1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Accelerator Installation Plan Gregory Fries Project Engineer, Accelerator Systems Division CFAC Review of NSLS-II.

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Transition to Operations Erik D. Johnson, Deputy ALD for Programs Science Advisory Committee April 4, 2011.
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Beneficial Occupancy Readiness Evaluation Plan Update Brian Heneveld, P.E., CIH NSLS-II BORE Coordinator Conventional.
1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring - Conventional Facilities Interfaces Erik Johnson, Accelerator Systems Interface Manager Accelerator Systems.
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
1 BROOKHAVEN SCIENCE ASSOCIATES As-Built Drawings and Commissioning Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Vacuum Systems H.C. Hseuh, Vacuum Group Leader 8 th ASAC Meeting for NSLS-II Project May 10-11, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11,
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II EFAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES Plans for LOBs and Site Master Plan Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11,
1 BROOKHAVEN SCIENCE ASSOCIATES CF Role in NSLS-II Operations Marty Fallier Conventional Facilities Advisory Committee Review October 5-6, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II ASAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
1 BROOKHAVEN SCIENCE ASSOCIATES Transition to Installation Erik Johnson ASD Deputy Director and Interface Manager NSLS-II CFAC Meeting November 9-10, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Status Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Accelerator.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Status & Charge to ASAC Steve Dierker Associate Laboratory Director for Light Sources, NSLS-II Project Director.
Global Design Effort Beam Delivery System => EDR LCWS07 June 2, 2007 at DESY Andrei Seryi for BDS Area leaders Deepa Angal-Kalinin, A.S., Hitoshi Yamamoto.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review – Title II Design Status Ove Dyling Assistant Director for Design Conventional Facilities NSLS-II Conventional.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Update Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities NSLS-II Conventional Facilities Update May 8, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Installation & Integrated Testing Status & Plans Gregory Fries, ASD Project Engineer 9 th ASAC meeting for NSLS-II Project.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Steve Dierker Director, NSLS-II Conventional Facilities Division NSLS-II User Workshop July 17,
1 BROOKHAVEN SCIENCE ASSOCIATES Redundancy Requirements for Critical Devices R. Casey August 8, 2007.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Procurement David Dale Procurement Manager NSLS-II Project Project Advisory Committee November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES ASAC Meeting NSLS-II Project July , 2008 G. Ganetis Power Supplies & Electrical Utilities ASAC Meeting National Synchrotron.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Overview Satoshi Ozaki Director, Accelerator Systems Division NSLS-II Project March 27, 2007.
Transport of the CLIC Modules and Elements CLIC Workshop October 2007 Two Beam Hardware and Integration Working Group Keith Kershaw (CERN)
1 BROOKHAVEN SCIENCE ASSOCIATES CF FY09 Work Plan & Schedule Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES EFAC Review Conventional Facilities Update Marty Fallier Director for Conventional Facilities May 10, 2007.
BDS: 1 October 13, 2007 BDS KOM EDR planning discussion Andrei Seryi October 13, 2007.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities Schedule Review December 13, 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Installation Gregory Fries, Project Engineer 8 th ASAC meeting for NSLS-II Project May 10-11, 2011.
1 BROOKHAVEN SCIENCE ASSOCIATES Getting the NSLS-II Accelerator ‘on-line’ Erik Johnson, Steve Hoey, Ferdinand Willeke NSLS-II PAC Meeting December 10-11,
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer Review of ESS Accelerator Conventional Facility Design.
1 BROOKHAVEN SCIENCE ASSOCIATES Beam Stability Overview NSLS-II CFAC Meeting May 8, 2007 S. Krinsky.
WBS – 30 Straight Section Reconfiguration g-2 Accelerator – 30 Straight Section Reconfiguration D. Still Fermilab Muon g-2 IDR, June 5-7.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Ferdinand Willeke Director, NSLS-II Accelerator Systems NSLS-II PAC Meeting November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
Cryomodule test stand at ESS site
Installation Global System
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
Renovation of the 45-year old PS magnets
XFEL Vacuum System Commissioning
Undulator System Installation
Presentation transcript:

1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Accelerator Installation Plan Gregory Fries Project Engineer, Accelerator Systems Division CFAC Review of NSLS-II October 5-6, 2010

2 BROOKHAVEN SCIENCE ASSOCIATES Outline Phasing of Installation Coordination with Conventional Facilities Storage Ring Installation Injector Installation Storage and Rigging Installation Schedule Experimental Installation Potential Obstacles Summary

3 BROOKHAVEN SCIENCE ASSOCIATES Phasing of Construction and Installation Beneficial Occupancy Installation

4 BROOKHAVEN SCIENCE ASSOCIATES Installation and Operation Zones Key Points: Utilities and infrastructure are segmented as shown BOD handovers aligned with support infrastructure Installation and testing within these segments Linac/Booster test/commission may overlap with construction activities 1 2 B L RF

5 BROOKHAVEN SCIENCE ASSOCIATES Coordination with Conventional Facilities Lay-down area for storage containers outside of building Beneficial occupancy conditions for installation Systematic hand-off of completed building zones BNL BORE process to be used for occupancy permits Access to space with beneficial occupancy for installation while construction continues Interaction of installation activity with LOB construction to avoid potential interference CFD represented in ASD installation meetings (O. Dyling) ASD reviewing all CFD ECNs for impact ASD installation coordinator named

6 BROOKHAVEN SCIENCE ASSOCIATES Key Aspects of Production and Installation Accelerator Production – We procure injector sub-systems (Linac, Booster Ring) We build (integrate) Transfer Lines, B-RF and SR components Accelerator Installation – Storage Ring BNL Storage Ring RF BNL Booster RF BNL Transport Lines BNL Linac Vendor w/ BNL oversight Booster Ring Vendor using BNL technicians for all hands–on work w/ BNL oversight

