Injection test? Mike Lamont For initial discussion.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
Commissioning the access system M. Gruwé Machine checkout workshop November 8 th 2007.
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
R.Giachino / M.Albert Be/op 5 April 2015 LHC Machine check out 1v1.
LHC 15 April :19: UFO event detected by on BLM 15.R8 and beam dump 8:46: P2 cold compressor trip and recovery during morning shift. Access given.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
Linear Collider Machine Protection Issues M. Palmer Injection System Injector Damping Rings Bunch Compressor and Transfer Sections Main LINAC Beam Delivery.
Technical review on UPS power distribution of the LHC Beam Dumping System (LBDS) Anastasia PATSOULI TE-ABT-EC Proposals for LBDS Powering Improvement 1.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Injection test1 Injection test in 2006 The installation schedule version 1.7 recently approved includes a ‘possible injection test’ - foreseen in April.
LHC ACCESS SYSTEM 1Authors: P, Ninin, S. Grau & LHC access team EDMS: Access System during the LHC Injection tests P. Ninin, S. Grau - TS/CSE Workshop.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
LHC Sector Test1 LHC Sector Test - Beam IntroductionMike LamontIntroductionMike Lamont Proposed tests with beamBrennan GoddardProposed tests with.
Machine status – December 28  Machine status - overview  Blue ring: ramp development  Yellow ring: obstruction update  Set-up and ramp-up.
1 Interlock logic for LHC injection: intensity limitations Jörg Wenninger AB-OP-SPS Outcome of the join Machine-Experiments Workshop on Machine Protection.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
LHC Sector Test 1 Roger Bailey, Helmut Burkhardt, Paul Collier, Brennan Goddard, Stephen Jackson, Lars Jensen, Rhodri Jones, Verena Kain, Alex.
LHC Sector Test Mike Lamont. LHC sector test - MAC June /6/2007 Outline Overview Motivation Pre-requisites/preparation Tests with beam Organisation.
Schedule IT General Schedule 9 th, September 09 Today.
‘Review’ of the machine protection system in the SPS 1 J. Wenninger BE-OP SPS MPS - ATOP 09.
LHC Machine Checkout & Dry Runs Strategy Acknowledgements: R.Alemany, R.Giachino M. Albert LHC Beam Operation Workshop June 2014.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
Running scenario 2009/10 Run through components – and then synthesis.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Overview Extraction tests: TT40 and TT60, week 21 –controls and data, interlocking, extraction, MKE6 transfer function and energy tracking, high intensity,
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Transfer Line Test preparation meeting V. Kain, R. Alemany.
LHC sector test - summary 1 14/03/2008 Possible injection into part of the machine Options etc.Mike Lamont Stopping the beamStefano Redaelli Proposed Tests.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
LHC machine protection close-out 1 Close-out. LHC machine protection close-out 2 Introduction The problem is obvious: –Magnetic field increase only a.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
Commissioning Strategy - Chamonix LHC Commissioning with Beam Overall Strategy Mike Lamont AB-OP 17 th January 2005 Chamonix XIV B.D.S.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
Options for Possible Sector Test Mike Lamont. LHC sector test
The TV Beam Observation system - BTV
DRY RUNS 2015 Status and program of the Dry Runs in 2015
LHC Commissioning with Beam
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
LHC schedule.
The LHC - Status Is COLD Is almost fully commissioned
Summary of week 7 Hardware Commissioning:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Monday 11/07: Recovery Plenty of accesses.
Machine plans - Alignment workshop
MPSC Procedures An update
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
LHC Injection and Dump Protection
LHC Morning Meeting - G. Arduini
Week 35 – Technical Stop and Restart
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Machine plans - CMS startup workshop
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
The LHC Beam Interlock System
Beam commissioning plans, 2007 and 2008
HI2011 Commissioning Status
Presentation transcript:

Injection test? Mike Lamont For initial discussion

LHC injection test? Possible scenario Phase Time Mid JulyAll sector colds Couple of weeks for cryo stabilization etc Recovery from UX85 intervention End JulyDSO tests, close ring 2 days Early AugustInjection test 2 days - weekend Day afterRadiation survey, establish supervised areas 1 day AugustHardware commissioning of last sectors 2 weeks AugustMachine checkout 2 weeks Weekend (Friday evening to Monday morning) ~ 4 weeks before full commissioning

Access Ring fully closed DSO tests appropriate to injection test scenario Experiments out for a week-end  “a disturbance but acceptable” – clearly to be confirmed Access during test possible  to areas that don’t see beam General access mode following test  where appropriate LHC injection test?

