October 22, 2003H.J. Krebs1 LST Mechanical Design Review 2004 IR-2 Installation Schedule H.J. Krebs October 22, 2003.

Slides:



Advertisements
Similar presentations
Click on this image to open the full PDF document.
Advertisements

Bill Miller NOνA-May 04 NOνA Total Active Liquid Scintillator Detector Installation First Pass Estimate Bill Miller U of M.
V. Carassiti - Princeton (USA) 9-13/01/ BABAR IFR UPGRADE DETECTOR ASSEMBLING AND MOUNTING.
October 21, 2003LST Mechanical Design Review - SLACN. Yu BaBar IFR Upgrades An FEA Study of the Effects of Adding Brass Plates in the IFR.
10/21/03H.J. Krebs1 LST Mechanical Design Review Brass Absorber Design H.J. Krebs October 21, 2003.
MTF SLIT COMPONENTS Adjusting Blocks and Mounting Plate Steel Blocks
October 21, 2003H.J. Krebs1 LST Mechanical Design Review West Coast Team Mechanical Engineering and Design Manpower & Organization H. James Krebs October.
October 22, 2003H.J. Krebs1 LST Mechanical Design Review 2005 IR-2 Installation Discussion H.J. Krebs October 22, 2003.
BaBar: The Detector Richard F Boyce 21 October 2003.
2004 BRASS INSTALLATION HARDWARE. BRASS INSTALLATION FOR 2004 TOP AND BOTTOM SEXTANTS ONLY PROCEEDURE AND FIXTURES FOR TOP AND BOTTOM ARE SIMULAR.
May 5, 2004H.J. Krebs LST Installation Readiness Review 2004 IR-2 Installation Schedule H.J. Krebs May 5, 2004.
March 23, 2009H.J. Krebs1 BaBar D&D Schedule & Budget Overview H. James Krebs March 23, 2009.
May 4, 2004Bill Wisniewski1 Installation Review. May 4, 2004Bill Wisniewski2 Charge ( W. Althouse, G. Bowden, W. Innes(chair), J.Weisend, (D. Nelson))
October 22, 2003H.J. Krebs1 LST Mechanical Design Review Mechanical Installation Preparation H. James Krebs October 21, 2003.
General idea of a couple of check rod system and adjustments
ZDC Remote Handling System March 10, 2011 Project Status and Forward Planning Technical Implementation Group Meeting Paul Debbins University of Iowa.
May 5, 2004H.J. Krebs LST Installation Readiness Review Brass Absorber Production H.J. Krebs May 5, 2004.
08/24/07Shutdown’07 Week 3 F.G. Garcia1 MTA beam line installation Weekly Report August 24, 2007 Period covered: August 17 th to August 24 th (Week 3)
DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1.
IFR End Door Enhancement Mechanical Engineering Status & Installation Issues H. James Krebs June 23, 2001.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
Construction and Installation of the CLIC Experimental Area
C. Bromberg 1 Michigan State University Feb. 8, 2004 RPC Monolithic Detector l Most absorber shipped direct to the site äShipping minimized äHeavy (~20.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester Jun 4, 2012.
Integration GlueX Detector Integration Mission: To ensure systems meet or exceed physics driven goals To ensure that detectors are designed in a sensible.
LST Storage and Testing at SLAC in the SLD Hall Available space Available Infrastructure Needed Infrastructure Time Line People Money Carsten Hast (SLAC)
1 GLD Surface Assembly Y. Sugimoto KEK
October 21, 2003H.J. Krebs1 LST Mechanical Design Review Handling & Installation Fixtures Design and Fabrication Status H.J. Krebs October 10, 2003.
OK, now my favorite subject: RPCs in a shipping container
NuMI NBI2006 September 9, 2006 NuMI Repairs for Hot Components Jim Hylen / FNAL Page 1 NuMI Repairs for Hot Components (1 sievert = 100 rem) Problem On.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
September 18, 2007H. J. Krebs1 SiD Collaboration One Piece End Door Design Concept plus Forward Equipment Interfaces H. James Krebs SLAC September 18,
LST Upgrade LST Upgrade Readiness Review William Sands, Princeton University,
ORKA Preservation Task Force ORKA Preservation Task Force first meeting Wednesday, February 8, Notes by Peter H. Garbincius Notes from meeting are.
11/15/02H.J. Krebs IFR Improvement Phase II (Barrel) Mechanical Engineering Issues H. James Krebs November 15, 2002.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Baby MIND coil modules assembly the aluminium folded strip solution 1 Alexey, Philippe, Gabriella, Helder, Herman Baby Mind Magnet CERN June.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Ken Periman Problem solving, Sub frame bolt issue
The BaBar Upgrade Load transfer of the Barrel and Endcap Calorimeters Richard F Boyce 21 October 2003.
September 20, 2007H. J. Krebs/B. Wands/B. Cooper1 SiD Collaboration Preliminary End Door Design Concept Support of Forward Systems H. James Krebs Bob Wands.
M1 Central Part Cable Routing R3 FAR R2 CLOSE R2 FAR + GEM A3 B From chain GEM R2 CLOSE R2 FAR A1 20 A1 A1 A2 A CHAIN Access Front Dané.
SiD MDI Issues Tom Markiewicz/SLAC Beijing ACFA/GDE Meeting 05 February 2007.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
LSTs in the IFR gaps Workshop on IFR replacement SLAC November 14, 2002 L. Piemontese INFN Ferrara.
T2 Status Report IP5 Installation Future plans. IP5 installation The mechanical structure has shown problems on installation and should be changed slightly.
Rapid Change Technology The following is a presentation to aid Technicians in the replacement of the Rapid Change Technology Block.
Long-Baseline Neutrino Facility LBNF Beamline optimization schedule Vaia Papadimitriou LBNF Beamline Manager Accelerator and Beam Interface Group Meeting.
October 7, 2009H.J. Krebs1 Super B WorkShop Overview of BaBar Detector Assembly/Installation Documentation Jim Krebs.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
DTU A VISION OF SUPPORTING NEUTRON CHOPPER ESS PT 1 - BUNKER SYSTEMS Discussion Document.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
June 2, 2008 Bill Wisniewski1 BaBar Disassembly and Disposal Overview.
Comments on Services Elba Comments on Services & … Bill Wisniewski SLAC.
Introduction BaBar Components The Problem IFR Upgrade: 2004 & 2005
PANDA Collaboration Meeting , BINP Sergey Pivovarov.
News and brief overview of Beamline plans for the next few months
BaBar IFR Upgrade Mark Convery SLAC 7 Jun 06.
LST Mechanical Design Review
Integration and IR Hall
LST Module Installation
CSC Electronics Installation and Commissioning CSCE I&C
Removal of salon doors on 1968 Roamer Sedan.
8” MCP Flow for 8/7/ and -003 coated at Fermi and returned to ANL on 8/3/ and -050 packed and ready for Fermi courier to.
Limited Streamer Tube Project Summary
Bunker Wall Design Wall ESS
BaBar LST Upgrade Richard F Boyce
Polarized 3He target installation
Presentation transcript:

