Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September 2009 o Update on ATLAS insertable B-layer LHCC Upgrade session CERN, September, 22 nd 2009.

Slides:



Advertisements
Similar presentations
3D Sensor Processing - IBL G. Darbo – INFN / Genova Venezia, 4 June 2009 o IBL per Marzio G. Darbo - INFN / Genova Agenda page:
Advertisements

Reviewer’s Mandate G. Darbo – INFN / Genova Sensor Review, 4 May 2011 o Sensor Review Slides for Jörn Talk IBL Sensor Review Kick-off Meeting CERN, May,
IBL interim-MoU Annexes G. Darbo – INFN / Genova PEIB, 1 March 2010 o IBL interim-MoU Annexes Pixel Extended Institution Board CERN, March 1 st, 2010 NCP.
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
ATLAS detector upgrades ATLAS off to a good start – the detector is performing very well. This talk is about the changes needed in ATLAS during the next.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
ATLAS POH.P, G.D12/5/2009 IBL Update H. Pernegger, G. Darbo (PO 12/5/09) Organization and WG coordinator Schedule Decision Items Organization Tools & Meetings.
U.S. ATLAS Executive Meeting Upgrade R&D August 3, 2005Toronto, Canada A. Seiden UC Santa Cruz.
IBL Slides G. Darbo – INFN / Genova CSN1, 22 November 2010 o IBL Spare Slides Commissione I – 22 Nov 2010 G. Darbo - INFN / Genova.
Towards a TDR for the IBL G. Darbo - INFN / Genova AW, 24 February 2009 o Towards a TDR for the IBL ATLAS Upgrade Week CERN, 24 February 2009 Session:
ALICE ITS Coordination Board 16 July 2013 L. Musa 1.
The ATLAS Insertable B-Layer (IBL) Project C. Gemme, INFN Genova On behalf of the ATLAS IBL COllaboration RD11 Firenze July 2011.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
IBL MoU G. Darbo – INFN / Genova 24 April 2010 o IBL MoU ATLAS Upgrade Week DESY, April 24 th 2010 M. Nordberg, M. Nessi, C. Gößling, H. Pernegger Presented.
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
IBL Project Status G. Darbo – INFN / Genova AW, 9 October 2009 o Insertable B-layer Project Status ATLAS Week Barcelona, October, G. Darbo - INFN.
IBL Status, TDR & MoU G. Darbo – INFN / Genova ATLAS Week, 26 February 2010 o IBL Status, TDR & MOU ATLAS Week CERN, February 26, 2010 G. Darbo - INFN.
IBL MoU G. Darbo – INFN / Genova 17 April 2010 o IBL MoU Contribution prepared for Marzio’s talk at April RRB G. Darbo - INFN / Genova.
ATLAS Preparations for LHC Phase-I Upgrade G. Darbo – INFN / Genova ATLAS Week, 8 July 2009 o ATLAS Preparations for LHC Phase-I Upgrade ATLAS Week CERN,
CERN, Main challenges for the ATLAS upgrade project in the coming year.
SLHC SG: ATLAS Pixel G. Darbo - INFN / Genova SLHC SG, July 2004 ATLAS Pixel at SLHC G. Darbo - INFN / Genova Talk overview: A table with different High.
Reviewer’s Mandate G. Darbo – INFN / Genova Sensor Review, 4 May 2011 o Sensor Review Mandate IBL Sensor Review Kick-off Meeting CERN, May, 4 th 2011 G.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September 2009 o Update on ATLAS insertable B-layer LHCC Upgrade session CERN, September, 22 nd 2009.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
ATLAS PIXEL SYSTEM OVERVIEW M. Gilchriese Lawrence Berkeley National Laboratory March 11, 1999.
ATLAS FP TRACKER PLANS Steve Watts School of Physics and Astronomy University of Manchester Well defined design in the FP420 Design Report Based on the.
Communications G. Darbo – INFN / Genova IBL MB#15, 5 October 2009 o Bump Bonding Selex / INFN Roma, October, 30 th 2009 G. Darbo - INFN / Genova.
T. Kawamoto1 ATLAS muon small wheels for ATLAS phase-1 upgrade LHCC T. Kawamoto (New) small wheels ? Why new small wheels for high.
