Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Weekly summary Summary Week /19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1.
Saturday 6:13 – 15:00 STABLE BEAMS  scans etc. 15:00 moved to ADJUST Squeeze to 2 m in two steps 11 – 5 – 2  remarkably smooth  tertiary collimators.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
17/09/2012LHC 8:30 meeting LHC Summary Week 37 Coordination: Jorg Wenninger & Jan Uythoven.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
Saturday 7ish – refill for RP set-up 9:15 Going for Roman pot alignment. Stefano is coming. 12:10 TOTEM: Alignment of horizontal RPs B2 finished, short.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
Fri – Sat - Sunday 30 Sept - 2 nd October Friday  06:00 Operator dump fill #2171, integrated lumi 75 pb-1.  90 m  * optics Optics ok, collisions at.
Friday 2 nd November 08:45 Stable beams Fill 3253 Initial luminosity ~7.3e33 cm-2s-1 09:45 Increase RF voltage from 10 MV to 12 MV 12:00 ADT to wideband.
● Morning: Physics fill with 25 bunches: – 07:00: Injection; – 07:25: Start ramp; – 09:00: End of squeeze and stable beams; – Emittances:  x1 = 3.0 
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
From yesterday LHC status Wednesday 26 th Welcome Verena back on shift 07:08 Access in PM85 for piquet EPC (O.Fournier).  Fuse on RD2.R8 circuit.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
– Machine closed. Ramp for powering tests & pre-cycle – Pilots through nominal cycle up to collisions. Measure chroma during squeeze. Check dump of pilots.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.
Saturday 14:10 Cryogenics back [26 hours 40 minutes] Pre-cycle 15:30 Beam 2 in  Interlock on TCLIB.6R2.B1. Alessandro Masi found a broken sensor, it would.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
28/01/2013LHC 8:30 meeting Summary of Week 4 pPb physics Machine Coordination: Mike Lamont & Jan Uythoven Ion coordination: John Jowett.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Tuesday 7 th August - morning 07:10 Reinjection after loss of fill 2920 to UFO near ALICE  26 pb -1 in 1h16m; peak lumi 6.4e33 cm -2 s -1 08:10 dump at.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
Wed :55 Fill 2653 stable beams 1.40e11 ppb, cm-2s-1peak lumi, 11.6 pb-1 total lumi delivered. 09:31 Dumped by collimator interlock:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Tuesday 11th September LHCb dipole presently fault off
Monday 11/07: Recovery Plenty of accesses.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Thursday morning 09:30 Dump of pPb fill.
Lost at 12:05 to power converter (RTQX2.R1) problem
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Wire almost entirely through beam before BLM triggers dump
Friday Morning 7:30 injection for fill 2908
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
LHC Morning Meeting - G. Arduini
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Thursday 26th July 13:21 Fill 2880 beam dumped
Friday 07:00 Fill 1729 dumped. Movement device allowed flag switching to FALSE. From the logs, it seems the energy went to FFFF/7860 GeV. To be confirmed.
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Thursday 22 September 2011.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 16th May 03:05 beam dump, RF fault crowbar problem on module M1B2 06:09 Another crowbar at injection. Access for RF; problem Beam Imminent Warning.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Another Immortal Fill….
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
Presentation transcript:

Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started, RF tests with higher HV 13:00 RF access for klystron problem (not related) 16:00 Starting injection, Problems with ions, timing events not sent out correctly. 18:30 Filling ions. 19:00 Start of ramp. Lost the beam on TCT position interlocks. QPS problems. RF problems. 22:52 at 4 TeV with 15 p and 15 Pb bunches 00:50 Start of loss maps 01:26 Stable beams, first time pPb LHC 8:30 meeting 13/09/2012

RF – mixed bag of tests and problems Run with higher HV to test for larger RF power requirement with (more) 25 ns bunches  The klystron high voltage setting was raised from 50 to 58 kV in preparation for the 25 ns ramp. No issues were observed. Philippe, Themis, John M1B1 went in fault for a problem on the klystron filament heater.  Suspect non-identified dodgy connector  Not related to HV tests Struggling with B2/Pb injection. There is a problem with the timing system that does not transmit the RF ring/bucket information at the correct time. With some manual tweaks we manage to get in 2 Pb bunches. Klystron filament problem back in the evening  Klystron 2B1 is disabled by the RF experts  Replace modulator BEFORE going back to high intensity. 1 hour LHC 8:30 meeting 13/09/2012

19:14 First ramp pPb started 19:16, dumped at 626 GeV Collimator functions / limits not coherent  Beams dumped  Move back to standard, tighter collimator settings for next fill Blow-up during the ramp over-doing it with the small bunch length at the start  Re-program for next ramp LHC 8:30 meeting 13/09/2012

Second pPb ramp 4 TeV 23:00 Re-phasing – found collisions 00:50 Start of loss maps 01:26 Stable beams, first time pPb  Lumi’s approaching 10^26 cm-2s-1 LHC 8:30 meeting 13/09/2012

Fill continued 02:44 LHCb switched on SMOG gas injection 06:00 Displace collision point by - 50 cm  We made 4 trims of -120 degrees (400 MHz) on ring 1 (w.r.t. ring 2). That displaces the collision point by half the value, that is 240 degrees at 400 MHz or -50 cm.  07:40 Moved collision point to +50 cm LHC 8:30 meeting 13/09/2012 Lumi from logging, calibration to be verified

ALICE event LHC 8:30 meeting 13/09/2012 Hannes Wessels

The Plan (updated after the meeting) Thursday, Today  pPb pilot run – 13 bunches colliding each beam, expect to finish around 9:30  Replace RF modulator during ramp down (1h)  1000 m beta*, few bunches (if all goes well, until 08:00) Friday  09:00: pPb MD with 318 p+ bunches w. 4 Pb bunches (1 shift max)  Test ramp, reversed LHCb polarity and split collision beam process SPS switched over to Q20 optics  Physics Saturday & Sunday: Physics Monday 06:00 dump for start of Technical Stop 3 LHC 8:30 meeting 13/09/2012