Access – DSO tests Goal  Nominal system deployed and tested before end July Plan evening shifts for one week in July  2 points an evening  test doors [350] – sample or all  by-pass safety elements to avoid hitting them too often, check receipt of signals etc.  by-pass BIW Plus one weekend of test Resources required  Personnel for test, documentation etc. LHC injection test? Ghislain Roy

DSO – Injection Test Close whole ring Test all doors in 7 & 8 against injection chain Qualify rest of ring against injection chain Condem main power supplies down-stream (block beam) Potentially interesting option acting as useful milestone LHC injection test?

Radiation Supervised areas after test  Given analysis, and measurements during and after the test, it is envisaged that:  Certain areas might be declared controlled areas for the first few days after the test;  Thereafter these areas would join the rest of the sectors involved as supervised areas Not really an issue at this stage. LHCb – presumably ready to accept beam by this stage LHC injection test?

LHC injection test? Option 1: Injection R8 – A78 – R7 No temporary dump to be installed at IR7 - use collimators instead (3 primaries, 5 secondaries for the single beam)  detailed proposal in place (Stefano) No temporary installation of beam instrumentation at IR7. Need small part of 8-1, all 7-8 hardware commissioned to 450 GeV+. Minimal Impact Solution

LHC injection test? Option 1: Pros and Cons Minimal requirements on Cryogenics & HWC Less area classified by RP Less impact on other systems  BI, LBDS Only one sector test - less systems tested  BI, LBDS, collimators missed BI configuration not perfect  Rely on in situ instrumentation  Not ideal – no BCT – some implications for measurements

LHC injection test? Option 2: Injection R8 – A78 – A67 – Dump Use TCDQ and TCS to block down stream aperture – safeguard only - no installation of temporary dump. RP approval/study required Beam onto TDE – LBDS/B2 will be ready for action Can use correctors to steer into dump channel - so should be able to guarantee very little beam goes onto TCDQ etc. Rely on in situ instrumentation (BCT in dump line etc.). No temporary installation required. Need small part of 8-1, all 7-8, all 6-7 hardware commissioned to 450 GeV+.

LHC injection test? Option 2: Pros & Cons Test beam dump and related systems Don't irradiate ring - beam onto TDE (beam dump block) Check IR7 optics, performance of warm magnets Beam through 3 IRs, 2 full sectors Full suite of Beam Instrumentation in place  FBCT, Screens, BLMs Support required for 3 cold sectors cold – sectors should be operational anyway Favoured Solution

LHC injection test? Option 3 – Injection point 2 – B1 Need partial 1-2, complete 2-3 Dump on collimators in IR3  scheme sketched by Stefano Could do both B1 and B2! But demands on Access/DSO tests would be greater.

LHC injection test? Proposed Tests

Tests Pilot Beam for the most part:  single bunch of x 10 9 protons Total intensity:  ~ protons Gives a first good look at:  Full injection set-up  Instrumentation  Aperture  Field quality, polarities No doubt we would learn a lot – some lead-in time for problem resolution LHC injection test?

LHC injection test? Monitoring Radiation monitoring  RAMSES operational  LHCb: 4-5 monitors planned under RAMSES Beam Loss Monitors  Sensitive to losses at 1% level with pilot bunch intensity Beam Intensities  Beam extracted, injected (and to dump) to be logged RPG survey after the event and perhaps during the test to ensure that activation remains low.  Careful survey afterwards planned after the test near the injection dump and dump itself.

LHC injection test? BIC 3/16 of LHC Beam Interlock System SPS Extr. Kicker BIC SPS Extraction Lines Interlock System Radiation levels BLM Powering Interlock Warm Magnet Interlock Vacuum LHCb Access system will provide input to BIS which will inhibit SPS extraction. Configurable if the case of extraction required & LHC not ready (e.g. extraction tests) BIS Old Slide!!! – see Bruno for update

LHC injection test? Other systems Injection elements: septa, kickers Collimators Machine Protection Beam Instrumentation:  BPMs, BLMs, BTV, BCT, BST Magnet Model Controls Software/tools Access system Radiation Protection Radiation Monitoring Optics, aperture model Test preparation orthogonal to HWC and already ongoing.

LHC injection test? Injectors

LHC injection test? Impact Fairly limited demands on cold circuits  Beam 2 & limited recycling  8-1 and 7-8 already complete, 6-7 starting soon  Re-cool-down following UX85 intervention required Cryogenics, QPS, HWC support required during test  In general, low current levels with occasional cycles  Sectors concerned would hopefully be operational by then  Experience from 56 Access  Experiments – key, would have to sacrifice a few days access  HWC – commissioning in other sectors can continue (if we’re working weekends) – not an issue for sectors concerned