AMS HVCMOS status Raimon Casanova Mohr 14/05/2015.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
IBL - Opening G. Darbo - INFN / Genova AW, 25 February 2009 o IBL Introduction & Project Organization ATLAS Upgrade Week CERN, 25 February 2009 Session:
M. Gilchriese ATLAS Pixel Upgrade Thoughts on US Role.
Reviewer’s Mandate G. Darbo – INFN / Genova Sensor Review, 4 May 2011 o Sensor Review Mandate IBL Sensor Review Kick-off Meeting CERN, May, 4 th 2011 G.
C. Kiesling, 1st Open Meeting of the SuperKEKB Collaboration, KEK, Dec , The DEPFET-Project: European Collaboration for a Pixel SuperBelle.
October RRB G. Darbo & H. Pernegger RRB – October 2010 o October RRB Slides for Marzio’s RRB talk CERN, October, 11 th 2010 G. Darbo & H. Pernegger.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 o IBL kick off meeting summary and issues ATLAS Upgrade Project Office.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
15/09/20111 ATLAS IBL sensor qualification Jens Weingarten for the ATLAS IBL Collaboration (2 nd Institute Of Physics, Georg-August-Universität Göttingen)
Transition to cables Staves Services IP Underside of stave: IBL modules IBL Design.
IBL – UniGe involvements UniGe Team : G. Barbier, F. Cadoux, A. Clark, S. Débieux, D. Ferrère, C. Husi, G. Iacobucci, M. Weber Other member (KEK): Y. Takubo.
ATLAS Upgrade Plans ATLAS Hardware – Challenges and Opportunities Norwegian CERN “Town Meeting” Bergen
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
IBL TDR G. Darbo / INFN Genova ATLAS CB – October 2010 o TDR of Insertable B-layer ATLAS CB, October 8 th 2010 G. Darbo / INFN - Genova Indico agenda page:
IBL Progress D. Ferrère for the IBL community LHCC Upgrade Session – June 14 th 2011 Detailed progress was reported at the IBL General meeting, June 8-10.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
TDAQ and L1Calo and Chamonix (Personal Impressions) 3 Mar2010 Norman Gee.
ATLAS Italia – IBL G. Darbo – INFN / Genova CERN, 2 March 2011 o IBL ATLAS Italia / Referee CERN, March 2 nd 2010 G. Darbo – C. Meroni INFN / GE – MI Agenda:
RD42 Status Report W. Trischuk for the RD42 Collaboration LHCC Meeting – June 12, 2013 Development of CVD Diamond Tracking Detectors for Experiments at.
The ATLAS IBL Project – 5 th Trento Workshop G. Darbo – INFN / Genova Manchester, February 2010 o The ATLAS IBL Project The 5 th "Trento" Workshop.
The ATLAS Insertable B-Layer Detector (IBL) F. Hügging on behalf of the ATLAS IBL collaboration Pixel th International Workshop on Semiconductor.
20/07/ Marzio Nessi Agenda For NIKHEF plans for the ATLAS Upgrade. NIKHEF ATLAS upgrade plans and organization DL/NH Potential.
Upgrade plans for ATLAS. Nigel Hessey (Nikhef) is overall ATLAS upgrade coordinator.
ATLAS Pixel Upgrade G. Darbo - INFN / Genova LHCC- CERN 1/76/2008 o Pixel/B-layer Developments LHCC Upgrade Session CERN, 1 / 7 / 2008 G. Darbo - INFN.
Straw man layout for ATLAS ID for SLHC
Manchester, 24/02/2010 G.-F. Dalla Betta The common floor-plan of the ATLAS IBL 3D sensor prototypes Gian-Franco Dalla Betta (Univ. Trento and INFN) for.
TC activities.
FBK / INFN Roma, November , 17th 2009 G. Darbo - INFN / Genova
SVT subchapters & editors
P. Morettini Towards Pixel TDR PM - ITk Italia - Introduction 8/2/2017.
SVT – SuperB Workshop – SLAC 6-9 Oct 2009
IBL Overview Darren Leung ~ 8/15/2013 ~ UW B305.
Francesco Forti University and INFN, Pisa
(with R. Arcidiacono, A. Solano)
Valerio Re (INFN-Pavia) on behalf of the RD53 collaboratios
Communications Share Point Collaborative WS:
CO2 cooling requirements for the IBL
Update on ATLAS insertable B-layer
Presentation transcript:

