1 The Utility Breaker Tim Heard DDC Engineer AEP Texas SWEDE 2006.

Slides:



Advertisements
Similar presentations
Control Circuit Protection Supplementary Protectors vs
Advertisements

Utilizing IED Capability to Reduce Wiring Terrence Smith, GE Digital Energy Multilin Richard Hunt, GE Digital Energy Multilin Jakov Vico, GE Digital Energy.
BACKGROUND: We are finding an increase in instances where the available fault current at underground (UG) 1-phase residential service entrance equipment.
A Path breaking Technology for Network Maintenance and Optimization
Cigré/Brasil CE B5 – Proteção e Automação Seminário Interno de Preparação para o Colóquio de Madri 2007 Rio de Janeiro, outubro/07.
Transmission Operator Protection System Misoperations 2014 ERCOT Transmission Protections System Misoperations Data – 138kV and 345kV Combined (Not including.
Tuesday 13 th December 2005 Substation SB400. Final testing in 10Kv substation.
 E4 Electrical Installation #1 Power Distribution.
MIFII DIGITAL FEEDER PROTECTION A Cost Effective Protection Solution for Overcurrent Protection at Any Voltage Level GE Multilin
Ward 21 Reliability Cedarvale and Surrounding Area Prepared for Councillor Mihevc Toronto Hydro System Planning March 25, 2015.
© American Standard Inc. CAUSES AND EFFECTS OF DEFERRED MAINTENCE s Texas Association of Community Schools s Houston, Texas s October 20, 2014 Greg Spencer.
1 Distributed Generation and Power Quality. 2 Relaying considerations DG infeed may reduce the reach of overcurrent relays –DG feeds fault, so utility.
RT3b – André Smit, Siemens USA
W650 Wind Generator Protection System
King Abdul Aziz University College of Engineering Electrical and Computer Department EE 454 SWITCHG.& PROT. OF PWR. SYS. Lectures Book Dr. ABDULRAHMAN.
Tap Conductor Rules.
1 BROOKHAVEN SCIENCE ASSOCIATES Electrical Power Status Thomas Nehring Conventional Facilities Advisory Committee Review October 5-6, 2010.
Nelson Hydro Downtown Conversion July 26, 2010 Project Overview.
1 Distribution Automation Survey Presented at SWEDE Conference 2005 By Kevin Clark.
1 1 Substation Asset Strategy Kevin Dasso, Senior Director Engineering and Operations IEEE/PES Annual Substations Committee Meeting April 7, 2008.
IMPACTS OF LARGE DISTRIBUTED GENERATORS ON CENTERPOINT ENERGY’S DISTRIBUTION SYSTEM 1 Presented by Ed Briggs, P.E. Manager of Electric Distribution Planning.
1 PCA2 On-load Protection Condition Analyser. 2 PCA2 online testing concept Concept introduction: PCA2 is a new system test approach intended to save.
SUBSTATION MODELING: PROTECTION AND AUTOMATION
1 CREZ COMMUNICATIONS Presented by American Electric Power Telecommunications Engineering Matt WilliamsDon Demand Columbus, OHTulsa, OK.
Interconnect Protection of Dispersed Generators
THE ELECTRIC SUB STATION
1 Power Quality Mary Santori, P.E. Senior Engineer September 12, 2013.
Engineer Training XL1200 Electric. Engineer Training XL1200 Electric Confidential 2 Block Diagram.
SWEDE - April 26 th, Bastrop Tommy Nylec Austin Energy Fusing and Fault Indicator Applications.
Electrical & High Temperature Utility Distribution Upgrade.
All rights reserved MV SWITCHGEAR.
Texasheart.org Main Substation (MSS1) 13,800 volts Analogies: Chest Pain = Corona Minor Stroke = Tracking Cardiac Arrest = Arcing (may not be able to resuscitate.
© ABB PTMV - 1, ABB Overhead Distribution Systems.
SWEDE 2014 Remote Monitoring of Faults – Frank Daniel (Oncor)
Oncor Electric Delivery Intelligent Grid at Oncor Electric Delivery SWEDE Conference Alan Bern – SCADA / Automation Manager May 1, 2008.
Substation Inspection Program. Mission Substation Incident The event occurred on December 20, 2003 during the peak Christmas shopping season A fire occurred.
What is a SUBSTATION ?. . These are excellent questions! Let’s deal with them one at a time. What is a substation? … what does it do? … how does it work?
EE 445 Course Presentation Power System Protection
Frankfurt (Germany), 6-9 June 2011 Louise Jakobsen, Danish Energy Association – Denmark – Session 3 – Paper 0811 Louise Jakobsen, Danish Energy Association.
Power Plant Construction and QA/QC Section 4.4 – In-Plant Electrical Distribution Engineering Technology Division.
Utility Engineers, PC.  Generation  Transmission  Distribution.
1 Distributed Generation and Power Quality-Continued.
POWER HOUSE.
Jesus A. Guerra, P.E. Distribution System Reliability CenterPoint Energy SWEDE 2011.
Introduction to switchgears
A PRESENTATION OF PRACTICAL TRAINING ON “400KV GSS “ \
SUBSTATION LAYOUT AND ACCESSORIES
SEMINAR PRESENTATION ON 220 KV GSS UDAIPUR
SERVICE ENTRANCE EQUIPMENT
ON 400 KV GSS RAISER JAIPUR ROAD ,BIKANER
A Training Presentation On 132 KV GSS JAIPUR Submitted in partial fulfillment For the award of the degree of BACHELOR OF TECHNOLOGY Submitted To:- Submitted.
A SEMINAR ON 400 KV GSS(RRVPNL) BIKANER.
1 Industrial Systems BUS2000 Busbar Differential Protection System Differential overcurrent system with percentage restraint protection.
Bywater Reliability Update Gary Huntley Entergy New Orleans, Inc. Regional Manager Entergy New Orleans, Inc. July 28, 2010.
Presentation Topic: Circuit Breakers Represented to: Dr. M. Riaz Khan Represented by: M. Mujahid.
ECE 498HZ: Power Distribution System Analysis
Protection of Power Systems
Increased Reliability of EHV Systems through Station Switchable Spare Transformer and Shunt Reactor Design and Operation Olivia Welcome & introduction.
This picture shows what the wiring of a new alternator looks like
Interconnect Protection of Dispersed Generators
Engineering Technology Division
35kV Assessment SWEDE 2007 May 10, 2007.
Mersen’s Fused Coordination Panelboard
Reliability Valuation in AEP Texas
Georgia Tech Protective Relaying Conference May 2, 2018
EUS 260 Capstone Project.
Repairing the Electrical Components
Presentation transcript:

1 The Utility Breaker Tim Heard DDC Engineer AEP Texas SWEDE 2006

2 Introduction A Utility Breaker is a spare breaker that can be used as a: Feeder replacement breaker Totalizing breaker Bus tie breaker

3 History Mid 1960’s-CPL began installing utility breakers Utility breakers removed from substation design standard Today- 41 Utility breakers available for service in TCC (old CPL) 0 Utility breakers in TNC (old WTU)

4 SCADA 1-LINE OUT OF SERVICE

5 SCADA 1-LINE AS FDR REPLACEMENT

6 SCADA 1-LINE AS TOTALIZER

7 SCADA 1-LINE AS BUS TIE

8 PICTURE OF SWITCHES

9

10 PICTURE OF SWITCHES

11

12

13 PICTURE OF CONTROL PANEL

14 PICTURE OF SELECTOR SWITCH

15 Relay Transfer Switch

16 Relay Transfer Switch Operations Utility Breaker CT secondaries are switched to Utility Breaker overcurrent relays. Utility Breaker relay trips are switched to Utility Breaker trip coil.

17 Relay Transfer Switch Operations Utility Breaker CT secondaries are switched to #3 Transformer Differential Relays and #3 Transformer Totalizing relays. #3 Differential trips and Totalizing trips are switched to Utility Breaker trip coil.

18 Relay Transfer Switch Operations Utility Breaker CT secondaries are shorted. Utility Breaker overcurrent relay trips remain switched to Utility Breaker trip coil.

19 Utility Breaker Cost Installation costs is 40%-50% higher than feeder breaker due to:  1- Utility Breaker or 2- Feeder Breakers can fit in standard 20’x20’ bay  Breaker, risers, and switches rated for 2000 amps vs amps  More cable work for CT and trip circuits

20 BENEFITS Huge impact on SAIDI/ CAIDI when dealing with Substation related outages Time/ Labor savings in switching for routine maintenance

21 Questions?