October 22, 2003H.J. Krebs1 LST Mechanical Design Review 2004 IR-2 Installation Schedule H.J. Krebs October 22, 2003

H.J. Krebs Installation Scope of work is located on top & bottom sextants –Remove 18 layers of RPCs –Install 6 layers of 7/8” thick brass absorber in layers 5,7,9,11,13 & 15 – 11.5 tons/sextant –Install LST detectors in layers 1,2,3,4,6,8,10,12,14,16,17 & 18 –An investigation will be performed at commencement of this down to determine if the layer 19 RPC can be retained at some functioning level

October 22, 2003H.J. Krebs Installation Schedules do not include any time for: –Post and pre-run PEP survey work In the past, this has been 2.5 to 3 work days –PPS certification In the past, this has been 4 days –Tours and photography sessions In 2002, we lost two days to this If tours or photography sessions are important, they may occur between midnight and 07:00 –LST commissioning 15 work days for bottom sextant 2 work days for top sextant –Replacement of any LST detectors that have problems after installation

October 22, 2003H.J. Krebs Installation Flux return steel –Side gap plates Have removed many times Very confident in schedule for these tasks –Center gap plates Have never removed before Very confident in schedule for these tasks –Corner plates Have never removed before Schedule times for these tasks are an educated guess Test removal of two corner block bolts in summer 2003 –Somewhat easy to remove –Bolt threads appear to be in excellent condition An unbolting/bolting sequence needs to be developed –Assume torquing these bolts 3 times during reinstallation –Helicoils Have had trouble with these in the past Assume a problem with 1% of helicoils –Means replacing two helicoils in 2004 –There is no time included in the schedule for helicoil replacement »Probably a few hours per helicoil replacement

October 22, 2003H.J. Krebs Installation Steel position –Shall be monitored to assure that the barrel assembly is stable –Some early thoughts on this Dial indicators at strategic locations Survey targets added at strategic locations –i.e., on mid corner blocks to see if structure is becoming egg shaped Take periodic measurements –At beginning for reference –After bolts are loosened on each corner plate –At the beginning of each day –At the beginning of second shift –At the end of each day –At end for final reference

October 22, 2003H.J. Krebs Installation RPC removal –RPCs are “ripped” out HV & gas line still connected on BWD end Time may be lost cleaning the steel gaps of this debris –Bottom RPCs must be ripped loose, then cut, then pulled, then cut, etc. Not enough space in Z to extract in one piece –RPCs range in weight from approximately 150 pounds for layer 1 to 250 pounds for layer 18 –3600 sq ft of RPCs will be removed –Cover FWD beamline and detector face for protection

