Detector Systems Update MICO Feb 25, 2008. MICE Detector Systems  CKOV u CKOV installation planned during March shutdown u Cable issues resolved. Geneva.

Slides:



Advertisements
Similar presentations
Detector Systems Update MICO March 17, MICE Detector Systems  CKOV u Mississippi RAL  TOF0/1 u Hamamatsu PMT assemblies show an increasing.
Advertisements

MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009.
Detector Systems Update MICO April 23, MICE Detector Systems  CKOV u Nothing new  TOF0/1 u Tests to identify the source of the problems in the.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
November 4th 2009MICE CM25 - RAL1 Commissioning Needs – MICO83 m. apollonio  g. cecchet.
MICO 22 nd February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
Detector Systems Update MICO May 19, MICE Detector Systems  Beam Monitors u Over heating of sender boards has been s Solution.
Detector Systems Update MICO April 14, MICE Detector Systems  CKOV u Nothing new  TOF0/1 u H6533MOD PMT assembly reliability is the main concern.
MICE CM15 June 2006Jean-Sébastien GraulichSlide 1 DDAQ Pending Issues o Detector FEE o Software framework o Trigger o Data Storage Jean-Sebastien Graulich,
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Detector Systems Update MICO March 3, MICE Detector Systems  CKOV u CKOV humidity (HIH4000) and temperature (LM35) sensors in hand for installation.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting June 7, 2010.
Detector Systems Update MICO April 7, MICE Detector Systems  CKOV u Installed, first signals seen  TOF0/1 u 8 new H6533MOD assembly PMTs have.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
Commissioning needs MICO meeting 30 June 2008 MOM ( Roumen Tsenov)
Detector Systems Update MICO March 10, MICE Detector Systems  CKOV u No update  TOF0/1 u Tests with laser injection system progressing. u Tests.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
1 Timescales Construction LCR MICE Beam Monitoring counters + DAQ My understanding Jan 07 Feb 07 Mar 07 Apr 07 May 07 Jun 07 Jul 07 Aug 07 Sep 07 ISIS.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting May 24, 2010.
Cryo Update and Power Distribution Alan Bross Tracker Parallel – MICE CM October 7, 2007.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
MICE CMPB Alain Blondel 19 April spokesperson remarks CMPB MICE NEWS.
MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW corner –Replacement West wall concrete ordered, corner pieces.
Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
K. Long, 10 October 2015 Project Manager’s report Status/progress since CM18 Looking forward Organisation Conclusions.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Detector Systems For May/June Run MICE Video Meeting April 24, 2008.
DAQ MICO Report Online Monitoring: –Status All histograms are now implemented Still not fully online –Only monitoring from data file (slightly offline,
MICO July 07Jean-Sébastien GraulichSlide 1 Detector DAQ Status o Overview – Hardware status o Installation at RAL o DAQ workshop o Current Activities Jean-Sebastien.
Tracker Summary Alan Bross MICE CM October 10, 2007.
1M. Ellis - MICE VC - 1st November 2007 Cosmic Ray Test Preparations  The cosmic ray test was initially planned to be held in R12, but this proved to.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
M. Bonesini - MICE Inst Meeting M. Bonesini INFN Milano TOF installation plans.
Online Reconstruction 1M.Ellis - CM th October 2008.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
1 CKOV1 at the MICE Experiment CKOV1 to perform mu/pi id w TOF0/TOF1. Progress since CM16 CKOV1 Fabrication and Installation TOF0 CKOV1 TOF1 EMCAL TOF2.
VLPC System Update A.Bross MICE CM Feb 9, Cryo  Production cryostats 1 and 2 ran smoothly at operating temperature  However, Cassette 109 in cryo.
1 MICE PID Group Meeting 11 May 2005 Update on Design & Safety Review Presented by Wing Lau.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
Database David Forrest. What database? DBMS: PostgreSQL. Run on dedicated Database server at RAL Need to store information on conditions of detector as.
MICE CM39 St Catherine’s, Oxford, 26 June 2014 Paul Soler Instrumentation Global Commissioning Plan.
Tracker Cosmic Ray Test 2011 Linda R. Coney UC Riverside CM 29 - February 16, 2011.
Detector Summary Tracker. Well, as far as the tracker hardware is concerned, we are done. – Need to do the system test to make sure nothing has degraded.
M. Bonesini – CM 291 PID detectors summary M. Bonesini Sezione INFN Milano Bicocca.
Software Overview 1M. Ellis - CM21 - 7th June 2008  Simulation Status  Reconstruction Status  Unpacking Library  Tracker Data Format  Real Data (DATE)
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
1 MICE UK meeting at RAL 05 May 2005 Integrated Design & Safety Review Presented by.
VC98 March 07Jean-Sébastien GraulichSlide 1 DDAQ Status o DAQ Software o Front-End and Trigger o What will happen soon o Schedule Milestones Jean-Sebastien.
Minerva Test Beam 2 Status Geoff Savage for the Test Beam 2 Team March 23, /23/2015AEM - Minerva Test Beam 2 Status1.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
Linda Coney MICO June 6, 2011 MICE Online Report.
Chris Booth Sheffield 29th March 2006
Status of the MICE Construction Project
Installation of an Instrument on a CERN machine
MICE Target Report Video Conference 29/11/07
10/month is the present production rate 2 FTE + sporadic contributions
Presentation transcript:

Detector Systems Update MICO Feb 25, 2008

MICE Detector Systems  CKOV u CKOV installation planned during March shutdown u Cable issues resolved. Geneva shipping DSA-MLCR cables. to RAL u Cables routed by RAL personnel in coming weeks. u Table bracket design by Oxford. Waiting go-ahead for machining at Oxford. u Some work on environmental sensors and gas flushing hardware at UM.  TOF0 u No Update  Tracker u Cryo-system #4 for first tracker has now been replaced by system #2 due to a cool-down problem u Readout tests of AFEIIt boards continue. To date, functional readout of a full set of boards (8) has not been accomplished s Estimate for shipment to RAL has not changed.  Calorimeter u KL s The additional iron shielding bars for KL has been built and the complete frame will be reassembled this week. u SW s No Update

 Beam Monitors u Small Beam Monitor is complete and tested u Large Beam Monitor is nearing completion u Target is to ship equipment by 3/13 u Fermilab Team arrives at RAL on 3/24 for installation and commissioning