TDC2-TCC2 consolidation status report to EATM EDMS 1410848 October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG.

Slides:



Advertisements
Similar presentations
NA YETS: schedule week by week S. Evrard.
Advertisements

Study report on the TDC2/TCC2 Cabling and Low Voltage activities Ivan Moya Martinez– EN/EL/CF – WP 31st Meeting
Engineering Department EN Cooling and Ventilation issues 1 FUTURE EXPLOITATION OF THE EAST AREA EN-CV Michel OBRECHT.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
PEP-II Ramp Down to a Minimum Maintenance State J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
TDC2/TCC2 consolidation EATM 15/07/2014. EN/EL – DC and control cable identification and cut completed – Old light removal in TDC2 – New AUG installed.
YETS ACTIVITIES SPS-NA S. Girod & S. Evrard on behalf of the SBA team, EATM,
HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
S. Evrard — EN/MEF IEFC Workshop, March 08, 2012 TCC2/TDC2 Shutdown Activities and Consolidation Plans On behalf of the TDC2/TCC2.
Jean-Claude Guillaume ATOP Days – CERN, 5 March 2009 Review of irradiated cables in the SPS Part I – Present strategy Jean-Claude Guillaume Cables and.
Remote manipulations / diagnostics in radioactive areas and handling of radioactive material Workshop, Geneva, Switzerland 6 th May 2013 THE REPLACEMENT.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
2013 NATEF Task Area A-7 Heating, Ventilation, and A/C A. A/C System Diagnosis & Repair B. Refrigeration System Component D & R C. Heating, Ventilation.
EATM12-08 Contribution NA62 Francois Butin, Lau Gatignon / EN-MEF 4 September 2012.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
HiRadMat : report from WG2 – WANF dismantling WG3 - Irradiation Area October S. Evrard 1 WG2&3 meeting organization Preliminary WBS for related.
1 EL Consolidation IEFC Workshop F. Duval on behalf of EN/EL
EN-STI Group meeting 1 st February 2013 EN-STI Group meeting 1 st February 2013 Interventions for LS1 Elodie Macario EN/STI.
TDC2-TCC2 consolidation status report to RSSO EDMS October 14 th, 2014 E. Harrouch, Q. Bouirek, EN-MEF, on behalf of the TDC2/TCC2 WG.
Upgrades and Activities of 13kA EE systems during LS1 Bozhidar Panev TE-MPE-EE
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
N-TOF review HVAC and cooling systems YB-JIG 15/06/07.
Status of North Area Target (TCC2) & prospects EATM 28/07/2015D. Grenier1 Targets (T2, T4, T6 and T10) replaced in 2014 during LS1 (+ 4 spares) Previous.
John Osborne : GS-SEM Civil Engineering 19 May 2009 Report on behalf of CLIC Civil Engineering and Services (CES) WG CTC 19 May 2009 Tunnel Cross Section.
Cooling of NA62 vacuum system November 11 th, 2014 E. Harrouch, EN-MEF, on behalf of the NA62 Vacuum Team.
1 Target Station Design Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory EuroNu Annual Meeting 2012.
East Area, M2, K12 Lau Gatignon / EN-MEF, EATM
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Claudio Bortolin 03/09/2012. SPD (RP analyses required) 1) Pump 17b replacement and leak test 2)Pressure test on the old inlet lines (technicians coming.
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
NA YETS: schedule week by week S. Evrard.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
Update on the Laser Beam Line
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Essential Consolidation Items for LIU-PSB Collection from LIU-PSB WP holders.
IEFC Workshop 9 th March 2012 – Magnet activities in IEF during LS1 – J. Bauche 1 Magnet activities during LS1 J.Bauche, on behalf of the TE/MSC/MNC section.
HIGH RADIATION TO MATERIALS Ans Pardons for the HiRadMat project team IEFC Workshop, March 22, 2011 Outline  The HiRadMat facility – Why, What, When,
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.
TE-CRG Activities D. Delikaris, TE-CRG.
The HiRadMat Facility Outline  Location  Status  WANF dismantling  Beam line  Experimental area  Schedule  Project management S. Evrard – EN/MEF.
HiRadMat : Coordination meeting 02 October S. Evrard 1 News from project team General information : access,... PR532 repair : plans Existing services.
LSC May 2013 Outcome of the magnets tests from the PS, Leir and transfer lines Dominique Bodart.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
LSC 19 th April 2013 – SPS Magnet Test Campaign and Consequences for LS1 1 SPS Magnet Test Campaign and Consequences for LS1 J. Bauche*, P. Catherine,
Tracker cooling plant refurbishment Project status Revised plan Financial impact.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
DTU A VISION OF SUPPORTING NEUTRON CHOPPER ESS PT 1 - BUNKER SYSTEMS Discussion Document.
EBS-1 # COOLANT FLUID EXCHANGE QUICK REFERENCE ATTENTION: Using the Coolant Fluid Exchange requires the FILL and VAC Valves on the SERVICE.
Warm Magnets - LS1 Feedback J. Bauche, on behalf of the TE-MSC-MNC Team.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Repair of MCWV magnets (TT84 – M2). Works on three magnets : MCWV 693, MCWV 697, and MCWV 701 and the associated XABS Cause of the repair : XABS jam into.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
Report Technical Director Storage-Ring-Installation Completed
Update on the PSB Cooling and Ventilation Systems
AD consolidation activities in LS2
EN-HE SPS works during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
Experimental Areas – LS2 planning
Aziz AMAMOU EACM – 21th May 2019
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

TDC2-TCC2 consolidation status report to EATM EDMS October 7 th, 2014 S. EVRARD, EN-MEF, on behalf of the TDC2/TCC2 WG