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September 2009 o Update on ATLAS insertable B-layer LHCC Upgrade session CERN, September, 22 nd 2009 G. Darbo - INFN / Genova Indico agenda page:

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September IBL Project Status Project approved by ATLAS Project Leader endorsed by ATLAS CB (February 20 th ) IBL has put in place its management structure (Management Board) – members nominated ATLAS Institutes Participation IBL Kick-off (July 8 th ) meeting with Institute’s Leaders to focus participation in the project. Large interest in the project (~35÷40 institutes participated at the kick-off meeting and have shown interest in parts of the project) Project cost evaluated and funding model proposed: 4.0 MCH (M&O-A), 5.6 MCH (M&O-B, new project) Technical Design Report (TDR) Main editor / technical editor (K. Einsweiler / M. Capeans) and chapter editors in charge Few editor’s meetings since end of July, TDR foreseen for April Memorandum of Understanding foreseen in “interim” form by the end of the year: MoU will be signed after TDR (spring 2010)

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September IBL Organisation Structure Module WG (2 coordinators) FE-I4 Sensors Bump-Bonding Modules Test & QC Irradiation Module WG (2 coordinators) FE-I4 Sensors Bump-Bonding Modules Test & QC Irradiation Stave WG (1 Phys + 1 Eng.) Staves Cooling Design & Stave Thermal Management HDI Internal Services Loaded Stave Test & QC Stave WG (1 Phys + 1 Eng.) Staves Cooling Design & Stave Thermal Management HDI Internal Services Loaded Stave Test & QC IBL Integr.-Install. (2 Eng.) Stave Integration Global Sup. Beam Pipe (BP) Ext.services inst. IBL+BP Installation Cooling Plant Test & QC IBL Integr.-Install. (2 Eng.) Stave Integration Global Sup. Beam Pipe (BP) Ext.services inst. IBL+BP Installation Cooling Plant Test & QC Off-detector (1 Phys + 1 E.Eng.) Power DCS ROD Opto-link Ext.serv.design/proc. Test Beam System Test Off-detector (1 Phys + 1 E.Eng.) Power DCS ROD Opto-link Ext.serv.design/proc. Test Beam System Test IBL Management Board Membership: IBL PL + IBL TC 2 coordinators from each WG Plus “extra” members IBL Management Board Membership: IBL PL + IBL TC 2 coordinators from each WG Plus “extra” members Membership IBL Project Leader: G. Darbo IBL Technical Coordinator: H. Pernegger “Module” WG (2 Physicists): F. Hügging & M. Garcia- Sciveres “Stave” WG (1 Phy. + 1 M.E.): O. Rohne + D. Giugni “IBL Assembly & Installation” WG (2 M.E. initially, a Phy. Later): N. Hartman + R. Vuillermet “Off-detector” WG (1 Phy. + 1 E.E.): T. Flick + S. Débieux “Extra” members: Ex officio: Upgrade Coordinator (N. Hessey), PO Chair (M. Nessi), Pixel PL (B. Di Girolamo), ID PL (P. Wells), Pixel Chair (C. Gößling) Offline “liaison” Pixel Off-line coordinator: A. Andreazza TDR editor (temporary): K. Einsweiler Whole project divided into 4 working groups IBL Management Board has 10 members, plus “extra” and ex-officio members. Frequent meetings (every ~14 days) in this phase of the project.

