B.P. BIS Commissioning in point 8: follow-up 1 of 16 BIS Commissioning in Point 8 on week#17 (21st-> 25th April 08) 2 Controllers for LHC-ring BIS: 26.

Slides:



Advertisements
Similar presentations
RS-485 Data Link Tester Team Members:Raymond Weber Lance Spotted Elk Sponsor:LED Effects.
Advertisements

1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
Etienne CARLIER AB/BT/EC
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
A. Castañeda 07 th September 2009 Generators and Detectors Permit Loop / CIBG / CIBO 0v0.
The Architecture, Design and Realisation of the LHC Beam Interlock System Machine Protection Review – 12 th April 2005.
January 2006Beam dump and injection inhibits / J.Wenninger1 Beam Dump and Injection Inhibits J. Wenninger AB-OP & D. Macina TS-LEA LHC experiments signals.
Status of the Roman Pot Movement System and the Interlocks Mario Deile
Status of Data Exchange Implementation in ALICE David Evans LEADE 26 th March 2007.
RF voltage and frequency interlocks A. Butterworth MP review 17/6/2010.
Beam Interlock System PR b-CTM, October 7th, 2010 Cesar Torcato de Matos.
B. Todd et al. 25 th August 2009 Observations Since v1.
B. Todd on behalf of TE/MPE/MI 25 th May 2009 Beam Interlock System Changes Following 2006 Audit 1v0.
1 Chap. 3 Interface. 2 Interface  Physical connection between node and transceiver  Network interface card (NIC)  Physical connection between transceivers.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
1 VeLo L1 Read Out Guido Haefeli VeLo Comprehensive Review 27/28 January 2003.
1 Interlock logic for LHC injection: intensity limitations Jörg Wenninger AB-OP-SPS Outcome of the join Machine-Experiments Workshop on Machine Protection.
Kicker generator and controls installation in ECA5? Etienne CARLIER
B. Todd AB/CO/MI BIS Audit 18 th September 2006 Signal Integrity Electro-Magnetic Compatibility Dependability.
BP & RS: BIS & SLP for AB/CO Review, 23 h Sept Realisation of the interlocking between SPS, LHC and CNGS and open issues Beam Interlock Systems.
Interlocks for Magnet Protection System Iván Romera Ramírez, Markus Zerlauth - CERN.
Machine Interlocks Upgrading MPE workshopChristophe MARTIN14 th Dec
LLRF FOR CHOPPER Grégoire Hagmann Philippe Baudrenghien BE/RF/FB February 24th, 2013.
Isabelle Laugier, AT/VAC/ICM Section May 6 th 2008 LHC Vacuum Control system.
Product development Engineering & Regulatory Raj Agrawal InnAccel.
BLM “sunglasses” Filter Box. Current layout: BLM crates CIBU units Rack BY02 / SR8 BIC crate ( UA83 ) User_Permits Maskable channel Unmaskable channel.
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
Stéphane Gabourin on behalf of TE/MPE-EP MPP Linac4 – 9 th July 2015 BIS installation in Linac4 For 50 MeV operation.
Overview Extraction tests: TT40 and TT60, week 21 –controls and data, interlocking, extraction, MKE6 transfer function and energy tracking, high intensity,
LIU-PSB BIS presentation / Christophe Martin TE-MPE-EP 28/02/ Beam Interlock System for Transfer Lines & PS Booster Christophe Martin TE/MPE/EP.
Christophe Martin TE-MPE-EP 02/06/ The BIS and SMP activities during LS1 MPE Group Review, 2 June 2015 Christophe Martin, Stephane Gabourin & Nicolas.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
CERN Andrea Apollonio page 1 MACHINE PROTECTION CONSIDERATIONS FOR 50 MeV LINAC4 BIS COMMISSIONING A.Apollonio, B. Mikulec, C. Martin, B. Puccio, F. Roncarolo,
BIS main electronic modules - Oriented Linac4 - Stéphane Gabourin TE/MPE-EP Workshop on Beam Interlock Systems Jan 2015.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
New PSB beam control BIS Interlocks A. Blas PSB Beam Control 20/01/ BIS: Beam Interlock.
23/06/2011 Linac4 BCC meeting. 23/06/2011 Linac4 BCC meeting Watchdog = Machine protection element whose function is to cut the beam if losses exceed.
The LHCb Online Framework for Global Operational Control and Experiment Protection F. Alessio, R. Jacobsson, CERN, Switzerland S. Schleich, TU Dortmund,
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
LDR 531 Week 3 Summary R-531/LDR-531-Week-3-Summary For more details
0v1.
Data providers Volume & Type of Analysis Kickers
The TV Beam Observation system - BTV
Beam Interlock System SPS CIBU Connection Review
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Overview of the Beam Interlock System
Overview of CERN BIS and Communication Hardware
Injectors BLM system: PS Ring installation at EYETS
Configuration Management and Layout Database ELENA Project
LINAC4 50 MeV phase BIS STATUS
RF interlocks for higher intensities (LMC 15 June)
B.Todd, M. Zerlauth, I. Romera, A. Castaneda
1v0.
Safe mode transmission
Hot Checkout System for LERF Resuscitation
Powering from short circuit tests up to nominal
Commissioning and Testing the LHC Beam Interlock System
0v1.
MPSC Procedures An update
Test and start‐up procedures
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Beam Dump and Injection Inhibits
Design Specification Document
Signal Conditioning.
Interlocking of LHC experiments
Beam Interlocks for Detectors and Movable Devices
The LHC Beam Interlock System
Interlocking strategy
Safety Readiness Review (SRR) Thomas Hansson, ESH
SPS Injection BIS - Draft requirements
Presentation transcript:

B.P. BIS Commissioning in point 8: follow-up 1 of 16 BIS Commissioning in Point 8 on week#17 (21st-> 25th April 08) 2 Controllers for LHC-ring BIS: 26 links in total 1 Controller for LHC-ring BIS: 7 available links

B.P. BIS Commissioning in point 8: follow-up 2 of 16 Commissioning Procedure

B.P. BIS Commissioning in point 8: follow-up 3 of 16 CIBU Documentation

B.P. BIS Commissioning in point 8: follow-up 4 of 16 Input current limits

B.P. BIS Commissioning in point 8: follow-up 5 of 16 CIBU Input Specifications

B.P. BIS Commissioning in point 8: follow-up 6 of 16 EMC Compliance of interconnection

B.P. BIS Commissioning in point 8: follow-up 7 of 16 Electrical Architecture CIBU User System In USER rackIn INTERLOCK rackCable

B.P. BIS Commissioning in point 8: follow-up 8 of 16 Testing with ‘A’ and ‘B’

B.P. BIS Commissioning in point 8: follow-up 9 of 16 Testing with ‘A’ and ‘B’

B.P. BIS Commissioning in point 8: follow-up 10 of 16 Testing with ‘A’ and ‘B’ User System to User Interface TEST in the same way

B.P. BIS Commissioning in point 8: follow-up 11 of 16 BIS Commissioning: MTF steps (summary) 1. System (controller level) has completed IST 2-1. Reception of USER SYSTEM Inputs: Beam 1 (IST) 2-2. Reception of USER SYSTEM Inputs: Beam 2 (IST) 3-1. Verification of USER_PERMIT and CIBU functional response: Beam Verification of USER_PERMIT and CIBU functional response: Beam BIC BEAM_PERMIT (BP) response to USER_PERMITs (UPs): Beam BIC BEAM_PERMIT (BP) response to USER_PERMITs (UPs): Beam Transmission of BEAM_PERMIT_INFO(BPI) to User System: Beam Transmission of BEAM_PERMIT_INFO(BPI) to User System: Beam 2

B.P. BIS Commissioning in point 8: follow-up 12 of 16 BIS Commissioning: MTF steps 3 & 4 (details) Step Value Units Comments CIBU_V for A: A=T & B=F 4>x <30 V Verify cable voltage at input-A (CIBU): USER_PERMIT_A = TRUE & USER_PERMIT_B = FALSE CIBU_I for A: A=T & B=F >9 mA Verify current at input-A (CIBU): USER_PERMIT_A = TRUE & USER_PERMIT_B = FALSE CIBU_V for B: A=T & B=F <1 V Verify cable voltage at input-B (CIBU): USER_PERMIT_A = TRUE & USER_PERMIT_B = FALSE CIBU_I for B: A=T & B=F <1 mA Verify current at input-B (CIBU): USER_PERMIT_A = TRUE & USER_PERMIT_B = FALSE Glitch Counter: A=T & B=F OK/Not OKVerify Glitch Counter for both input-A & input-B: USER_PERMIT_A = TRUE & USER_PERMIT_B = FALSE BIC response: A=T & B=F OK/Not OKVerify BIC response for both input-A & input-B: USER_PERMIT_A = TRUE & USER_PERMIT_B = FALSE History Buffer: A=T & B=F OK/Not OKVerify History buffer should show a trouble-free transition: USER_PERMIT_A = TRUE & USER_PERMIT_B = FALSE Re-do the above sequence with USER_PERMIT_A = FALSE & USER_PERMIT_B = TRUE

B.P. BIS Commissioning in point 8: follow-up 13 of 16 Verification in the BIC’s History buffer occurrence time

B.P. BIS Commissioning in point 8: follow-up 14 of 16 Measured values for A Input (when A=True) CIBUS.UA83.L8WIC23.60 Volts13.95 mA CIBUS.UA83.L8Vacuum b1b CIBUS.UA87.R8Vacuum b1b CIBUS.UA87.R8LHCb_DET CIBUS.UA87.R8LHCb_Mov CIBUS.UA87.R8LHCb_Mag CIBUS.UA83.L8PICL_MSK CIBUS.UA83.L8PICL_UNM CIBUS.UA87.R8PICR_MSK CIBUS.UA87.R8PICR_UNM CIBUS.UA83.L8BLM_MSK CIBUS.UA83.L8BLM_UNM CIBUD.UA87.R8BTV-b CIBUS.SR8.INJ2COLL_MOT-b CIBUS.SR8.INJ2COLL_ENV-b CIBUS.SR8.INJ2Vacuum b CIBUS.SR8.INJ2LHCb Injection Inhibit CIBUS.SR8.INJ2MKI CIB.UA83.L8.B1.B2COLL_MOT-b1-b CIB.UA87.R8.B1.B2COLL_MOT-b1-b CIB.UA83.L8.B1.B2COLL_ENV-b1-b CIB.UA87.R8.B1.B2COLL_ENV-b1-b CIB.UA83.L8.B1.B2Vacuum b1-b CIB.UA87.R8.B1.B2Vacuum b1-b

B.P. BIS Commissioning in point 8: follow-up 15 of 16 summing up ●Fruitful collaboration BIS  User Systems ●Most of the links (LHC-ring BIS) have been validated – LHCb Detector & Velo: both OK – LHCb Magnet signal out of limits => test postponed ●Links for Injection Inhibit partially done: – CIBU for Beam-2 Inhibit: input signals OK – CIBF for Beam-1 Inhibit: input signals OK – Tests are going to continued when cable and F.O. will be in place.