Outline  Objectives and schedule  Completed activities  Dose management & budget  Conclusions IEFC

Objectives Reduce corrosion of vacuum equipment Replace PVC-insulated cables Re-route cable trays and cables Eradicate water leaks Upgrade ventilation Reduce machine downtime Replace damaged equipment (TCSC, ion pumps, beam instrumentation) Replace obsolete low voltage equipment Install radiation resistant equipment Apply ALARA principle Reduce maintenance time Increase Mean Time Between Failures IEFC

2014 Schedule IEFC L3 ALARA Committee agreement in October EDMS L3 ALARA Committee agreement on May 20th for EN/EL activities. EDMS

Outline  Objectives and schedule  Completed activities  Dose management & budget  Conclusions IEFC

Removal of hot equipment TCSC removed first and brought to B splitter2 magnets and 2 MDLV removed and stored in TDC2 Various beam monitors, BLM and vacuum beam pipes

Cooling and ventilation upgrades IEFC  New chilled water pipes (200 m DN 200)  New cooling coils in all AHU’s  AHU cabinet (40 years old) quite in good shape  Demineralized water circuit: 20 new valves  Challenge: asbestos removal

Civil Engineering IEFC Repair of the TDC2 roof joints: 3 joints have been fitted with a metallic gutter driving water and bitumen to 3 retention boxes. Repair of the mezzanine floor: Resin flooring

Civil Engineering: drain network maintenance IEFC Contractor Vallier checked all the manholes and inspection chambers High pressure cleaning Cleaning water collected and RP checked before disposal Sludge treated as radioactive waste

Civil Engineering: various repairs IEFC New, extension of, repair to water collecting gutters Exchange of all remaining PVC pipes by PE pipes New drain connection

Heavy handling equipment IEFC PR544 maintenance and test Power supply rail (feeding TT20 for transport vehicles) has been removed from TDC2

Magnet upgrade IEFC  One manifold dismounted in order to estimate time needed for future exchange  Cooling flexible replacement completed in TDC2 (joints replaced)  About 120 seals exchanged

Magnet upgrade  Splitter rails and vacuum tank

Cabling activities Re-routing of 5 Cable trays (5x40m) Replacement of 70 DC and 42 control cables Installation of 10 new cables (new requests) IEFC Gangway Average 100µSv/h. Max: 500µSv/h Courtesy of I. Moya

IEFC Cabling activities Control  Power  General services  New situation

Replacement of emergency and conventional light fittings Total 66 emergency light fittings (Not compliant with current standards) Total 338 conventional light fittings Replacement of AUG buttons Replacement of power distribution outlets Installation of cable distribution for vacuum pump heaters IEFC Emergency radiation resistant LED light fitting High Power LEDs hung from walkway TCC2 TDC2 Conventional light fittings Low voltage activities Courtesy of J. Devine

Target refurbishment Preparation in EHN1 cleanroom: Production of new monitors and target boxes for target stations T2, T4, T6 & T10 + spare survey and vacuum & motorisation tests IEFC Courtesy of D.Grenier

T2, T4 and T6 target refurbishment In TCC2: Proximity cabling has been renovated Old monitors and target boxes remotely removed Dedicated shielded container for long term storage in B. 954 and 955. Re-installation of new monitors and target boxes currently in progress IEFC Courtesy of D.Grenier

Upgrade of 12 XTAX tables: Removal of spiral springs (screw protection) Jacks greasing Functional test of each tables Cleaning and maintenance of the base plates Realignment of XTAX4 XTAX table upgrade

Vacuum consolidation New beam pipes (100m) New ion pumps (10 units) Heated collars Vacuum consolidation

New TCSC collimator New beam instrumentation A few new units Maintenance of 40 beam instruments Collimator & beam instrumentation

Outline  Objectives and schedule  Completed activities  Dose management & budget  Conclusions IEFC

Dose management IEFC Operational dose  Cumulated collective dose on = uSv

Maximum individual dose on = 2033 uSv # of participants: 362 Dose management

Budget IEFC

Outline  Objectives and schedule  Completed activities  Dose management & budget  Conclusions IEFC

Conclusions IEFC  The TDC2/TCC2 consolidation activities are successfully completed, within schedule, budget and with no major problem.  The corrective and preventive maintenance recently implemented will reduce corrosion of the vacuum equipment and reduce machine downtime in the future operation of the beam lines.  Individual dose management has been challenging for some groups.

TEAM WORK IEFC

Acknowledgements P. Catherine, M. Dumas, J. Bauche, P. Schwarz, M. Duraffourg, C. Vuitton, M. Hamani, R. Folch, D. Grenier, Z. Ajdid, M. Calviani J. Ferreira, T. Mongelluzzo, P. Chiggato, B. Rio, P. Debernard, R. Morton, A. Dodard, J-C Guillaume, D. Ricci, G. Gros, M. Da Costa, M. Dujardin, J-P. Billon-Grand, J. Pierlot, C. Crombez, S. Delarue, J. Devine, I. Moya, J-F Faure, A. Herve, Y. Pira, C. Theis, H. Vincke, L. Ulrici, Y. Algoet, M. Piccard, L. Gatignon, I. Efthymiopoulos, E. Harrouch, A. Bouvard, Y. Muttoni, C. Magnier, F. Galleazzi, A. Beynel, P. Bestmann, M. Troillet, S. Girod, A. Ebn Rhamoun, J. Etheridge, M. Bonnet, T. Wijnands, A. Pardons, J. Pedersen, Y. Seraphin, J-L. Grenard, C. Bertone, P. Brunero, P. Vallet, S. Deleval, A. Avian, B. Bannister, J. Lehtinen, F. Moro, R. Barrilliere, M. Baudin. IEFC