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September TDR - Schedule ActionDeadline # Weeks from previous TDR Printout, submission to LHCCApril 1 st Final Draft Deadline for commentsMarch 15 th Sent to Collaboration for ApprovalMarch 1 st Draft 2 Deadline for commentsFeb 15 th Sent to CollaborationJan 25 th Draft 1 Deadline for commentsJan 11 th Sent to CollaborationDec 15 th Approval by TDR Editors and PO/USGDec 1 st Preparation TDR IntegrationNov 16 th Editors meeting 4 - final internal draftOctober 19 th Editors meeting 3September 28 th Editors meeting 2September 7 th Editors meeting - final chapter’s structureAugust 19 th Editors Kick off meetingJuly 22 nd 2009

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September IBL Layout and New Beam Pipe Reduction of beam-pipe (ID from 29R to 25R) allows enough clearance to fit the IBL The IBL internal envelope is defined by the new beam pipe and by the thickness of the insulation required during the bakeout. Beam pipe ID= 50, thickness = 0.8 mm, Insulation =4 mm Several layouts under study: 14 staves at R min =~3.2 cm Single and double staves – One or two (redundant) cooling channels Inverted turbine Bus FE/module Pigtail 1.11 Junction Bus-Pigtail Wire-Bondings FE- Pigtail Ref: N. Hartman:

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September Module Layout - Convergence Sensor technology (3D, Planar, Diamond) taken after TDR module prototypes with FE-I4 (second half 2010) – Common Engineering specifications (layout, Max Vbias, Ibias, power) under definition to progress on cooling/stave/service design; Common sensor baseline for engineering and system purposes 3D/Diamond – single chip modules / Planar sensors – 2 chip modules Sensor/module prototypes for ~10% of the detector in 2010 Stave prototype tested with modules and cooling Credits: M.Garcia-Sciveres – F. Hügging

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September Requirements for Sensors/Electronics Requirements for IBL IBL design Peak Luminosity = 3x10 34 cm- 2 s -1  New FE-I4, higher hit rate Integrated Luminosity seen by IBL = 550 fb -1 Total NIEL dose = 2.4 x ± 30% (σ pp ) ± 50% (damage factor) = 4.7 x n eq /cm 2  more rad-hard sensors Total radiation dose > 200 Mrad ATLAS Pixel Sensor/FE-I3 designed for n eq /cm 2 / 50 Mrad Fit made for 2 < r < 20 cm for L=1000fb -1 Gives for 3.7 cm (550 fb -1 ):  1MeV =2.4x10 15 (1.2 MGy) Safety factors not included in the computation (pp event generator: 30%, damage factor for 1 MeV fluences: 50%) Ref. Ian Dawson – ATLAS Upgrade Week (Feb.09)

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September Sensor: 3D, Planar, Diamond IBL sensor developments coming from ATLAS R&D efforts – IBL define specification and requirements for the sensors: ATLAS 3D Sensor Collaboration (16 Institutes and 4 processing facilities): Bergen, Bonn, CERN, Cosenza, Freiburg, Genova, Glasgow, Hawaii, LBNL, Manchester, New Mexico, Oslo, Prague, SLAC, Stony Brook, Udine - Processing Facilities: CNM Barcelona, FBK- IRST (Trento), SINTEF/Stanford ATLAS Planar Pixel Sensor R&D Collaboration (16 Institutes) Bonn, Berlin, DESY, Dortmund, MPP & HLL Munich, Udine, KEK, CNM Barcelona, Liverpool, LBNL, LPNHE, New Mexico, Orsay, Prague, Santa Cruz. ATLAS Diamond R&D Collaboration (6 Institutes): Bonn, Carleton, CERN, Ljubljana, Ohio State, Toronto Bring the 3 sensor technologies to the prototype phase Select technology on prototype results by end of 2010

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September FE-I4 FE-I3 not suitable for IBL ~7% inefficiency at 3.7 cm and L =3x10 34 cm -2 s -1 FE-I3 works at 50 Mrad, but has major faults at 100 Mrad FEI4 design collaboration formed in 2007 between: Bonn, CPPM, Genova, LBNL, NIKHEF FE-I4_proto chip (3/08) Main analog blocks (3x4mm 2 ) Irradiated to 200 Mrad: noise increase by 20% (ENC 100- >120 with 400fF load and I AVDD =10µA/pixel)

