Claim Tracking System
Why was the Claim Tracking System Built? Mandated by the 2002 Legislature Automated Monthly Summary Reports Track and Ensure Construction and Contractor Timeliness on Claims Enhanced Statistical Reporting for Construction Engineering Services Bureau Management Staff and Legislature Standardized MS Word Templates
Automated Monthly Summary Reports
Standardized MS Word Templates Construction Engineering Services Bureau –Response to Notice of Claim –Response to Certified Claim –Extension Request for Response to Certified Claim –Request to Schedule a Mediation Date –Decision from Mediation –Board of Contract Appeals Decision –Lessons Learned Contractor –Notice of Claim –Request for Mediation –Request for Appeal
Accessing the Claim Tracking System MDT Intranet Access the Oracle Menu –Log on to Oracle Select TRNS*PORT Select Claim Tracking System Select Claim Data Entry and Query Form
Claim Data Entry Screen
Claim Data Entry Screen Features List of Values (LOV) –Project Number –Cntl No –EPM Name –Subcontractor –Claim Type –Subject of Claim Type –Bid Item Drop Down List –Claim Status –Proj Type –Board Apl Dec –Mediation Decision Date Calendar –EPM Dates Notice Response Received Cert Claim –DCE Dates Decision Submit Claim Package –CES Dates Received Request for Appeal Received Claim Package –Construction Engineer Dates Mediation Rqst Mediation Meet User Documentation –Available online Lessons Learned –Link to Lessons Learned documents via the comments
List of Values (LOV)
Drop Down List
Date Calendar
Establishing a Claim for a Project To record a claim for a project the user must first determine if the project already exists in the Claim Tracking System Existing Project –Query on the Project –Record a new claim on the existing Project New Project –Record the Project –Record a new claim Query on Project Project Exists Record Claim Yes No Record Project
Query on Project Click on Query Button Query Fields –Project Number –Control Number –Project Description Enter selection criteria Click on Execute Button
Required Fields for Establishing a Claim for a Project Project Information Claim Information –Claim Number – automatically generated –EPM Name –Claim Type –Claim Status –Project Type Dates –Dates will be required as claim progresses through business process –Date counter begins when date is entered
Optional but Recommended Fields for Claims Subcontractor Subject of Claim Type Bid Item Add Time Claim Amount Settled Time Settled Amount Comments
New Claim Established
Notification Links in allow for easy access to application and standardized word templates
Date Logic and Status Notice of Claim Date –01/12/2007 Response to Notice of Claim –Due 14 days from Notice of Claim Date –Warning message will be sent on the 12th day –Overdue message will be sent 14th day
Claim History Screen Users can query and display Claim History Information
Claim History Report
Contractor Details Screen Users can query and display Contractor and associated Claim History
Contractor Details Report Page 1
Contractor Details Report Page 2
Contractor Details Report Page 3
Project Details Screen Users can query and display Project Detail Information
Project Details Report
Claim Query Screen Users can query and display Claim Information for Projects
Claim Query Report Page 1
Claim Query Report Page 2
Claim Query Report Last Page
Message Text Code Table Screen
Distribution Lists Code Table Screen
Claim Types Code Table Screen
Board of Contract Appeals Meeting Dates Code Table
Subject of Claim Types Code Table Screen
Conclusion Training –CES Reviewers in March Production Rollout in April Integration with SiteManager –Claim Documents may attached to Contract in SiteManager as a PDF document