Giovanni Polese 1 HV cabling multiconductor connettorization (600 ch) : pretest and fixing: 1 month * 2 people connectorization: 2 months * 2 people HV cable-distrib: 1 month * 2 people people involved up to now: G. Passeggio, F. Cassese, A. Vanzanella A. Cimmino and P. Noli HV Patch Panel connection: 2 weeks * 2 people
Giovanni Polese 2 Power system Status New CAEN firmware 2.4. Is sync now OK ?? test in Napoli is OK ?? No offset change test at CERN next week !!! No news on the thermal drift !! LV tower cable installed (W ) 1 more LV board + 3 HV boards broken 2 HV crates in CR (W+2 and W+1) have been connectorized and are under test (A. Cimmino) 3 more HV crates will be worked by CPE ??
Giovanni Polese 3
4
5
6 LV cabling tower and tower-tower cabling installation: (1 week * 2 people)/wh 5 weeks LV test: (1 week * 2 people)/tw 10 weeks temp test: (1 week * 2 people)/wh. 5 weeks Infrastructure cabling and test (1 week * 2 people)/wheel 5 weeks
Giovanni Polese 7 HV & LV components status Log scale
Giovanni Polese 8 Components - numbers modelloordinaticonsegnatimancanti SY A MACISTE312 A3512N - HV BC A A CRATE34 0 A3000FB - FAN14 0 A3486S - MAO505 A LV60573 To modify Late delivery