installation of new system. The second radiation shield outer shell penetrations are being cut. End plates have been machined. Old bore tubes being prepared. Both vacuum vessels have new holes plasma cut and have been ground clean. Both are ready for the assembly phase. MAP tech board meeting yesterday. Some changes to the Testing and Operations section of the schedule to give a more realistic timescale for the testing. This is the first iteration for the testing methods, some timescale changes may be implemented at a later date when more information has been collected. Control system requirements

Testing and Operations changes Soak testing of the coolers reduced from 2 weeks to 3 days. Thermal differences during soak test of the cryo coolers At the tapered joint on the 1 st stage of the coolers At the single stage cooler All points of the radiation shield Warm bore using temperature probe Monitoring of the Heater / Helium Pressure feedback system Magnetic Mapping of the solenoids will not be a detailed analysis. The current thinking is for a simple on beam axis measurement at the approximate coil centres using a single Hall probe. Reduction from 3 weeks to 1 day This measurement will be carried out in a single day after a steady state for the coils has been achieved. Coil Ramp / Operation with probable quench / re-cool after quench / thermal characterization. Reduced from 6 weeks to 2 weeks. 1 – 2 Quench / cool cycles per day

Control System Requirement Previously stated required date 1 st December for start of cool down. Mid November arrival requested to give time to debug / setup. Wang internal milestone. Wanting equipment onsite as soon as possible. Indicated date for requirement 31 st January for start of cool down (errors found / updates in schedule since ). Shipping early Jan More conservative schedule. As soon as possible after completion of the AFC control system.

Milestones 1.Resistor/Diode Pack with conduction plate installed to Cold Mass – 19 th September. 2.Cold Mass ready for Helium leak checking – 22 th September. 3.Machining work on Vacuum Vessel completed – 22 nd September 4.Cold Mass ready for MLI wrapping – 28 rd September 5.Assembly Starts on Upstream Spectrometer Solenoid – 11 th October 6.Cold Mass and Shield inside the Vacuum Vessel – 31 st October 7.Cold Mass aligned to the Vacuum Vessel – 9 th November ~Delivery of Upstream Solenoid to RAL – 16 th April 2012 ~Delivery of Downstream Solenoid to RAL – 10 th July 2012 R Preece/S Virostek 14/10/11