7 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Systems Installation Per Pentant Mechanical Utilities Electrical Utilities Magnet/Girder Assemblies RF Systems Vacuum System Power Supplies Beam Instrumentation Beam Line FEs, DWs, IDs (where applicable) Injection Straight

8 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Pentant 1 Installation: Week Exp’l floor Tunnel Service Building Mezzanine 23 Status: ~ 1/3 of material in building Installation starting 26 Activities: Prepare tunnel Stage components on floor Start cable tray on mezzanine 2

9 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Pentant 1 Installation: Week Exp’l floor Tunnel Service Building Mezzanine 23 Status: Most material in building Installation on mezzanine Installation in tunnel 26 Activities: Tray and manifolds in place in tunnel Racks well underway Stage cable and start pulling

10 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Pentant 1 Installation: Week Exp’l floor Tunnel Service Building Mezzanine 23 Status: Most wiring pulled Process utilities connected 26 Activities: Girder installation Populating racks Terminating cables

11 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Pentant 1 Installation: Week Exp’l floor Tunnel Service Building Mezzanine 23 Status: About 2/3 vacuum complete 26 Activities: Girder installation Cable pulls all done Testing underway

12 BROOKHAVEN SCIENCE ASSOCIATES Injector Installation Phases Mechanical & Electrical Utilities Booster RF LtB Transport Line Part 1 Through wall, up to vac valve in booster vault, needed to commission linac Linac Booster LtB Transport Line Part 2 TL complete, need to commission booster BtS Transport line Part 1 Up to beam dump, needed to commission booster

13 BROOKHAVEN SCIENCE ASSOCIATES Injector Installation Phases Layout Linac Booster LtB TL Part 1 Phase Separation BtS TL Part 1 Booster RF Phase Separation (end of injector install) LtB TL Part 2

14 BROOKHAVEN SCIENCE ASSOCIATES Component Storage & Staging Reviewing storage requirements for each ASD group Finalizing number of sea containers needed at site for storage Approx ft x 8 ft x 40 ft containers Experimental floor will be used for staging Temporary cages may be installed

15 BROOKHAVEN SCIENCE ASSOCIATES Lay-down Areas for Sea Containers Lay-down Area for SR Component Storage Containers Lay-down Area for Linac & Booster Containers Outside Access to Experimental Floor for Unloading

16 BROOKHAVEN SCIENCE ASSOCIATES Rigging Requirements ItemQty.UOMDate Hours (team) Total Hours (team) Weight (lbs) Total Weight (lbs) DimensionsFromToComments RF Group SR Transmitter1EAJun-11885,000 6 x 2 x 2.3m tentative TruckRF Building SR Transmitter1EATBD885,000 6 x 2 x 2.3m tentative TruckRF Building SR Transmitter Transformer1EAJun-11225,500 TruckRF BuildingInstalled separately SR Transmitter Transformer1EATBD225,500 TruckRF BuildingInstalled separately SR Klystron1EAJun-11442,750 TruckRF BuildingHorizontal-to-Vertical SR Klystron1EATBD442,750 TruckRF BuildingHorizontal-to-Vertical SR Cavity1EAAug ,000 Truck RF Straight in Tunnel Installed in 20cm trench SR Cavity1EANov ,000 Truck832Installed in 20cm trench Cold Box1EANov-11885,600 Truck RF Building - Cryo Mezzanine Requires special forklift to 20', unit for rent identified by Bob Sikora Dewar1EANov-11443,800 ` RF Building - Cryo Mezzanine Valve Box2EANov ,3006,600 Truck Tunnel Mezzanine at RF Verify difficulty to get on mezzanine Booster Transmitter1EADec-11885,000 TruckInjector RF Building Booster Cavity1EADec-11442, Booster Tunnel As soon as tunnel is available; preceeds transmitter

17 BROOKHAVEN SCIENCE ASSOCIATES Rigging Summary & Status Reviewed requirements with the riggers Will have two dedicated 3-man rigging teams ASD installation coordinator will be contact to riggers Rigging requirements will continue to be detailed

18 BROOKHAVEN SCIENCE ASSOCIATES Component Transport Forklift has been ordered 10,000 lbs. capacity 208” max lift to reach mezzanine from experimental floor Dolly system will be used for magnet/girder assembly transport

19 BROOKHAVEN SCIENCE ASSOCIATES Installation, Testing & Commissioning Schedule

20 BROOKHAVEN SCIENCE ASSOCIATES Installation Schedule Installation schedule currently being reviewed with each CAM and expanded for completeness, durations and logic Emphasis will be placed on installation schedule flexibility based on building and component availability

21 BROOKHAVEN SCIENCE ASSOCIATES Experimental Installation XFD Installation follows ASD installation by pentant Activities Per Beamline Pentant Hand-off from ASD Pentant Clean-up Hutches Utilities Beamline Components

22 BROOKHAVEN SCIENCE ASSOCIATES Potential Obstacles Coordinating multiple activities/teams/access during installation Maintaining component delivery schedules Will epoxy floor installation on experimental floor impact ASD installation schedule? XFD installation needs might conflict with required flexibility of ASD installation schedule (hand-over delays)

23 BROOKHAVEN SCIENCE ASSOCIATES Summary Installation schedule in process of being expanded and re- evaluated Focus on flexibility in installation schedule based on availability of building and components Building to be available for start of ASD installation Feb ‘11 Detailing installation logistics Rigging and storage requirements in process Good communication established with CFD & XFD Conclusion: Installation Planning is very advanced