October 22, 2003H.J. Krebs Installation Where do items go during the installation process? –Flux return steel to IR-12 –Flux return bolts There are approximately 232 bolts 1-1/2”-6UNC x 14” lg. Need to keep track of these Need to protect threads –Platforms and walkways along service road to Building 611 –Main shield wall blocks along the Loop Road –RPCs thrown out in the IR-2 parking lot Where do items come from during the installation process? –Steel handling fixtures from IR-12 –Elevator platforms from IR-12 –Brass absorber plates from IR-12 –LST detectors from SLD Collider Hall –Electronics and gas system from SLD Collider Hall

October 22, 2003H.J. Krebs Installation Schedules are based on: –Mechanical installation assumes two 8-hour shifts per day, six days per week (3 rd,6 th and last week one 10- hour shift) – very taxing –LST installation assumes one 10-hour shift per day, six days per week Mechanical installation team will provide support to LST team during this period and will also work one 10-hour shift per day, six days per week –Wireway installation, cabling and gas hookup will be performed on owl shift –Installation schedules denote IFR/LST work only Work by other systems must be performed during owl shift

October 22, 2003H.J. Krebs9 Hall Crew Actual Work Time (Two 8-hour Shifts) DaysActual Work Time minutes 0.11 hour 18 minutes hour 57 minutes 0.22 hours 36 minutes hours 15 minutes 0.33 hours 54 minutes hours 33 minutes 0.45 hours 12 minutes hours 51 minutes 0.56 hours 30 minutes hours 9 minutes 0.67 hours 48 minutes hours 27 minutes 0.79 hours 6 minutes hours 45 minutes hours 24 minutes hours 3 minutes hours 42 minutes hours 21 minutes 113 hours

October 22, 2003H.J. Krebs10 Hall Crew Actual Work Time (One 10-hour Shift) DaysActual Work Time minutes minutes hour 10 minutes 0.21 hour 33 minutes hour 56 minutes 0.32 hours 20 minutes hours 43 minutes 0.43 hours 6 minutes hours 29 minutes 0.53 hours 53 minutes hours 16 minutes 0.64 hours 39 minutes hours 2 minutes 0.75 hours 26 minutes hours 49 minutes 0.86 hours 12 minutes hours 36 minutes 0.96 hours 59 minutes hours 22 minutes 17 hours 45 hours

October 22, 2003H.J. Krebs Installation Schedule

October 22, 2003H.J. Krebs12 Open FWD and BWD End Doors

October 22, 2003H.J. Krebs13 Install EQ Braces & Remove IFR Cooling Loops Earthquaqe blocks are installed with shims. Earthquaqe blocks

October 22, 2003H.J. Krebs Installation Schedule

October 22, 2003H.J. Krebs15 Install Beam Line Protection, Remove Solenoid Support Arms Beam pipe protection can interfere with the man lift.

October 22, 2003H.J. Krebs Installation Schedule

October 22, 2003H.J. Krebs17 Remove Gap Plates, Upper Corner Blocks & Upper Flux Bar

October 22, 2003H.J. Krebs18 Remove Lower Corner Blocks & Lower Flux Bar Install Elevator Platform, Begin Brass Absorber and LST Installation

October 22, 2003H.J. Krebs Installation Schedule

October 22, 2003H.J. Krebs Installation

October 22, 2003H.J. Krebs Installation Schedule

October 22, 2003H.J. Krebs Installation Schedule

October 22, 2003H.J. Krebs Installation Schedule

October 22, 2003H.J. Krebs Installation Schedule

October 22, 2003H.J. Krebs Critical Path

October 22, 2003H.J. Krebs Critical Path

October 22, 2003H.J. Krebs Critical Path

October 22, 2003H.J. Krebs Critical Path

October 22, 2003H.J. Krebs Critical Path

October 22, 2003H.J. Krebs30 Conclusions and Comments 10 weeks of scheduled work time is needed to replace RPCs with 6 layers of brass absorber and 12 layers of LST detectors in both the top and bottom sextants if NOTHING goes wrong –Additional 4 days of PPS certification almost a certainty –Some time lost for tours and/or photography is a probability –No time allotted to replace LSTs that are not functioning properly after installation – overly optimistic –17 days allotted for commissioning of lower sextant LSTs but only 2 days are allotted for commissioning of upper sextant LSTs –Many tasks have NEVER been performed previously – could be a long learning curve –Will lose 1:1 on schedule time for any of the above There may be some schedule optimization possible – but not much. From the critical path it is determined that the schedule is: –Driven by crane usage – 1 crane –Driven by LST installation – 1 installation team –Most everyone is working in the same place – FWD end of barrel

October 22, 2003H.J. Krebs31 Conclusions and Comments Our mechanical installation team is aging –Have some young replacements but not as experienced A mechanical breakdown of the crane would have an adverse schedule effect An agreement must be worked out to deal with the VESDA system during this installation period –Have experienced significant schedule delays in the past by us setting off the fire alarms A two month down would result in a reduced scope of work –Only one sextant could have the brass absorber/LST replacement, or –Remove RPCs and replace with brass in both sextants but NO LST installation (just an opinion), or –Some other option Our goal is to be ready as early as possible to take advantage of any potential schedule advancement.