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September FE-I4: Review, Submission, Prototyping FE-I4 submission review Review on “GDS II” ready Nov 3-4 (K. Einsweiler to chair) Submission, if review is passed, planned before the end of the year Engineering run Up to 12 wafers from one engineering run (under investigation possibility of additional ones) ~50 FE-I4 fit in a 8” wafer – yield “for good enough for module prototype” chip estimated 40÷70% Planned prototypes with sensors by spring 2010 Limited number of sensor options (max 3) for each of the three technologies ~10% of IBL in prototyping size FE-I4 in a 8” wafer Review team: Francis Anghinolfi, CERN - Stéphane Debieux, Geneva (IBL Electronic Project Engineer) - Kevin Einsweiler, LBNL (Review Chair) - Philippe Farthouat, CERN (Project Office) - Alex Grillo, UCSC - Kostas Kloukinas, CERN - Xavier Llopart, CERN - Mitch Newcomer, Penn - Ivan Peric, Heidelberg - Ned Spencer, UCSC - Mike Tyndel, RAL (Project Office) - Rick Van Berg, Penn, Vladimir Zivcovic

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September Stave Design To put here Layout (preferred) Motivate the need of a small beam pipe: tight clearance, gaining 0.5 cm is large respect the available space between BL and present beam pipe, beam pipe bake-out need space for IBL safety (show thermal simulation), use an IBL PST to simplify insertion…. Show developments: Pipe, Thermal Management, Fittings, options Goal to reduce material budget from 2.7 to 1.5 %X0 ~2-3 slides

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September Next step was to flip the sensor making them pointing inward. The single stave reversed, in both flavors single and double pipe, offers a wider area for the flex on the back of the stave. The recent estimate on the thermal transient during the bake leads to be optimistic about the module temperature. If confirmed by the tests, this solution Single pipe reversed turbine temperature. If confirmed by the tests, this solution becomes very appealing: Naturally the staves can be supported from outside decoupling the layer from the beam pipe. There is also a slight decrease of the senor mean diameter that must be evaluated for physic. Double pipe

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September FEI4 drives the schedule for modules -getting the next FEI4 asap is crucial for module qualification Stave 0 plays a crucial to qualify the IBL system (mechanics, staves and off detector electronics) Service installation happens in shutdowns - need definition & procurement of services (USA15->PP2) early on to use shutdown time efficiently Commissioning as part of Pixel system

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September Schedule We plan to be ready for installing by end 2014: Cannot be ready much before without sacrificing performance: need new technology development (on going) and prototyping (next year) for FE-I4 (more radiation hard, R/O efficiency), Sensors (more radiation hard), Staves (lighter). IBL, in addition to take over the B-layer when accumulated dose will reduce its efficiency, will improve the present tracking performance (lighter and at small radius than present B-Layer) and will be an insurance for hard failures (cooling, opto-links, interconnections, etc.) of present B-layer. To install the IBL we need a long shutdown (8 months): Need to synchronize a long shutdown (8 months) for IBL installation – this could be in the “shadow” of machine element installation The IBL is in the roadmap of the new Pixel detector at sLHC The technologies needed for the IBL are either usable for Pixel outer layers or are a first step toward more radiation hard and higher R/O bandwidth components for the inner Pixels.

Update on ATLAS IBL G. Darbo – INFN / Genova LHCC, 22 September Implications of IBL IBL will impact other components of the LHC machine and ATLAS Smaller beam-pipe and larger aperture new triplets (sLHC phase I) require to revisit the TAS and the forward shielding Larger aperture triplet and new TAS design requires to look at: Effects on muon background; Protection of a smaller radius IBL. Also, we have other beam-pipe issues, like going to much longer beryllium sections. This is not strictly sLHC phase-I, but has same timescale.